Bid Tabulations
Letting of
09/22/2010
LA DOTD Headquarters
| Lead Project: 166-01-0027 | |
| Parish: Tensas, Caldwell | |
| Routes: LA 604, LA 561, LA 573, LA 133, LA 573, LA 892 | |
| Description: LA 133 - RICHLAND PARISH LINE | |
| Type Const: ASHALTIC SURFACE TREATMENT AND RELATED WORK | |
| Estimated Construction Cost: $898,438.68 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 05635 | Dreher Contracting, Inc. | $803,910.30 |
| 2 | 35378 | P.R. Parker Company Inc | $824,934.53 |
| 3 | 14422 | T. L. Wallace Construction, Inc. | $871,690.55 |
| 4 | 30339 | Missouri Petroleum Products Co. LLC | $878,308.22 |
| 5 | 10989 | Dickerson & Bowen, Inc. | $900,555.58 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Dreher Contracting, Inc. |
- 2 - P.R. Parker Company Inc |
- 3 - T. L. Wallace Construction, Inc. |
- 4 - Missouri Petroleum Products Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 139,690 | GAL | 2.95 | 412,085.50 | 2.75 | 384,147.50 | 3.00 | 419,070.00 | 2.90 | 405,101.00 |
| 0002 | 507-02-00200 | Aggregate (S2) | 264,006 | SQYD | 0.77 | 203,284.62 | 0.73 | 192,724.38 | 0.90 | 237,605.40 | 0.90 | 237,605.40 |
| 0003 | 507-02-00300 | Aggregate (S3) | 101,421 | SQYD | 0.63 | 63,895.23 | 0.55 | 55,781.55 | 0.85 | 86,207.85 | 0.72 | 73,023.12 |
| 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 10,000.00 | 10,000.00 | 19,000.00 | 19,000.00 | 22,000.00 | 22,000.00 | 17,000.00 | 17,000.00 |
| 0005 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 7,954 | EACH | 1.55 | 12,328.70 | 2.00 | 15,908.00 | 1.50 | 11,931.00 | 1.00 | 7,954.00 |
| 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 18,000.00 | 18,000.00 | 82,500.00 | 82,500.00 | 12,150.00 | 12,150.00 | 59,000.00 | 59,000.00 |
| 0007 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,979 | EACH | 3.75 | 14,921.25 | 4.50 | 17,905.50 | 4.00 | 15,916.00 | 3.75 | 14,921.25 |
| 0008 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 51.694 | MILE | 1,100.00 | 56,863.40 | 900.00 | 46,524.60 | 1,050.00 | 54,278.70 | 1,000.00 | 51,694.00 |
| 0009 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 20.886 | MILE | 600.00 | 12,531.60 | 500.00 | 10,443.00 | 600.00 | 12,531.60 | 575.00 | 12,009.45 |
| CONTRACTOR TOTAL | 803,910.30 | 824,934.53 | 871,690.55 | 878,308.22 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Dickerson & Bowen, Inc. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 139,690 | GAL | 3.48 | 486,121.20 |
| 0002 | 507-02-00200 | Aggregate (S2) | 264,006 | SQYD | 0.81 | 213,844.86 |
| 0003 | 507-02-00300 | Aggregate (S3) | 101,421 | SQYD | 0.58 | 58,824.18 |
| 0004 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 17,250.00 | 17,250.00 |
| 0005 | 713-06-00200 | Temporary Reflectorized Raised Pavement Markers (Tabs) | 7,954 | EACH | 0.75 | 5,965.50 |
| 0006 | 727-01-00100 | Mobilization | 1 | LUMP | 26,500.00 | 26,500.00 |
| 0007 | 731-02-00100 | Reflectorized Raised Pavement Markers | 3,979 | EACH | 4.45 | 17,706.55 |
| 0008 | 732-02-01000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 40 mil) | 51.694 | MILE | 1,168.39 | 60,398.75 |
| 0009 | 732-03-01000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 40 mil) | 20.886 | MILE | 667.65 | 13,944.54 |
| CONTRACTOR TOTAL | 900,555.58 | |||||