LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 195-04-0021
Parish: Calcasieu
Routes: LA 385, LA 1138-2
Description: LEFT TURN LANES ON LA 385 AT LA 1138-2 IN LAKE CHARLES
Type Const: CLEARING AND GRUBBING, GRADING, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, COLD PLANING ASPHALTIC PAVEMENT, PORTLAND CEMENT CONCRETE PAVEMENT, SIGNALIZATION, AND RELATED WORK
Estimated Construction Cost: $816,900.56


RankLicenseBidderConstruction Bid
1 36384 John Bailey, Inc. $962,444.73
2 50078 Fenton Excavating & Const. Inc. $968,203.31
3 39462 Jb James Construction Llc $978,942.46
4 52550 Gibbs & Register Inc $1,111,806.23


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
John Bailey, Inc.
- 2 -
Fenton Excavating & Const. Inc.
- 3 -
Jb James Construction Llc
- 4 -
Gibbs & Register Inc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      lump 10,000.00 10,000.00 5,900.00 5,900.00 90,000.00 90,000.00 5,000.00 5,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      lump 15,000.00 15,000.00 2,950.00 2,950.00 32,000.00 32,000.00 13,500.00 13,500.00
0003 202-02-00010 Removal of Sprinkler System (Rt. of Station 11+469) 1      each 2,500.00 2,500.00 1,336.23 1,336.23 1.00 1.00 1,200.00 1,200.00
0004 202-02-00010 Removal of Sign and Slab Foundation (6' X 6' Metal Sign, Rt. of Station 99+985) 1      each 1,000.00 1,000.00 2,723.26 2,723.26 1.00 1.00 3,000.00 3,000.00
0005 202-02-00010 Removal of Sign and Foundation (2.5' X 3' Metal Sign, Rt. of Station 11+485) 1      each 500.00 500.00 1,386.80 1,386.80 1.00 1.00 2,500.00 2,500.00
0006 202-02-00010 Removal of Sign, Brick Planter and Slab Foundation (5' X 5' Brick Planter with Sign Standard and Sign, Rt. of Station 99+985) 1      each 1,500.00 1,500.00 2,950.00 2,950.00 1.00 1.00 3,000.00 3,000.00
0007 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+952) 1      each 1,000.00 1,000.00 1,386.80 1,386.80 1.00 1.00 1,500.00 1,500.00
0008 202-02-00010 Removal of Sign and Slab Foundation (8' X 15' Metal Sign, Rt. of Station 100+015) 1      each 1,000.00 1,000.00 2,873.30 2,873.30 1.00 1.00 5,000.00 5,000.00
0009 202-02-00010 Removal of Fence and Slab Foundation (2' X 2' Brick Pillars with 6' Metal Rails, 165 ln. ft., Rt. of Station 99+948) 1      each 5,000.00 5,000.00 8,177.40 8,177.40 1.00 1.00 3,000.00 3,000.00
0010 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+995) 1      each 1,000.00 1,000.00 748.18 748.18 1.00 1.00 1,000.00 1,000.00
0011 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+989) 1      each 1,000.00 1,000.00 748.18 748.18 1.00 1.00 1,000.00 1,000.00
0012 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+982) 1      each 1,000.00 1,000.00 748.18 748.18 1.00 1.00 1,000.00 1,000.00
0013 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+964) 1      each 1,000.00 1,000.00 748.18 748.18 1.00 1.00 1,000.00 1,000.00
0014 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+970) 1      each 1,000.00 1,000.00 748.18 748.18 1.00 1.00 1,000.00 1,000.00
0015 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+976) 1      each 1,000.00 1,000.00 748.18 748.18 1.00 1.00 1,000.00 1,000.00
0016 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+958) 1      each 1,000.00 1,000.00 748.18 748.18 1.00 1.00 1,000.00 1,000.00
0017 202-02-00010 Removal of Fence and Slab Foundation (2" X 104' Pipe Railing, Lt. of Station 99+946) 1      each 4,000.00 4,000.00 1,436.53 1,436.53 1.00 1.00 3,000.00 3,000.00
0018 202-02-00010 Removal of Flag Pole and Slab Foundation (3" X 20', Lt. of Station 99+946) 1      each 1,000.00 1,000.00 1,416.30 1,416.30 1.00 1.00 1,000.00 1,000.00
0019 202-02-06100 Removal of Concrete Walks and Drives 1,129      sq m 18.00 20,322.00 13.90 15,693.10 9.00 10,161.00 15.00 16,935.00
0020 202-02-06140 Removal of Curbs (Concrete) 632.7    ln m 32.00 20,246.40 13.85 8,762.90 10.00 6,327.00 25.00 15,817.50
0021 202-05-00100 Excavation, Disposal and Backfilling of Contaminated Soil 235      cu m 105.00 24,675.00 160.40 37,694.00 140.00 32,900.00 33.00 7,755.00
0022 203-05-00100 Excavation and Embankment 1      lump 50,000.00 50,000.00 69,139.81 69,139.81 80,000.00 80,000.00 12,000.00 12,000.00
0023 204-02-00100 Temporary Hay or Straw Bales 32      each 25.00 800.00 11.80 377.60 12.00 384.00 35.00 1,120.00
0024 204-06-00100 Temporary Silt Fencing 44      ln m 13.25 583.00 5.90 259.60 25.00 1,100.00 36.00 1,584.00
0025 302-02-03000 Class II Base Course (200 mm Thick) 1,155.6    sq m 35.00 40,446.00 28.20 32,587.92 25.00 28,890.00 28.00 32,356.80
0026 304-05-00100 Lime Treatment (Type E) 16      Mg 551.00 8,816.00 295.00 4,720.00 450.00 7,200.00 3,100.00 49,600.00
0027 305-01-01000 Subgrade Layer (150 mm Thick) 385.2    sq m 54.00 20,800.80 26.30 10,130.76 14.00 5,392.80 23.00 8,859.60
0028 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 67.5    cu m 110.00 7,425.00 83.99 5,669.33 90.00 6,075.00 70.00 4,725.00
0029 502-01-00100 Superpave Asphaltic Concrete 570.932  Mg 105.00 59,947.86 180.00 102,767.76 150.00 85,639.80 190.00 108,477.08
0030 509-01-00100 Cold Planing Asphaltic Pavement 4,070      sq m 5.00 20,350.00 8.65 35,205.50 4.00 16,280.00 3.00 12,210.00
0031 509-02-00100 Contractor Retained Reclaimed Asphaltic Pavement -203.5    cu m 0.01 -2.04 1.00 -203.50 0.01 -2.04 1.00 -203.50
0032 601-01-00100 Portland Cement Concrete Pavement (200 mm Thick) 789      sq m 107.50 84,817.50 88.00 69,432.00 90.00 71,010.00 190.00 149,910.00
0033 601-01-00300 Portland Cement Concrete Pavement (225 mm Thick) 220.2    sq m 115.00 25,323.00 91.00 20,038.20 95.00 20,919.00 200.00 44,040.00
0034 701-03-01020 Storm Drain Pipe (450 mm RCP/PP) 49.2    ln m 205.00 10,086.00 493.15 24,262.98 170.00 8,364.00 540.00 26,568.00
0035 702-03-00500 Catch Basins (CB-06(M)) 8      each 4,000.00 32,000.00 4,060.91 32,487.28 3,200.00 25,600.00 4,300.00 34,400.00
0036 705-06-00200 Chain Link Fence (1500 mm Height) 90      ln m 80.00 7,200.00 70.80 6,372.00 68.00 6,120.00 80.00 7,200.00
0037 706-01-00100 Concrete Walk (100 mm Thick) 305.4    sq m 70.00 21,378.00 61.75 18,858.45 60.00 18,324.00 44.00 13,437.60
0038 706-02-00200 Concrete Drive (150 mm Thick) 245.6    sq m 85.00 20,876.00 70.30 17,265.68 68.00 16,700.80 65.00 15,964.00
0039 706-04-00100 Handicapped Curb Ramps 3      each 1,500.00 4,500.00 1,818.13 5,454.39 600.00 1,800.00 1,500.00 4,500.00
0040 707-01-00100 Concrete Curb 120.1    ln m 82.00 9,848.20 56.35 6,767.64 28.00 3,362.80 122.00 14,652.20
0041 707-03-00100 Combination Concrete Curb and Gutter 395.7    ln m 180.50 71,423.85 89.41 35,379.54 95.00 37,591.50 230.00 91,011.00
0042 708-01-00100 Right-of-Way Monument 11      each 300.00 3,300.00 590.00 6,490.00 120.00 1,320.00 525.00 5,775.00
0043 713-01-00100 Temporary Signs and Barricades 1      lump 75,000.00 75,000.00 42,000.00 42,000.00 80,000.00 80,000.00 40,000.00 40,000.00
0044 714-01-00100 Slab Sodding (Bermuda Grass) 43      sq m 30.00 1,290.00 44.16 1,898.88 20.00 860.00 21.00 903.00
0045 717-01-00100 Seeding 20      kg 50.00 1,000.00 47.20 944.00 40.00 800.00 41.00 820.00
0046 718-01-00100 Fertilizer 20      kg 15.00 300.00 5.90 118.00 5.00 100.00 5.25 105.00
0047 722-01-00100 Project Site Laboratory 1      each 20,000.00 20,000.00 9,440.00 9,440.00 1,000.00 1,000.00 9,000.00 9,000.00
0048 726-01-00100 Bedding Material 10.3    cu m 150.00 1,545.00 76.87 791.76 90.00 927.00 160.00 1,648.00
0049 727-01-00100 Mobilization 1      lump 65,000.00 65,000.00 108,000.00 108,000.00 94,000.00 94,000.00 109,300.00 109,300.00
0050 729-01-00100 Sign (Type A) 7.83   sq m 600.00 4,698.00 590.00 4,619.70 130.00 1,017.90 145.00 1,135.35
0051 731-02-00100 Reflectorized Raised Pavement Markers 254      each 6.00 1,524.00 5.90 1,498.60 5.00 1,270.00 5.25 1,333.50
0052 732-01-01000 Plastic Pavement Striping (100 mm Width) (Thermoplastic 90 mil) 1,737      ln m 1.92 3,335.04 1.89 3,282.93 3.30 5,732.10 3.40 5,905.80
0053 732-01-01020 Plastic Pavement Striping (150 mm Width) (Thermoplastic 90 mil) 84      ln m 2.88 241.92 2.83 237.72 6.60 554.40 6.70 562.80
0054 732-01-01040 Plastic Pavement Striping (200 mm Width) (Thermoplastic 90 mil) 151      ln m 6.00 906.00 5.90 890.90 6.60 996.60 6.70 1,011.70
0055 732-01-01080 Plastic Pavement Striping (600 mm Width) (Thermoplastic 90 mil) 100      ln m 12.00 1,200.00 11.80 1,180.00 20.00 2,000.00 20.00 2,000.00
0056 732-01-02080 Plastic Pavement Striping (600 mm Width) (Thermoplastic 125 mil) 46.8    ln m 14.50 678.60 14.16 662.69 20.00 936.00 20.00 936.00
0057 732-04-01080 Plastic Pavement Legends and Symbols (Arrow - Left Turn) 12      each 204.00 2,448.00 200.60 2,407.20 300.00 3,600.00 315.00 3,780.00
0058 732-04-15020 Plastic Pavement Legends and Symbols (ONLY) 6      each 228.00 1,368.00 224.20 1,345.20 300.00 1,800.00 525.00 3,150.00
0059 736-01-00100 Trenching and Backfilling 56      ln m 16.20 907.20 15.93 892.08 10.00 560.00 11.50 644.00
0060 736-03-00200 Jacked or Bored Conduit (50 mm HPDE, Sch 80) 55      ln m 42.36 2,329.80 41.65 2,290.75 40.00 2,200.00 42.00 2,310.00
0061 736-03-00300 Jacked or Bored Conduit (75 mm HPDE, Sch 80) 80      ln m 57.72 4,617.60 56.76 4,540.80 50.00 4,000.00 56.00 4,480.00
0062 736-04-04140 Signal Support (12 m Single Mast Arm) 2      each 11,334.00 22,668.00 10,083.10 20,166.20 10,000.00 20,000.00 13,000.00 26,000.00
0063 736-04-04160 Signal Support (13.5 m Single Mast Arm) 1      each 11,796.00 11,796.00 10,596.40 10,596.40 11,000.00 11,000.00 13,000.00 13,000.00
0064 736-04-04180 Signal Support (15 m Single Mast Arm) 1      each 13,134.00 13,134.00 11,617.10 11,617.10 12,000.00 12,000.00 15,000.00 15,000.00
0065 736-05-02000 Signal Heads (3 Section, 300 mm Led Lens, R, Y, G) 8      each 1,218.00 9,744.00 1,109.20 8,873.60 850.00 6,800.00 1,200.00 9,600.00
0066 736-05-02020 Signal Heads (3 Section, 300 mm Led Lens, R, LT, Y, LT. G) 4      each 1,218.00 4,872.00 1,109.20 4,436.80 900.00 3,600.00 1,000.00 4,000.00
0067 736-05-04000 Signal Heads (5 Section, 300 mm Led Lens, R, LT. Y, Y, LT. G, G) 2      each 1,866.00 3,732.00 1,740.50 3,481.00 1,300.00 2,600.00 1,800.00 3,600.00
0068 736-06-00100 Signal Service 1      each 3,138.00 3,138.00 2,932.30 2,932.30 850.00 850.00 1,200.00 1,200.00
0069 736-08-01000 Signal Controller (TS-2, Type 1; Type 6 Cabinet) 1      each 27,732.00 27,732.00 25,499.80 25,499.80 25,000.00 25,000.00 30,000.00 30,000.00
0070 736-10-00300 Underground Junction Box (Type F) 6      each 720.00 4,320.00 649.00 3,894.00 420.00 2,520.00 500.00 3,000.00
0071 736-10-00500 Underground Junction Box (Type H) 1      each 1,278.00 1,278.00 1,180.00 1,180.00 850.00 850.00 1,000.00 1,000.00
0072 736-11-00200 Conduit (25 mm HDPE, Schedule 80) 28      ln m 3.60 100.80 3.42 95.76 7.50 210.00 8.00 224.00
0073 736-11-00300 Conduit (50 mm HDPE, Schedule 80) 10      ln m 6.00 60.00 5.37 53.70 9.00 90.00 9.00 90.00
0074 736-11-00400 Conduit (75 mm HDPE, Schedule 80) 18      ln m 9.30 167.40 8.20 147.60 14.00 252.00 16.00 288.00
0075 736-12-02000 Conductor (3c, 6 gauge / #6 awg) 83      ln m 12.60 1,045.80 11.68 969.44 12.00 996.00 15.00 1,245.00
0076 736-12-04000 Conductor (6c, #14 awg) 50      ln m 6.00 300.00 5.61 280.50 7.00 350.00 9.00 450.00
0077 736-12-06000 Conductor (10c, #14 awg) 420      ln m 8.64 3,628.80 7.79 3,271.80 7.50 3,150.00 9.00 3,780.00
0078 740-01-00100 Construction Layout 1      lump 5,000.00 5,000.00 14,160.00 14,160.00 20,000.00 20,000.00 12,000.00 12,000.00
0079 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 32,200      mmlm 0.25 8,050.00 0.30 9,660.00 0.20 6,440.00 0.30 9,660.00
0080 NS-602-00001 Milling Concrete Pavement 577.8    sq m 15.00 8,667.00 29.50 17,045.10 36.00 20,800.80 16.00 9,244.80
0081 NS-736-00005 Video Detection Cabinet Components 1      each 9,078.00 9,078.00 8,100.70 8,100.70 8,000.00 8,000.00 10,000.00 10,000.00
0082 NS-736-00006 Video Detection Camera 4      each 2,220.00 8,880.00 1,121.00 4,484.00 2,000.00 8,000.00 2,500.00 10,000.00
0083 NS-736-00007 Video Detection Training 1      lump 1.20 1.20 1.00 1.00 4.00 4.00 5.00 5.00
0084 NS-MSC-00120 Drainage Structure Convert Catch Basin to R-CB-11 8      each 1,500.00 12,000.00 3,353.56 26,828.48 1,200.00 9,600.00 4,000.00 32,000.00
                         
    CONTRACTOR TOTAL       962,444.73   968,203.31   978,942.46   1,111,806.23