LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 186-30-0009
Parish: Tensas
Routes: LA 573
Description: COOTER POINT - 4 MILES NORTH
Type Const: IN-PLACE CEMENT TREATED BASE COURSE, ASPHALTIC SURFACE TREATMENT, AND RELATED WORK.
Estimated Construction Cost: $967,520.07


RankLicenseBidderConstruction Bid
1 02268 Soil Stabilizers, Inc. $817,697.98
2 12312 Gilchrist Construction Co. LLC $953,102.90
3 14422 T. L. Wallace Construction, Inc. $977,962.00
4 39580 Gerace Construction Llc $1,034,103.00


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Soil Stabilizers, Inc.
- 2 -
Gilchrist Construction Co. LLC
- 3 -
T. L. Wallace Construction, Inc.
- 4 -
Gerace Construction Llc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 202-02-06100 Removal of Concrete Walks and Drives 1.11   SQYD 75.00 83.25 100.00 111.00 1,000.00 1,110.00 500.00 555.00
0002 203-07-00200 Borrow (Vehicular Measurement) (Selected Soils) 7,529      CUYD 15.00 112,935.00 21.00 158,109.00 18.00 135,522.00 16.00 120,464.00
0003 308-01-00100 In-Place Cement Treated Base Course (12" Thick) 47,432      SQYD 7.10 336,767.20 7.00 332,024.00 8.25 391,314.00 8.50 403,172.00
0004 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 29.7    TON 200.00 5,940.00 275.00 8,167.50 200.00 5,940.00 300.00 8,910.00
0005 507-01-00100 Asphaltic Material (CRS-2P Emulsion) 63,270      GAL 3.27 206,892.90 3.25 205,627.50 3.20 202,464.00 3.50 221,445.00
0006 507-02-00200 Aggregate (S2) (Crushed Stone Only) 93,044      SQYD 0.67 62,339.48 0.95 88,391.80 0.85 79,087.40 1.00 93,044.00
0007 507-02-00300 Aggregate (S3) (Crushed Stone Only) 93,044      SQYD 0.50 46,522.00 0.75 69,783.00 0.70 65,130.80 0.75 69,783.00
0008 713-01-00100 Temporary Signs and Barricades 1      LUMP 5,000.00 5,000.00 10,000.00 10,000.00 22,000.00 22,000.00 10,000.00 10,000.00
0009 713-06-00200 Temporary Reflectorized Raised Pavement Markers (Tabs) 1,982      EACH 1.50 2,973.00 1.15 2,279.30 1.25 2,477.50 2.00 3,964.00
0010 727-01-00100 Mobilization 1      LUMP 15,000.00 15,000.00 50,000.00 50,000.00 37,500.00 37,500.00 60,000.00 60,000.00
0011 731-02-00100 Reflectorized Raised Pavement Markers 1,451      EACH 3.25 4,715.75 5.80 8,415.80 4.50 6,529.50 6.00 8,706.00
0012 732-02-01000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) 7.392  MILE 1,200.00 8,870.40 1,600.00 11,827.20 1,150.00 8,500.80 1,500.00 11,088.00
0013 732-03-01000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) 5.765  MILE 600.00 3,459.00 720.00 4,150.80 400.00 2,306.00 800.00 4,612.00
0014 740-01-00100 Construction Layout 1      LUMP 5,000.00 5,000.00 4,000.00 4,000.00 17,000.00 17,000.00 18,000.00 18,000.00
0015 NS-600-00220 Saw Cutting Portland Cement Concrete Pavement 120      INLF 10.00 1,200.00 1.80 216.00 9.00 1,080.00 3.00 360.00
                         
    CONTRACTOR TOTAL       817,697.98   953,102.90   977,962.00   1,034,103.00
 Free Tourist Map  
The La DOTD Headquarters Building is located at 1201 Capitol Access Road, Baton Rouge, LA, 70802. Telephone: (225) 379-1232.
Please send us your Comments or Suggestions.