Bid Tabulations
Letting of
10/26/2011
LA DOTD Headquarters
| Lead Project: 177-05-0033-R1 | |
| Parish: Concordia | |
| Routes: LA 15 | |
| Description: 6.5 MI. N. OF LA 565 - 1.0 MI. S. OF LA 131 | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK | |
| Estimated Construction Cost: $559,364.09 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 02214 | W. E. Blain & Sons, Inc. | $526,677.12 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $614,250.27 |
| 3 | 05789 | D & J Construction Co., Inc. | $633,685.95 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - W. E. Blain & Sons, Inc. |
- 2 - Gilchrist Construction Co. LLC |
- 3 - D & J Construction Co., Inc. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 2,890 | CUYD | 18.00 | 52,020.00 | 22.00 | 63,580.00 | 18.00 | 52,020.00 |
| 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 321 | CUYD | 42.25 | 13,562.25 | 50.00 | 16,050.00 | 30.00 | 9,630.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 4,126.7 | TON | 84.00 | 346,642.80 | 95.00 | 392,036.50 | 102.00 | 420,923.40 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 43.9 | TON | 210.00 | 9,219.00 | 350.00 | 15,365.00 | 130.00 | 5,707.00 |
| 0005 | 509-01-00100 | Cold Planing Asphaltic Pavement | 16,041 | SQYD | 1.60 | 25,665.60 | 2.00 | 32,082.00 | 2.00 | 32,082.00 |
| 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -473 | CUYD | 0.10 | -47.30 | 1.00 | -473.00 | 0.10 | -47.30 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 100 | SQYD | 125.00 | 12,500.00 | 125.00 | 12,500.00 | 150.00 | 15,000.00 |
| 0008 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 8,600.00 | 8,600.00 | 6,500.00 | 6,500.00 | 15,000.00 | 15,000.00 |
| 0009 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 5.201 | MILE | 270.00 | 1,404.27 | 350.00 | 1,820.35 | 225.00 | 1,170.23 |
| 0010 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 3.901 | MILE | 300.00 | 1,170.30 | 100.00 | 390.10 | 325.00 | 1,267.83 |
| 0011 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 9.291 | MILE | 600.00 | 5,574.60 | 100.00 | 929.10 | 1.00 | 9.29 |
| 0012 | 716-01-00100 | Mulch (Vegetative) | 3.2 | TON | 630.00 | 2,016.00 | 710.00 | 2,272.00 | 750.00 | 2,400.00 |
| 0013 | 717-01-00100 | Seeding | 191 | LB | 8.50 | 1,623.50 | 9.60 | 1,833.60 | 8.50 | 1,623.50 |
| 0014 | 718-01-00100 | Fertilizer | 3,190 | LB | 0.60 | 1,914.00 | 0.65 | 2,073.50 | 0.50 | 1,595.00 |
| 0015 | 727-01-00100 | Mobilization | 1 | LUMP | 26,000.00 | 26,000.00 | 55,000.00 | 55,000.00 | 54,000.00 | 54,000.00 |
| 0016 | 731-02-00100 | Reflectorized Raised Pavement Markers | 173 | EACH | 4.50 | 778.50 | 6.00 | 1,038.00 | 16.00 | 2,768.00 |
| 0017 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.3 | MILE | 3,000.00 | 3,900.00 | 3,200.00 | 4,160.00 | 5,000.00 | 6,500.00 |
| 0018 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.097 | MILE | 800.00 | 2,477.60 | 960.00 | 2,973.12 | 1,000.00 | 3,097.00 |
| 0019 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 3,400.00 | 3,400.00 | 7,500.00 | 7,500.00 |
| 0020 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 720 | INLF | 2.30 | 1,656.00 | 1.00 | 720.00 | 2.00 | 1,440.00 |
| CONTRACTOR TOTAL | 526,677.12 | 614,250.27 | 633,685.95 | |||||||