Bid Tabulations
Letting of
06/15/2011
LA DOTD Headquarters
| Lead Project: 196-04-0026 | |
| Parish: Jefferson Davis | |
| Routes: LA 380, LA 14 | |
| Description: POTTER RD - LA 26 | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT AND RELATED WORK. | |
| Estimated Construction Cost: $2,535,428.75 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 33663 | Glenn Lege Construction Inc | $2,264,268.82 |
| 2 | 00183 | R. E. Heidt Construction Co., Inc. | $2,329,616.40 |
| 3 | 14096 | Bessette Development Corp. | $2,343,229.00 |
| 4 | 34356 | Prairie Contractors Inc. | $2,396,448.55 |
| 5 | 12487 | Diamond B Construction Co., L.L.C. | $2,545,578.47 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Glenn Lege Construction Inc |
- 2 - R. E. Heidt Construction Co., Inc. |
- 3 - Bessette Development Corp. |
- 4 - Prairie Contractors Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 61 | SQYD | 20.00 | 1,220.00 | 10.10 | 616.10 | 10.00 | 610.00 | 10.00 | 610.00 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,617 | CUYD | 16.00 | 25,872.00 | 15.00 | 24,255.00 | 18.00 | 29,106.00 | 20.00 | 32,340.00 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,217 | CUYD | 26.50 | 85,250.50 | 61.50 | 197,845.50 | 70.50 | 226,798.50 | 36.00 | 115,812.00 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 14,087 | TON | 77.50 | 1,091,742.50 | 89.00 | 1,253,743.00 | 84.50 | 1,190,351.50 | 99.40 | 1,400,247.80 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 4,498.4 | TON | 98.50 | 443,092.40 | 86.00 | 386,862.40 | 102.50 | 461,086.00 | 45.00 | 202,428.00 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 95,806 | SQYD | 2.10 | 201,192.60 | 1.25 | 119,757.50 | 1.40 | 134,128.40 | 1.75 | 167,660.50 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,993 | CUYD | 1.00 | -3,993.00 | 1.25 | -4,991.25 | 0.50 | -1,996.50 | 0.01 | -39.93 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 508 | SQYD | 81.00 | 41,148.00 | 86.00 | 43,688.00 | 51.50 | 26,162.00 | 105.00 | 53,340.00 |
| 0009 | 510-02-00100 | Pavement Widening | 1,295.6 | SQYD | 81.00 | 104,943.60 | 92.00 | 119,195.20 | 65.50 | 84,861.80 | 75.00 | 97,170.00 |
| 0010 | 706-01-00100 | Concrete Walk (4" Thick) | 116.8 | SQYD | 60.00 | 7,008.00 | 50.00 | 5,840.00 | 49.50 | 5,781.60 | 50.00 | 5,840.00 |
| 0011 | 706-04-00100 | Handicapped Curb Ramps | 18 | EACH | 1,000.00 | 18,000.00 | 1,206.95 | 21,725.10 | 1,195.00 | 21,510.00 | 700.00 | 12,600.00 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 35,500.00 | 35,500.00 | 5,500.00 | 5,500.00 | 5,371.00 | 5,371.00 | 15,000.00 | 15,000.00 |
| 0013 | 713-02-00400 | Temporary Pavement Markings (12" Width) | 70 | LNFT | 0.50 | 35.00 | 0.46 | 32.20 | 0.30 | 21.00 | 0.50 | 35.00 |
| 0014 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 523 | LNFT | 0.98 | 512.54 | 0.91 | 475.93 | 0.75 | 392.25 | 0.01 | 5.23 |
| 0015 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 16.258 | MILE | 700.00 | 11,380.60 | 212.58 | 3,456.13 | 153.75 | 2,499.67 | 400.00 | 6,503.20 |
| 0016 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 15.136 | MILE | 327.24 | 4,953.10 | 303.00 | 4,586.21 | 475.00 | 7,189.60 | 0.01 | 0.15 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 39.523 | MILE | 545.40 | 21,555.84 | 505.00 | 19,959.12 | 550.00 | 21,737.65 | 0.01 | 0.40 |
| 0018 | 717-01-00100 | Seeding | 91 | LB | 9.27 | 843.57 | 12.12 | 1,102.92 | 8.50 | 773.50 | 10.00 | 910.00 |
| 0019 | 718-01-00100 | Fertilizer | 1,462 | LB | 0.66 | 964.92 | 1.01 | 1,476.62 | 0.60 | 877.20 | 1.00 | 1,462.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 53,200.00 | 53,200.00 | 20,600.00 | 20,600.00 | 27,160.18 | 27,160.18 | 186,000.00 | 186,000.00 |
| 0021 | 729-16-00200 | Object Marker Assembly (Type 2) | 41 | EACH | 54.54 | 2,236.14 | 75.75 | 3,105.75 | 65.00 | 2,665.00 | 50.00 | 2,050.00 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,257 | EACH | 4.91 | 6,171.87 | 4.55 | 5,719.35 | 5.25 | 6,599.25 | 5.00 | 6,285.00 |
| 0023 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 70 | LNFT | 3.27 | 228.90 | 3.03 | 212.10 | 2.50 | 175.00 | 10.00 | 700.00 |
| 0024 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 512 | LNFT | 6.54 | 3,348.48 | 6.06 | 3,102.72 | 5.00 | 2,560.00 | 6.00 | 3,072.00 |
| 0025 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 20.872 | MILE | 2,836.08 | 59,194.66 | 2,626.00 | 54,809.87 | 2,650.00 | 55,310.80 | 2,600.00 | 54,267.20 |
| 0026 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 8.24 | MILE | 872.64 | 7,190.55 | 808.00 | 6,657.92 | 850.00 | 7,004.00 | 1,000.00 | 8,240.00 |
| 0027 | 732-05-00100 | Removal of Existing Markings | 1.884 | MILE | 4,363.20 | 8,220.27 | 4,040.00 | 7,611.36 | 3,000.00 | 5,652.00 | 3,000.00 | 5,652.00 |
| 0028 | 735-01-00100 | Mailboxes | 124 | EACH | 1.00 | 124.00 | 1.01 | 125.24 | 1.00 | 124.00 | 2.00 | 248.00 |
| 0029 | 735-02-00100 | Mailbox Supports (Single) | 119 | EACH | 120.00 | 14,280.00 | 109.08 | 12,980.52 | 105.00 | 12,495.00 | 120.00 | 14,280.00 |
| 0030 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 137.00 | 685.00 | 166.65 | 833.25 | 120.00 | 600.00 | 250.00 | 1,250.00 |
| 0031 | 740-01-00100 | Construction Layout | 1 | LUMP | 16,665.00 | 16,665.00 | 7,000.00 | 7,000.00 | 3,909.00 | 3,909.00 | 100.00 | 100.00 |
| 0033 | NS-507-00003 | Clean and Seal Ran Cracks in Asph Conc Pave (Hot Poured) | 238 | LNFT | 6.31 | 1,501.78 | 7.28 | 1,732.64 | 7.20 | 1,713.60 | 10.00 | 2,380.00 |
| CONTRACTOR TOTAL | 2,264,268.82 | 2,329,616.40 | 2,343,229.00 | 2,396,448.55 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Diamond B Construction Co., L.L.C. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 61 | SQYD | 45.81 | 2,794.41 |
| 0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,617 | CUYD | 27.13 | 43,869.21 |
| 0003 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,217 | CUYD | 31.28 | 100,627.76 |
| 0004 | 502-01-00100 | Superpave Asphaltic Concrete | 14,087 | TON | 94.35 | 1,329,108.45 |
| 0005 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 4,498.4 | TON | 115.12 | 517,855.81 |
| 0006 | 509-01-00100 | Cold Planing Asphaltic Pavement | 95,806 | SQYD | 1.61 | 154,247.66 |
| 0007 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -3,993 | CUYD | 0.10 | -399.30 |
| 0008 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 508 | SQYD | 112.20 | 56,997.60 |
| 0009 | 510-02-00100 | Pavement Widening | 1,295.6 | SQYD | 77.57 | 100,499.69 |
| 0010 | 706-01-00100 | Concrete Walk (4" Thick) | 116.8 | SQYD | 55.64 | 6,498.75 |
| 0011 | 706-04-00100 | Handicapped Curb Ramps | 18 | EACH | 1,343.34 | 24,180.12 |
| 0012 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 16,002.12 | 16,002.12 |
| 0013 | 713-02-00400 | Temporary Pavement Markings (12" Width) | 70 | LNFT | 0.34 | 23.80 |
| 0014 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 523 | LNFT | 0.84 | 439.32 |
| 0015 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 16.258 | MILE | 188.62 | 3,066.58 |
| 0016 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 15.136 | MILE | 533.96 | 8,082.02 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 39.523 | MILE | 618.27 | 24,435.89 |
| 0018 | 717-01-00100 | Seeding | 91 | LB | 9.56 | 869.96 |
| 0019 | 718-01-00100 | Fertilizer | 1,462 | LB | 0.67 | 979.54 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 41,417.90 | 41,417.90 |
| 0021 | 729-16-00200 | Object Marker Assembly (Type 2) | 41 | EACH | 73.07 | 2,995.87 |
| 0022 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,257 | EACH | 5.90 | 7,416.30 |
| 0023 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 70 | LNFT | 2.81 | 196.70 |
| 0024 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 512 | LNFT | 5.62 | 2,877.44 |
| 0025 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 20.872 | MILE | 2,978.95 | 62,176.64 |
| 0026 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 8.24 | MILE | 955.51 | 7,873.40 |
| 0027 | 732-05-00100 | Removal of Existing Markings | 1.884 | MILE | 3,372.40 | 6,353.60 |
| 0028 | 735-01-00100 | Mailboxes | 124 | EACH | 1.12 | 138.88 |
| 0029 | 735-02-00100 | Mailbox Supports (Single) | 119 | EACH | 118.03 | 14,045.57 |
| 0030 | 735-03-00100 | Mailbox Supports (Double) | 5 | EACH | 134.90 | 674.50 |
| 0031 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,306.86 | 7,306.86 |
| 0033 | NS-507-00003 | Clean and Seal Ran Cracks in Asph Conc Pave (Hot Poured) | 238 | LNFT | 8.09 | 1,925.42 |
| CONTRACTOR TOTAL | 2,545,578.47 | |||||