Bid Tabulations
Letting of
02/24/2010
LA DOTD Headquarters
| Lead Project: 186-30-0009 | |
| Parish: Tensas | |
| Routes: LA 573 | |
| Description: COOTER POINT - 4 MILES NORTH | |
| Type Const: IN-PLACE CEMENT TREATED BASE COURSE, ASPHALTIC SURFACE TREATMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $967,520.07 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 02268 | Soil Stabilizers, Inc. | $817,697.98 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $953,102.90 |
| 3 | 14422 | T. L. Wallace Construction, Inc. | $977,962.00 |
| 4 | 39580 | Gerace Construction Llc | $1,034,103.00 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Soil Stabilizers, Inc. |
- 2 - Gilchrist Construction Co. LLC |
- 3 - T. L. Wallace Construction, Inc. |
- 4 - Gerace Construction Llc |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 1.11 | SQYD | 75.00 | 83.25 | 100.00 | 111.00 | 1,000.00 | 1,110.00 | 500.00 | 555.00 |
| 0002 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 7,529 | CUYD | 15.00 | 112,935.00 | 21.00 | 158,109.00 | 18.00 | 135,522.00 | 16.00 | 120,464.00 |
| 0003 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 47,432 | SQYD | 7.10 | 336,767.20 | 7.00 | 332,024.00 | 8.25 | 391,314.00 | 8.50 | 403,172.00 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 29.7 | TON | 200.00 | 5,940.00 | 275.00 | 8,167.50 | 200.00 | 5,940.00 | 300.00 | 8,910.00 |
| 0005 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 63,270 | GAL | 3.27 | 206,892.90 | 3.25 | 205,627.50 | 3.20 | 202,464.00 | 3.50 | 221,445.00 |
| 0006 | 507-02-00200 | Aggregate (S2) (Crushed Stone Only) | 93,044 | SQYD | 0.67 | 62,339.48 | 0.95 | 88,391.80 | 0.85 | 79,087.40 | 1.00 | 93,044.00 |
| 0007 | 507-02-00300 | Aggregate (S3) (Crushed Stone Only) | 93,044 | SQYD | 0.50 | 46,522.00 | 0.75 | 69,783.00 | 0.70 | 65,130.80 | 0.75 | 69,783.00 |
| 0008 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 | 22,000.00 | 22,000.00 | 10,000.00 | 10,000.00 |
| 0009 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 1,982 | EACH | 1.50 | 2,973.00 | 1.15 | 2,279.30 | 1.25 | 2,477.50 | 2.00 | 3,964.00 |
| 0010 | 727-01-00100 | Mobilization | 1 | LUMP | 15,000.00 | 15,000.00 | 50,000.00 | 50,000.00 | 37,500.00 | 37,500.00 | 60,000.00 | 60,000.00 |
| 0011 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,451 | EACH | 3.25 | 4,715.75 | 5.80 | 8,415.80 | 4.50 | 6,529.50 | 6.00 | 8,706.00 |
| 0012 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 7.392 | MILE | 1,200.00 | 8,870.40 | 1,600.00 | 11,827.20 | 1,150.00 | 8,500.80 | 1,500.00 | 11,088.00 |
| 0013 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 5.765 | MILE | 600.00 | 3,459.00 | 720.00 | 4,150.80 | 400.00 | 2,306.00 | 800.00 | 4,612.00 |
| 0014 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 | 17,000.00 | 17,000.00 | 18,000.00 | 18,000.00 |
| 0015 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 120 | INLF | 10.00 | 1,200.00 | 1.80 | 216.00 | 9.00 | 1,080.00 | 3.00 | 360.00 |
| CONTRACTOR TOTAL | 817,697.98 | 953,102.90 | 977,962.00 | 1,034,103.00 | ||||||||