Bid Tabulations
Letting of
12/16/2009
LA DOTD Headquarters
| Lead Project: 178-02-0021 | |
| Parish: Concordia | |
| Routes: LA 129 | |
| Description: WORKINGER BAYOU - US 84 | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE PAVEMENT, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, PAVEMENT PATCHING, AND RELATED WORK | |
| Estimated Construction Cost: $1,768,392.77 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 05789 | D & J Construction Co., Inc. | $1,732,968.17 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $1,870,906.49 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $1,875,338.90 |
| 4 | 02214 | W. E. Blain & Sons, Inc. | $1,898,087.11 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - D & J Construction Co., Inc. |
- 2 - Gilchrist Construction Co. LLC |
- 3 - Diamond B Construction Co., L.L.C. |
- 4 - W. E. Blain & Sons, Inc. |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 665 | LNFT | 6.00 | 3,990.00 | 10.00 | 6,650.00 | 7.00 | 4,655.00 | 3.00 | 1,995.00 |
| 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) STATIONS 251+30 AND 292+45 | 24 | LNFT | 10.00 | 240.00 | 24.00 | 576.00 | 84.00 | 2,016.00 | 60.00 | 1,440.00 |
| 0003 | 202-02-32180 | Removal of Pipe Headwalls | 4 | EACH | 500.00 | 2,000.00 | 250.00 | 1,000.00 | 1,100.00 | 4,400.00 | 470.00 | 1,880.00 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 971 | CUYD | 24.00 | 23,304.00 | 15.00 | 14,565.00 | 25.00 | 24,275.00 | 24.30 | 23,595.30 |
| 0005 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 2,064 | CUYD | 24.00 | 49,536.00 | 45.00 | 92,880.00 | 68.00 | 140,352.00 | 23.50 | 48,504.00 |
| 0006 | 502-01-00100 | Superpave Asphaltic Concrete | 10,872.9 | TON | 79.00 | 858,959.10 | 78.00 | 848,086.20 | 72.00 | 782,848.80 | 78.60 | 854,609.94 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 807.1 | TON | 79.00 | 63,760.90 | 185.00 | 149,313.50 | 150.00 | 121,065.00 | 140.00 | 112,994.00 |
| 0008 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 62,602 | GAL | 2.80 | 175,285.60 | 3.20 | 200,326.40 | 3.00 | 187,806.00 | 3.25 | 203,456.50 |
| 0009 | 507-02-00200 | Aggregate (S2) | 92,061 | SQYD | 1.00 | 92,061.00 | 1.00 | 92,061.00 | 1.10 | 101,267.10 | 0.85 | 78,251.85 |
| 0010 | 507-02-00300 | Aggregate (S3) | 92,061 | SQYD | 0.81 | 74,569.41 | 0.85 | 78,251.85 | 0.90 | 82,854.90 | 0.65 | 59,839.65 |
| 0011 | 509-01-00100 | Cold Planing Asphaltic Pavement | 94,303 | SQYD | 1.40 | 132,024.20 | 1.00 | 94,303.00 | 1.10 | 103,733.30 | 1.25 | 117,878.75 |
| 0012 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -1,962 | CUYD | 0.10 | -196.20 | 0.10 | -196.20 | 22.50 | -44,145.00 | 0.01 | -19.62 |
| 0013 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 491 | SQYD | 100.00 | 49,100.00 | 110.00 | 54,010.00 | 70.00 | 34,370.00 | 116.00 | 56,956.00 |
| 0014 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 96 | LNFT | 100.00 | 9,600.00 | 120.00 | 11,520.00 | 110.00 | 10,560.00 | 120.00 | 11,520.00 |
| 0015 | 701-15-00100 | Concrete Collar | 6 | EACH | 600.00 | 3,600.00 | 825.00 | 4,950.00 | 850.00 | 5,100.00 | 1,025.00 | 6,150.00 |
| 0016 | 704-03-00100 | Blocked Out Guard Rail | 300 | LNFT | 18.00 | 5,400.00 | 19.00 | 5,700.00 | 18.00 | 5,400.00 | 17.00 | 5,100.00 |
| 0017 | 704-07-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 87.5 | LNFT | 43.00 | 3,762.50 | 45.00 | 3,937.50 | 45.00 | 3,937.50 | 35.00 | 3,062.50 |
| 0018 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 191.7 | LNFT | 53.00 | 10,160.10 | 56.00 | 10,735.20 | 55.00 | 10,543.50 | 62.00 | 11,885.40 |
| 0019 | 704-11-00100 | Guard Rail End Treatment (Flared) | 3 | EACH | 2,000.00 | 6,000.00 | 2,100.00 | 6,300.00 | 2,200.00 | 6,600.00 | 2,100.00 | 6,300.00 |
| 0020 | 704-11-00200 | Guard Rail End Treatment (Tangent) | 4 | EACH | 2,300.00 | 9,200.00 | 2,500.00 | 10,000.00 | 2,200.00 | 8,800.00 | 2,500.00 | 10,000.00 |
| 0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 12,000.00 | 12,000.00 | 5,600.00 | 5,600.00 | 15,000.00 | 15,000.00 | 30,000.00 | 30,000.00 |
| 0022 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 14.344 | MILE | 225.00 | 3,227.40 | 300.00 | 4,303.20 | 150.00 | 2,151.60 | 335.00 | 4,805.24 |
| 0023 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 25.673 | MILE | 200.00 | 5,134.60 | 1.00 | 25.67 | 350.00 | 8,985.55 | 350.00 | 8,985.55 |
| 0024 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 62.621 | MILE | 1.00 | 62.62 | 1.00 | 62.62 | 650.00 | 40,703.65 | 650.00 | 40,703.65 |
| 0025 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 1,896 | EACH | 1.75 | 3,318.00 | 1.50 | 2,844.00 | 2.00 | 3,792.00 | 1.60 | 3,033.60 |
| 0026 | 716-01-00100 | Mulch (Vegetative) | 0.4 | TON | 3,000.00 | 1,200.00 | 3,200.00 | 1,280.00 | 3,100.00 | 1,240.00 | 1,500.00 | 600.00 |
| 0027 | 717-01-00100 | Seeding | 12 | LB | 21.00 | 252.00 | 20.00 | 240.00 | 22.00 | 264.00 | 50.00 | 600.00 |
| 0028 | 718-01-00100 | Fertilizer | 410 | LB | 2.60 | 1,066.00 | 2.70 | 1,107.00 | 2.75 | 1,127.50 | 1.70 | 697.00 |
| 0029 | 726-01-00100 | Bedding Material | 20.9 | CUYD | 90.00 | 1,881.00 | 85.00 | 1,776.50 | 110.00 | 2,299.00 | 150.00 | 3,135.00 |
| 0030 | 727-01-00100 | Mobilization | 1 | LUMP | 61,000.00 | 61,000.00 | 100,000.00 | 100,000.00 | 135,000.00 | 135,000.00 | 100,000.00 | 100,000.00 |
| 0031 | 729-16-00300 | Object Marker Assembly (Type 3) | 16 | EACH | 100.00 | 1,600.00 | 80.00 | 1,280.00 | 80.00 | 1,280.00 | 75.00 | 1,200.00 |
| 0032 | 731-02-00100 | Reflectorized Raised Pavement Markers | 949 | EACH | 5.50 | 5,219.50 | 5.70 | 5,409.30 | 5.00 | 4,745.00 | 4.50 | 4,270.50 |
| 0033 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 15.655 | MILE | 2,400.00 | 37,572.00 | 2,700.00 | 42,268.50 | 2,600.00 | 40,703.00 | 2,500.00 | 39,137.50 |
| 0034 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 6.418 | MILE | 1,500.00 | 9,627.00 | 925.00 | 5,936.65 | 750.00 | 4,813.50 | 700.00 | 4,492.60 |
| 0035 | 735-01-00100 | Mailboxes | 22 | EACH | 1.00 | 22.00 | 1.00 | 22.00 | 1.00 | 22.00 | 1.00 | 22.00 |
| 0036 | 735-02-00100 | Mailbox Supports (Single) | 20 | EACH | 120.00 | 2,400.00 | 140.00 | 2,800.00 | 140.00 | 2,800.00 | 100.00 | 2,000.00 |
| 0037 | 735-03-00100 | Mailbox Supports (Double) | 1 | EACH | 170.00 | 170.00 | 160.00 | 160.00 | 155.00 | 155.00 | 190.00 | 190.00 |
| 0038 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,500.00 | 10,500.00 | 6,000.00 | 6,000.00 | 9,600.00 | 9,600.00 | 18,000.00 | 18,000.00 |
| 0039 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 12,072 | INLF | 0.27 | 3,259.44 | 0.30 | 3,621.60 | 0.25 | 3,018.00 | 1.60 | 19,315.20 |
| 0040 | NS-700-00240 | Special Guard Rail Anchor Section | 1 | EACH | 1,100.00 | 1,100.00 | 1,200.00 | 1,200.00 | 1,200.00 | 1,200.00 | 1,500.00 | 1,500.00 |
| CONTRACTOR TOTAL | 1,732,968.17 | 1,870,906.49 | 1,875,338.90 | 1,898,087.11 | ||||||||