LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 134-02-0021
Parish: Vernon
Routes: LA 8
Description: LA 8 BRIDGES NEAR SIMPSON
Type Const: GRADING, DRAINAGE STRUCTURES, LIME TREATMENT, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, CONCRETE SLAB SPAN BRIDGES AND RELATED WORK.
Estimated Construction Cost: $10,909,848.05
Maximum Number of Days Allowed for Construction: 9999
Calculated Daily User Cost: $3,000.00


RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Total Bid
1 12312 Gilchrist Construction Co. LLC $9,314,833.82 450 $10,664,833.82
2 34567 James Construction Group LLC $8,997,307.74 800 $11,397,307.74
3 07740 Cajun Constructors, Inc. $12,675,534.78 840 $15,195,534.78
4 55519 Key, LLC Of Mississippi $12,911,393.51 800 $15,311,393.51
5 12135 Blount Bros. Construction, Inc. $14,023,376.15 450 $15,373,376.15
6 00060 F. Miller Construction Llc $14,531,480.42 580 $16,271,480.42
7 09090 Guinn Brothers, LLC. $13,423,946.05 1095 $16,708,946.05
8 01012 Cecil D. Gassiott, LLC $12,991,434.93 1260 $16,771,434.93
9 39462 Jb James Construction Llc $14,700,007.40 780 $17,040,007.40


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
Gilchrist Construction Co. LLC
- 2 -
James Construction Group LLC
- 3 -
Cajun Constructors, Inc.
- 4 -
Key, LLC Of Mississippi
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 325,000.00 325,000.00 175,000.00 175,000.00 135,000.00 135,000.00 185,000.00 185,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 5,000.00 5,000.00 3,500.00 3,500.00 2,600.00 2,600.00 20,000.00 20,000.00
0003 202-02-04000 Removal of Bridge STATION 206+78.41, 23' X 35', TIMBER TRESTLE 1      EACH 10,000.00 10,000.00 2,500.00 2,500.00 6,000.00 6,000.00 5,000.00 5,000.00
0004 202-02-04000 Removal of Bridge STATION 455+05.53, 23' X 40', TIMBER TRESTLE 1      EACH 10,000.00 10,000.00 2,500.00 2,500.00 6,000.00 6,000.00 5,000.00 5,000.00
0005 202-02-04000 Removal of Bridge STATION 305+19.36, 23' X 78', TIMBER TRESTLE 1      EACH 15,000.00 15,000.00 4,000.00 4,000.00 6,000.00 6,000.00 11,000.00 11,000.00
0006 202-02-04000 Removal of Bridge STATION 106+97.00, 23' X 121', TIMBER TRESTLE 1      EACH 20,000.00 20,000.00 10,000.00 10,000.00 7,000.00 7,000.00 12,000.00 12,000.00
0007 202-02-04000 Removal of Bridge STATION 407+50.00, 23' X 230', TIMBER TRESTLE 1      EACH 40,000.00 40,000.00 15,000.00 15,000.00 13,000.00 13,000.00 25,000.00 25,000.00
0008 202-02-04000 Removal of Bridge STATION 413+50.27, 23' X 268', TIMBER TRESTLE 1      EACH 45,000.00 45,000.00 20,000.00 20,000.00 14,000.00 14,000.00 25,000.00 25,000.00
0009 202-02-04000 Removal of Bridge STATION 433+10.88, 23' X 78', TIMBER TRESTLE 1      EACH 15,000.00 15,000.00 4,000.00 4,000.00 5,000.00 5,000.00 11,000.00 11,000.00
0010 202-02-04000 Removal of Bridge STATION 419+80.09, 23' X 173', TIMBER TRESTLE 1      EACH 30,000.00 30,000.00 12,000.00 12,000.00 10,000.00 10,000.00 22,000.00 22,000.00
0011 202-02-04000 Removal of Bridge STATION 425+73.81, 23' X 78', TIMBER TRESTLE 1      EACH 15,000.00 15,000.00 4,000.00 4,000.00 5,000.00 5,000.00 11,000.00 11,000.00
0012 202-02-14500 Removal of Guard Rail 4,798      LNFT 4.75 22,790.50 3.00 14,394.00 6.86 32,914.28 3.00 14,394.00
0013 203-01-00100 General Excavation 14,226      CUYD 9.00 128,034.00 5.00 71,130.00 9.79 139,272.54 7.00 99,582.00
0014 203-03-00100 Embankment 25,450      CUYD 12.00 305,400.00 7.00 178,150.00 16.74 426,033.00 12.00 305,400.00
0015 203-05-00100 Excavation and Embankment 1      LUMP 100,000.00 100,000.00 100,000.00 100,000.00 50,000.00 50,000.00 35,000.00 35,000.00
0016 204-05-00100 Temporary Sediment Check Dams (Hay) 71      EACH 200.00 14,200.00 145.00 10,295.00 150.00 10,650.00 250.00 17,750.00
0017 204-06-00100 Temporary Silt Fencing 17,325      LNFT 1.80 31,185.00 2.00 34,650.00 2.00 34,650.00 2.00 34,650.00
0018 302-02-01040 Class II Base Course (4" Thick) (Stone) 26,266.6    SQYD 12.20 320,452.52 11.00 288,932.60 14.00 367,732.40 13.00 341,465.80
0019 302-02-03020 Class II Base Course (8" Thick) (Soil Cement) 26,266.6    SQYD 13.40 351,972.44 7.00 183,866.20 10.00 262,666.00 11.50 302,065.90
0020 304-05-00100 Lime Treatment (Type E) 59.07   TON 365.00 21,560.55 250.00 14,767.50 565.42 33,399.36 450.00 26,581.50
0021 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 113      CUYD 85.00 9,605.00 100.00 11,300.00 92.00 10,396.00 35.00 3,955.00
0022 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 1,000      CUYD 25.00 25,000.00 75.00 75,000.00 92.82 92,820.00 1.00 1,000.00
0023 502-01-00100 Superpave Asphaltic Concrete 4,034.5    TON 99.00 399,415.50 130.00 524,485.00 183.22 739,201.09 130.00 524,485.00
0024 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,530.6    TON 145.00 221,937.00 150.00 229,590.00 211.41 323,584.15 150.00 229,590.00
0025 701-01-01081 Cross Drain Pipe (48" RCP) 172      LNFT 135.00 23,220.00 145.00 24,940.00 204.36 35,149.92 140.00 24,080.00
0026 701-05-01040 Side Drain Pipe (18" RCP/PP/CMP) 48      LNFT 45.00 2,160.00 60.00 2,880.00 86.68 4,160.64 50.00 2,400.00
0027 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 220      LNFT 45.00 9,900.00 60.00 13,200.00 80.34 17,674.80 65.00 14,300.00
0028 701-05-01140 Side Drain Pipe (48" RCP/PP/CMP) 180      LNFT 125.00 22,500.00 180.00 32,400.00 279.06 50,230.80 125.00 22,500.00
0029 704-03-00100 Blocked Out Guard Rail 1,962.5    LNFT 18.00 35,325.00 20.00 39,250.00 23.72 46,550.50 18.00 35,325.00
0030 704-05-00100 Guard Rail Anchor Sections (BCT) 125      LNFT 5.00 625.00 50.00 6,250.00 1.40 175.00 50.00 6,250.00
0031 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 700      LNFT 65.00 45,500.00 65.00 45,500.00 83.72 58,604.00 60.00 42,000.00
0032 704-11-00100 Guard Rail End Treatment (Flared) 27      EACH 2,100.00 56,700.00 2,400.00 64,800.00 2,720.82 73,462.14 2,200.00 59,400.00
0033 705-01-00100 Barbed Wire Fence 4,634      LNFT 6.30 29,194.20 6.00 27,804.00 9.21 42,679.14 8.00 37,072.00
0034 705-04-00100 Single Swinging Driveway Gates 1      EACH 550.00 550.00 800.00 800.00 1,116.23 1,116.23 650.00 650.00
0035 705-06-00100 Chain Link Fence (4-Foot Height) 455      LNFT 30.00 13,650.00 20.00 9,100.00 27.91 12,699.05 12.00 5,460.00
0036 705-07-02000 4-Foot Single Gates for Chain Link Fence (4-Foot Height) 1      EACH 825.00 825.00 800.00 800.00 1,116.23 1,116.23 650.00 650.00
0037 705-08-03000 8-Foot Double Gates for Chain Link Fence (4-Foot Height) 1      DBGT 1,200.00 1,200.00 1,250.00 1,250.00 1,744.11 1,744.11 650.00 650.00
0038 708-01-00100 Right-of-Way Monument 62      EACH 200.00 12,400.00 200.00 12,400.00 228.94 14,194.28 110.00 6,820.00
0039 708-02-00100 Right-of-Way Monument Witness Post 62      EACH 200.00 12,400.00 200.00 12,400.00 152.09 9,429.58 110.00 6,820.00
0040 711-01-03020 Riprap (30 lb, 18" Thick) 728      SQYD 50.00 36,400.00 50.00 36,400.00 79.53 57,897.84 65.00 47,320.00
0041 711-04-00100 Geotextile Fabric 728      SQYD 2.50 1,820.00 3.00 2,184.00 3.49 2,540.72 2.00 1,456.00
0042 712-04-00100 Flexible Revetment 9,219      SQYD 37.19 342,854.61 45.00 414,855.00 64.83 597,667.77 55.00 507,045.00
0043 713-01-00100 Temporary Signs and Barricades 1      LUMP 100,000.00 100,000.00 50,000.00 50,000.00 55,489.69 55,489.69 50,000.00 50,000.00
0044 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 1.781  MILE 300.00 534.30 300.00 534.30 697.25 1,241.80 300.00 534.30
0045 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 1.781  MILE 300.00 534.30 300.00 534.30 348.63 620.91 475.00 845.98
0046 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 8.989  MILE 400.00 3,595.60 460.00 4,134.94 486.78 4,375.67 475.00 4,269.78
0047 713-06-00200 Temporary Reflectorized Raised Pavement Markers (Tabs) 475      EACH 5.80 2,755.00 1.50 712.50 6.98 3,315.50 12.00 5,700.00
0048 716-01-00100 Mulch (Vegetative) 48      TON 545.00 26,160.00 650.00 31,200.00 906.94 43,533.12 750.00 36,000.00
0049 717-01-00100 Seeding 1,920      LB 7.74 14,860.80 8.50 16,320.00 11.86 22,771.20 8.00 15,360.00
0050 718-01-00100 Fertilizer 24,000      LB 0.45 10,800.00 0.55 13,200.00 0.77 18,480.00 0.75 18,000.00
0051 720-01-01000 Erosion Control System (Slope Protection) (Type A) 17,050      SQYD 1.10 18,755.00 1.50 25,575.00 1.95 33,247.50 1.00 17,050.00
0052 720-01-02000 Erosion Control System, Flexible (Channel Liner) (Type C) 289      SQYD 1.70 491.30 2.50 722.50 3.63 1,049.07 2.00 578.00
0053 720-01-02020 Erosion Control System, Flexible (Channel Liner) (Type D) 3,483      SQYD 2.00 6,966.00 2.50 8,707.50 3.63 12,643.29 2.00 6,966.00
0054 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 25,000.00 25,000.00 30,000.00 30,000.00 63,518.27 63,518.27 10,000.00 10,000.00
0055 725-01-00100 Temporary Detour Roads 26,323      SQYD 25.00 658,075.00 30.00 789,690.00 65.00 1,710,995.00 55.00 1,447,765.00
0056 725-02-00100 Temporary Detour Bridging 640      LNFT 800.00 512,000.00 1,000.00 640,000.00 2,700.00 1,728,000.00 3,770.00 2,412,800.00
0057 726-01-00100 Bedding Material 681.4    CUYD 92.00 62,688.80 90.00 61,326.00 118.60 80,814.04 35.00 23,849.00
0058 727-01-00100 Mobilization 1      LUMP 900,000.00 900,000.00 750,000.00 750,000.00 460,882.48 460,882.48 1,140,000.00 1,140,000.00
0059 729-16-00200 Object Marker Assembly (Type 2) 12      EACH 70.00 840.00 47.92 575.04 90.69 1,088.28 45.00 540.00
0060 729-16-00300 Object Marker Assembly (Type 3) 28      EACH 80.00 2,240.00 79.87 2,236.36 100.46 2,812.88 75.00 2,100.00
0061 731-01-00100 Nonreflectorized Raised Pavement Markers 376      EACH 13.00 4,888.00 10.00 3,760.00 16.74 6,294.24 12.00 4,512.00
0062 731-02-00100 Reflectorized Raised Pavement Markers 238      EACH 8.00 1,904.00 4.50 1,071.00 11.16 2,656.08 12.00 2,856.00
0063 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 4.025  MILE 3,400.00 13,685.00 2,800.00 11,270.00 4,320.04 17,388.16 3,100.00 12,477.50
0064 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.384  MILE 1,300.00 1,799.20 800.00 1,107.20 1,669.52 2,310.62 1,200.00 1,660.80
0065 740-01-00100 Construction Layout 1      LUMP 56,000.00 56,000.00 55,000.00 55,000.00 72,037.66 72,037.66 180,000.00 180,000.00
0066 804-01-00300 Precast Concrete Piles (16") 13,996      LNFT 53.00 741,788.00 65.00 909,740.00 82.50 1,154,670.00 86.00 1,203,656.00
0067 804-05-00300 Precast Concrete Test Piles (16") 5      EACH 15,000.00 75,000.00 45,000.00 225,000.00 15,000.00 75,000.00 25,000.00 125,000.00
0068 804-09-00100 Loading Test Piles 5      EACH 20,000.00 100,000.00 2,500.00 12,500.00 16,750.00 83,750.00 25,000.00 125,000.00
0069 804-10-00100 Reloading Test Piles 5      EACH 2,000.00 10,000.00 1,000.00 5,000.00 420.00 2,100.00 3,000.00 15,000.00
0070 804-11-00100 Redriving Test Piles 5      EACH 725.00 3,625.00 1,000.00 5,000.00 420.00 2,100.00 2,000.00 10,000.00
0071 804-12-00100 Loading Permanent Piles 7      EACH 100.00 700.00 1,000.00 7,000.00 300.00 2,100.00 3,000.00 21,000.00
0072 804-17-00100 Dynamic Monitoring 31      EACH 250.00 7,750.00 1,200.00 37,200.00 150.00 4,650.00 2,750.00 85,250.00
0073 805-01-00300 Class A Concrete (Box Culvert Headwalls) 96.65   CUYD 1,200.00 115,980.00 1,200.00 115,980.00 1,400.00 135,310.00 1,000.00 96,650.00
0074 805-01-00700 Class A Concrete (Bents) 352.5    CUYD 1,300.00 458,250.00 800.00 282,000.00 825.00 290,812.50 980.00 345,450.00
0075 805-03-00100 Class AA Concrete 1,495.85   CUYD 600.00 897,510.00 520.00 777,842.00 730.00 1,091,970.50 640.00 957,344.00
0076 805-12-01060 Reinforced Concrete Box Culverts (7' x 4') 630      LNFT 385.00 242,550.00 340.00 214,200.00 475.00 299,250.00 390.00 245,700.00
0077 805-12-05000 Reinforced Concrete Box Culverts (8' x 8') 258      LNFT 565.00 145,770.00 480.00 123,840.00 650.00 167,700.00 575.00 148,350.00
0078 806-01-00100 Deformed Reinforcing Steel 462,358      LB 0.70 323,650.60 1.00 462,358.00 1.00 462,358.00 1.10 508,593.80
0079 810-01-00100 Concrete Railing (Standard Barrier) 2,200      LNFT 80.00 176,000.00 50.00 110,000.00 97.00 213,400.00 65.00 143,000.00
0080 813-01-00100 Concrete Approach Slabs 1,928.92   SQYD 230.00 443,651.60 215.00 414,717.80 275.00 530,453.00 195.00 376,139.40
0081 NS-200-00020 Cleaning Existing Ditches 260      LNFT 16.00 4,160.00 5.00 1,300.00 14.50 3,770.00 12.00 3,120.00
0082 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 1,130      INLF 3.00 3,390.00 1.00 1,130.00 2.00 2,260.00 1.00 1,130.00
0083 202-02-02020 Removal of Asphalt Pavement 5,855      SQYD 2.00 11,710.00 10.00 58,550.00 8.25 48,303.75 3.25 19,028.75
                         
    ITEM TOTAL (CONSTRUCTION BID)       9,314,833.82   8,997,307.74   12,675,534.78   12,911,393.51
    NUMBER OF DAYS BID AT $3000 PER DAY.       1,350,000.00   2,400,000.00   2,520,000.00   2,400,000.00
    TOTAL BID       10,664,833.82   11,397,307.74   15,195,534.78   15,311,393.51



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Blount Bros. Construction, Inc.
- 6 -
F. Miller Construction Llc
- 7 -
Guinn Brothers, LLC.
- 8 -
Cecil D. Gassiott, LLC
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 200,000.00 200,000.00 118,183.34 118,183.34 240,000.00 240,000.00 145,000.00 145,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 50,000.00 50,000.00 33,308.22 33,308.22 20,000.00 20,000.00 25,000.00 25,000.00
0003 202-02-04000 Removal of Bridge STATION 206+78.41, 23' X 35', TIMBER TRESTLE 1      EACH 30,000.00 30,000.00 6,220.18 6,220.18 5,000.00 5,000.00 7,700.00 7,700.00
0004 202-02-04000 Removal of Bridge STATION 455+05.53, 23' X 40', TIMBER TRESTLE 1      EACH 35,000.00 35,000.00 6,220.18 6,220.18 5,000.00 5,000.00 7,700.00 7,700.00
0005 202-02-04000 Removal of Bridge STATION 305+19.36, 23' X 78', TIMBER TRESTLE 1      EACH 45,000.00 45,000.00 24,656.29 24,656.29 10,000.00 10,000.00 25,000.00 25,000.00
0006 202-02-04000 Removal of Bridge STATION 106+97.00, 23' X 121', TIMBER TRESTLE 1      EACH 60,000.00 60,000.00 36,984.01 36,984.01 12,500.00 12,500.00 35,000.00 35,000.00
0007 202-02-04000 Removal of Bridge STATION 407+50.00, 23' X 230', TIMBER TRESTLE 1      EACH 80,000.00 80,000.00 43,147.84 43,147.84 15,000.00 15,000.00 45,000.00 45,000.00
0008 202-02-04000 Removal of Bridge STATION 413+50.27, 23' X 268', TIMBER TRESTLE 1      EACH 90,000.00 90,000.00 49,311.71 49,311.71 22,000.00 22,000.00 55,000.00 55,000.00
0009 202-02-04000 Removal of Bridge STATION 433+10.88, 23' X 78', TIMBER TRESTLE 1      EACH 45,000.00 45,000.00 24,656.29 24,656.29 8,500.00 8,500.00 25,000.00 25,000.00
0010 202-02-04000 Removal of Bridge STATION 419+80.09, 23' X 173', TIMBER TRESTLE 1      EACH 70,000.00 70,000.00 30,820.15 30,820.15 15,000.00 15,000.00 35,000.00 35,000.00
0011 202-02-04000 Removal of Bridge STATION 425+73.81, 23' X 78', TIMBER TRESTLE 1      EACH 45,000.00 45,000.00 24,656.29 24,656.29 8,500.00 8,500.00 25,000.00 25,000.00
0012 202-02-14500 Removal of Guard Rail 4,798      LNFT 7.00 33,586.00 6.01 28,835.98 3.00 14,394.00 6.00 28,788.00
0013 203-01-00100 General Excavation 14,226      CUYD 15.00 213,390.00 8.71 123,908.46 6.00 85,356.00 5.00 71,130.00
0014 203-03-00100 Embankment 25,450      CUYD 15.00 381,750.00 14.93 379,968.50 14.00 356,300.00 15.00 381,750.00
0015 203-05-00100 Excavation and Embankment 1      LUMP 150,000.00 150,000.00 43,541.22 43,541.22 100,000.00 100,000.00 100,000.00 100,000.00
0016 204-05-00100 Temporary Sediment Check Dams (Hay) 71      EACH 200.00 14,200.00 149.28 10,598.88 150.00 10,650.00 200.00 14,200.00
0017 204-06-00100 Temporary Silt Fencing 17,325      LNFT 3.00 51,975.00 1.89 32,744.25 2.25 38,981.25 2.00 34,650.00
0018 302-02-01040 Class II Base Course (4" Thick) (Stone) 26,266.6    SQYD 10.00 262,666.00 16.17 424,730.92 11.00 288,932.60 15.00 393,999.00
0019 302-02-03020 Class II Base Course (8" Thick) (Soil Cement) 26,266.6    SQYD 9.00 236,399.40 14.31 375,875.05 22.00 577,865.20 30.00 787,998.00
0020 304-05-00100 Lime Treatment (Type E) 59.07   TON 305.00 18,016.35 559.82 33,068.57 500.00 29,535.00 200.00 11,814.00
0021 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 113      CUYD 80.00 9,040.00 43.54 4,920.02 100.00 11,300.00 80.00 9,040.00
0022 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 1,000      CUYD 80.00 80,000.00 1.24 1,240.00 50.00 50,000.00 95.00 95,000.00
0023 502-01-00100 Superpave Asphaltic Concrete 4,034.5    TON 180.00 726,210.00 161.72 652,459.34 175.00 706,037.50 140.00 564,830.00
0024 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,530.6    TON 190.00 290,814.00 186.61 285,625.27 210.00 321,426.00 170.00 260,202.00
0025 701-01-01081 Cross Drain Pipe (48" RCP) 172      LNFT 200.00 34,400.00 105.74 18,187.28 275.00 47,300.00 200.00 34,400.00
0026 701-05-01040 Side Drain Pipe (18" RCP/PP/CMP) 48      LNFT 40.00 1,920.00 62.20 2,985.60 120.00 5,760.00 68.00 3,264.00
0027 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 220      LNFT 60.00 13,200.00 70.91 15,600.20 150.00 33,000.00 87.00 19,140.00
0028 701-05-01140 Side Drain Pipe (48" RCP/PP/CMP) 180      LNFT 200.00 36,000.00 155.50 27,990.00 300.00 54,000.00 180.00 32,400.00
0029 704-03-00100 Blocked Out Guard Rail 1,962.5    LNFT 30.00 58,875.00 21.15 41,506.88 22.00 43,175.00 19.00 37,287.50
0030 704-05-00100 Guard Rail Anchor Sections (BCT) 125      LNFT 85.00 10,625.00 1.24 155.00 5.00 625.00 10.00 1,250.00
0031 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 700      LNFT 75.00 52,500.00 74.64 52,248.00 68.00 47,600.00 65.00 45,500.00
0032 704-11-00100 Guard Rail End Treatment (Flared) 27      EACH 3,000.00 81,000.00 2,425.87 65,498.49 2,250.00 60,750.00 2,000.00 54,000.00
0033 705-01-00100 Barbed Wire Fence 4,634      LNFT 11.00 50,974.00 8.21 38,045.14 10.00 46,340.00 7.00 32,438.00
0034 705-04-00100 Single Swinging Driveway Gates 1      EACH 700.00 700.00 622.02 622.02 2,000.00 2,000.00 1,400.00 1,400.00
0035 705-06-00100 Chain Link Fence (4-Foot Height) 455      LNFT 30.00 13,650.00 24.88 11,320.40 25.00 11,375.00 22.00 10,010.00
0036 705-07-02000 4-Foot Single Gates for Chain Link Fence (4-Foot Height) 1      EACH 500.00 500.00 995.23 995.23 1,000.00 1,000.00 900.00 900.00
0037 705-08-03000 8-Foot Double Gates for Chain Link Fence (4-Foot Height) 1      DBGT 1,100.00 1,100.00 1,555.05 1,555.05 2,000.00 2,000.00 1,400.00 1,400.00
0038 708-01-00100 Right-of-Way Monument 62      EACH 200.00 12,400.00 174.16 10,797.92 200.00 12,400.00 275.00 17,050.00
0039 708-02-00100 Right-of-Way Monument Witness Post 62      EACH 150.00 9,300.00 62.20 3,856.40 200.00 12,400.00 80.00 4,960.00
0040 711-01-03020 Riprap (30 lb, 18" Thick) 728      SQYD 80.00 58,240.00 80.86 58,866.08 75.00 54,600.00 58.00 42,224.00
0041 711-04-00100 Geotextile Fabric 728      SQYD 3.00 2,184.00 2.49 1,812.72 5.00 3,640.00 3.00 2,184.00
0042 712-04-00100 Flexible Revetment 9,219      SQYD 80.00 737,520.00 60.61 558,763.59 75.00 691,425.00 55.00 507,045.00
0043 713-01-00100 Temporary Signs and Barricades 1      LUMP 80,000.00 80,000.00 55,577.26 55,577.26 180,000.00 180,000.00 62,000.00 62,000.00
0044 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 1.781  MILE 1,000.00 1,781.00 310.83 553.59 400.00 712.40 325.00 578.83
0045 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 1.781  MILE 1,000.00 1,781.00 310.83 553.59 400.00 712.40 550.00 979.55
0046 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 8.989  MILE 1,100.00 9,887.90 434.01 3,901.32 550.00 4,943.95 1,100.00 9,887.90
0047 713-06-00200 Temporary Reflectorized Raised Pavement Markers (Tabs) 475      EACH 20.00 9,500.00 9.95 4,726.25 10.00 4,750.00 2.50 1,187.50
0048 716-01-00100 Mulch (Vegetative) 48      TON 700.00 33,600.00 808.62 38,813.76 750.00 36,000.00 700.00 33,600.00
0049 717-01-00100 Seeding 1,920      LB 20.00 38,400.00 10.57 20,294.40 12.00 23,040.00 9.00 17,280.00
0050 718-01-00100 Fertilizer 24,000      LB 1.00 24,000.00 0.68 16,320.00 1.00 24,000.00 0.60 14,400.00
0051 720-01-01000 Erosion Control System (Slope Protection) (Type A) 17,050      SQYD 2.50 42,625.00 1.74 29,667.00 2.00 34,100.00 1.60 27,280.00
0052 720-01-02000 Erosion Control System, Flexible (Channel Liner) (Type C) 289      SQYD 3.00 867.00 3.23 933.47 2.00 578.00 3.00 867.00
0053 720-01-02020 Erosion Control System, Flexible (Channel Liner) (Type D) 3,483      SQYD 3.00 10,449.00 3.23 11,250.09 4.50 15,673.50 3.00 10,449.00
0054 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 20,000.00 20,000.00 13,466.68 13,466.68 25,000.00 25,000.00 140,000.00 140,000.00
0055 725-01-00100 Temporary Detour Roads 26,323      SQYD 80.00 2,105,840.00 84.91 2,235,085.93 84.00 2,211,132.00 59.00 1,553,057.00
0056 725-02-00100 Temporary Detour Bridging 640      LNFT 1,500.00 960,000.00 2,176.33 1,392,851.20 1,500.00 960,000.00 2,735.00 1,750,400.00
0057 726-01-00100 Bedding Material 681.4    CUYD 80.00 54,512.00 48.03 32,727.64 100.00 68,140.00 85.00 57,919.00
0058 727-01-00100 Mobilization 1      LUMP 500,000.00 500,000.00 502,024.17 502,024.17 1,150,000.00 1,150,000.00 700,000.00 700,000.00
0059 729-16-00200 Object Marker Assembly (Type 2) 12      EACH 100.00 1,200.00 80.86 970.32 100.00 1,200.00 75.00 900.00
0060 729-16-00300 Object Marker Assembly (Type 3) 28      EACH 150.00 4,200.00 89.57 2,507.96 100.00 2,800.00 80.00 2,240.00
0061 731-01-00100 Nonreflectorized Raised Pavement Markers 376      EACH 20.00 7,520.00 14.93 5,613.68 16.00 6,016.00 11.00 4,136.00
0062 731-02-00100 Reflectorized Raised Pavement Markers 238      EACH 10.00 2,380.00 9.95 2,368.10 12.00 2,856.00 5.00 1,190.00
0063 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 4.025  MILE 4,000.00 16,100.00 3,851.72 15,503.17 3,850.00 15,496.25 3,000.00 12,075.00
0064 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.384  MILE 2,000.00 2,768.00 1,488.53 2,060.13 1,800.00 2,491.20 800.00 1,107.20
0065 740-01-00100 Construction Layout 1      LUMP 80,000.00 80,000.00 186,605.27 186,605.27 60,000.00 60,000.00 38,000.00 38,000.00
0066 804-01-00300 Precast Concrete Piles (16") 13,996      LNFT 110.00 1,539,560.00 80.63 1,128,497.48 66.00 923,736.00 60.00 839,760.00
0067 804-05-00300 Precast Concrete Test Piles (16") 5      EACH 10,000.00 50,000.00 34,744.23 173,721.15 15,000.00 75,000.00 12,500.00 62,500.00
0068 804-09-00100 Loading Test Piles 5      EACH 10,000.00 50,000.00 6,658.48 33,292.40 1.00 5.00 11,000.00 55,000.00
0069 804-10-00100 Reloading Test Piles 5      EACH 2,000.00 10,000.00 6,658.48 33,292.40 1.00 5.00 1,000.00 5,000.00
0070 804-11-00100 Redriving Test Piles 5      EACH 2,000.00 10,000.00 10,084.06 50,420.30 1.00 5.00 1,000.00 5,000.00
0071 804-12-00100 Loading Permanent Piles 7      EACH 3,000.00 21,000.00 4,976.14 34,832.98 1.00 7.00 2,500.00 17,500.00
0072 804-17-00100 Dynamic Monitoring 31      EACH 2,000.00 62,000.00 995.23 30,852.13 1,500.00 46,500.00 2,500.00 77,500.00
0073 805-01-00300 Class A Concrete (Box Culvert Headwalls) 96.65   CUYD 1,000.00 96,650.00 1,254.35 121,232.93 1,550.00 149,807.50 1,300.00 125,645.00
0074 805-01-00700 Class A Concrete (Bents) 352.5    CUYD 700.00 246,750.00 1,716.39 605,027.48 950.00 334,875.00 1,700.00 599,250.00
0075 805-03-00100 Class AA Concrete 1,495.85   CUYD 800.00 1,196,680.00 1,280.18 1,914,957.25 850.00 1,271,472.50 825.00 1,234,076.25
0076 805-12-01060 Reinforced Concrete Box Culverts (7' x 4') 630      LNFT 700.00 441,000.00 485.17 305,657.10 550.00 346,500.00 470.00 296,100.00
0077 805-12-05000 Reinforced Concrete Box Culverts (8' x 8') 258      LNFT 900.00 232,200.00 715.32 184,552.56 750.00 193,500.00 575.00 148,350.00
0078 806-01-00100 Deformed Reinforcing Steel 462,358      LB 2.00 924,716.00 1.99 920,092.42 1.00 462,358.00 1.00 462,358.00
0079 810-01-00100 Concrete Railing (Standard Barrier) 2,200      LNFT 110.00 242,000.00 98.78 217,316.00 90.00 198,000.00 70.00 154,000.00
0080 813-01-00100 Concrete Approach Slabs 1,928.92   SQYD 225.00 434,007.00 242.59 467,936.70 240.00 462,940.80 210.00 405,073.20
0081 NS-200-00020 Cleaning Existing Ditches 260      LNFT 20.00 5,200.00 14.93 3,881.80 50.00 13,000.00 10.00 2,600.00
0082 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 1,130      INLF 10.00 11,300.00 1.24 1,401.20 5.00 5,650.00 2.00 2,260.00
0083 202-02-02020 Removal of Asphalt Pavement 5,855      SQYD 8.50 49,767.50 4.04 23,654.20 5.00 29,275.00 5.00 29,275.00
                         
    ITEM TOTAL (CONSTRUCTION BID)       14,023,376.15   14,531,480.42   13,423,946.05   12,991,434.93
    NUMBER OF DAYS BID AT $3000 PER DAY.       1,350,000.00   1,740,000.00   3,285,000.00   3,780,000.00
    TOTAL BID       15,373,376.15   16,271,480.42   16,708,946.05   16,771,434.93



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 9 -
Jb James Construction Llc
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 900,000.00 900,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 150,000.00 150,000.00
0003 202-02-04000 Removal of Bridge STATION 206+78.41, 23' X 35', TIMBER TRESTLE 1      EACH 30,000.00 30,000.00
0004 202-02-04000 Removal of Bridge STATION 455+05.53, 23' X 40', TIMBER TRESTLE 1      EACH 30,000.00 30,000.00
0005 202-02-04000 Removal of Bridge STATION 305+19.36, 23' X 78', TIMBER TRESTLE 1      EACH 50,000.00 50,000.00
0006 202-02-04000 Removal of Bridge STATION 106+97.00, 23' X 121', TIMBER TRESTLE 1      EACH 50,000.00 50,000.00
0007 202-02-04000 Removal of Bridge STATION 407+50.00, 23' X 230', TIMBER TRESTLE 1      EACH 50,000.00 50,000.00
0008 202-02-04000 Removal of Bridge STATION 413+50.27, 23' X 268', TIMBER TRESTLE 1      EACH 50,000.00 50,000.00
0009 202-02-04000 Removal of Bridge STATION 433+10.88, 23' X 78', TIMBER TRESTLE 1      EACH 50,000.00 50,000.00
0010 202-02-04000 Removal of Bridge STATION 419+80.09, 23' X 173', TIMBER TRESTLE 1      EACH 50,000.00 50,000.00
0011 202-02-04000 Removal of Bridge STATION 425+73.81, 23' X 78', TIMBER TRESTLE 1      EACH 50,000.00 50,000.00
0012 202-02-14500 Removal of Guard Rail 4,798      LNFT 6.00 28,788.00
0013 203-01-00100 General Excavation 14,226      CUYD 12.00 170,712.00
0014 203-03-00100 Embankment 25,450      CUYD 31.00 788,950.00
0015 203-05-00100 Excavation and Embankment 1      LUMP 135,000.00 135,000.00
0016 204-05-00100 Temporary Sediment Check Dams (Hay) 71      EACH 120.00 8,520.00
0017 204-06-00100 Temporary Silt Fencing 17,325      LNFT 2.00 34,650.00
0018 302-02-01040 Class II Base Course (4" Thick) (Stone) 26,266.6    SQYD 15.00 393,999.00
0019 302-02-03020 Class II Base Course (8" Thick) (Soil Cement) 26,266.6    SQYD 16.00 420,265.60
0020 304-05-00100 Lime Treatment (Type E) 59.07   TON 650.00 38,395.50
0021 401-02-00100 Aggregate Surface Course (Adjusted Vehicular Measurement) 113      CUYD 115.00 12,995.00
0022 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 1,000      CUYD 85.00 85,000.00
0023 502-01-00100 Superpave Asphaltic Concrete 4,034.5    TON 155.00 625,347.50
0024 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 1,530.6    TON 175.00 267,855.00
0025 701-01-01081 Cross Drain Pipe (48" RCP) 172      LNFT 175.00 30,100.00
0026 701-05-01040 Side Drain Pipe (18" RCP/PP/CMP) 48      LNFT 50.00 2,400.00
0027 701-05-01060 Side Drain Pipe (24" RCP/PP/CMP) 220      LNFT 65.00 14,300.00
0028 701-05-01140 Side Drain Pipe (48" RCP/PP/CMP) 180      LNFT 140.00 25,200.00
0029 704-03-00100 Blocked Out Guard Rail 1,962.5    LNFT 19.00 37,287.50
0030 704-05-00100 Guard Rail Anchor Sections (BCT) 125      LNFT 1.00 125.00
0031 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 700      LNFT 60.00 42,000.00
0032 704-11-00100 Guard Rail End Treatment (Flared) 27      EACH 2,000.00 54,000.00
0033 705-01-00100 Barbed Wire Fence 4,634      LNFT 6.75 31,279.50
0034 705-04-00100 Single Swinging Driveway Gates 1      EACH 1,300.00 1,300.00
0035 705-06-00100 Chain Link Fence (4-Foot Height) 455      LNFT 20.00 9,100.00
0036 705-07-02000 4-Foot Single Gates for Chain Link Fence (4-Foot Height) 1      EACH 800.00 800.00
0037 705-08-03000 8-Foot Double Gates for Chain Link Fence (4-Foot Height) 1      DBGT 1,300.00 1,300.00
0038 708-01-00100 Right-of-Way Monument 62      EACH 150.00 9,300.00
0039 708-02-00100 Right-of-Way Monument Witness Post 62      EACH 125.00 7,750.00
0040 711-01-03020 Riprap (30 lb, 18" Thick) 728      SQYD 65.00 47,320.00
0041 711-04-00100 Geotextile Fabric 728      SQYD 3.00 2,184.00
0042 712-04-00100 Flexible Revetment 9,219      SQYD 52.00 479,388.00
0043 713-01-00100 Temporary Signs and Barricades 1      LUMP 150,000.00 150,000.00
0044 713-03-01000 Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) 1.781  MILE 300.00 534.30
0045 713-03-02000 Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) 1.781  MILE 300.00 534.30
0046 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 8.989  MILE 500.00 4,494.50
0047 713-06-00200 Temporary Reflectorized Raised Pavement Markers (Tabs) 475      EACH 10.00 4,750.00
0048 716-01-00100 Mulch (Vegetative) 48      TON 650.00 31,200.00
0049 717-01-00100 Seeding 1,920      LB 8.50 16,320.00
0050 718-01-00100 Fertilizer 24,000      LB 0.60 14,400.00
0051 720-01-01000 Erosion Control System (Slope Protection) (Type A) 17,050      SQYD 1.50 25,575.00
0052 720-01-02000 Erosion Control System, Flexible (Channel Liner) (Type C) 289      SQYD 3.00 867.00
0053 720-01-02020 Erosion Control System, Flexible (Channel Liner) (Type D) 3,483      SQYD 3.00 10,449.00
0054 722-02-00100 Project Site Laboratory (Equipped) 1      EACH 35,000.00 35,000.00
0055 725-01-00100 Temporary Detour Roads 26,323      SQYD 42.00 1,105,566.00
0056 725-02-00100 Temporary Detour Bridging 640      LNFT 1,100.00 704,000.00
0057 726-01-00100 Bedding Material 681.4    CUYD 85.00 57,919.00
0058 727-01-00100 Mobilization 1      LUMP 1,400,000.00 1,400,000.00
0059 729-16-00200 Object Marker Assembly (Type 2) 12      EACH 80.00 960.00
0060 729-16-00300 Object Marker Assembly (Type 3) 28      EACH 80.00 2,240.00
0061 731-01-00100 Nonreflectorized Raised Pavement Markers 376      EACH 10.00 3,760.00
0062 731-02-00100 Reflectorized Raised Pavement Markers 238      EACH 45.00 10,710.00
0063 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 4.025  MILE 2,600.00 10,465.00
0064 732-03-02000 Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) 1.384  MILE 800.00 1,107.20
0065 740-01-00100 Construction Layout 1      LUMP 150,000.00 150,000.00
0066 804-01-00300 Precast Concrete Piles (16") 13,996      LNFT 65.00 909,740.00
0067 804-05-00300 Precast Concrete Test Piles (16") 5      EACH 45,000.00 225,000.00
0068 804-09-00100 Loading Test Piles 5      EACH 500.00 2,500.00
0069 804-10-00100 Reloading Test Piles 5      EACH 500.00 2,500.00
0070 804-11-00100 Redriving Test Piles 5      EACH 500.00 2,500.00
0071 804-12-00100 Loading Permanent Piles 7      EACH 1,500.00 10,500.00
0072 804-17-00100 Dynamic Monitoring 31      EACH 1,500.00 46,500.00
0073 805-01-00300 Class A Concrete (Box Culvert Headwalls) 96.65   CUYD 1,250.00 120,812.50
0074 805-01-00700 Class A Concrete (Bents) 352.5    CUYD 2,000.00 705,000.00
0075 805-03-00100 Class AA Concrete 1,495.85   CUYD 1,500.00 2,243,775.00
0076 805-12-01060 Reinforced Concrete Box Culverts (7' x 4') 630      LNFT 400.00 252,000.00
0077 805-12-05000 Reinforced Concrete Box Culverts (8' x 8') 258      LNFT 550.00 141,900.00
0078 806-01-00100 Deformed Reinforcing Steel 462,358      LB 1.00 462,358.00
0079 810-01-00100 Concrete Railing (Standard Barrier) 2,200      LNFT 62.00 136,400.00
0080 813-01-00100 Concrete Approach Slabs 1,928.92   SQYD 200.00 385,784.00
0081 NS-200-00020 Cleaning Existing Ditches 260      LNFT 16.00 4,160.00
0082 NS-500-00340 Saw Cutting Asphaltic Concrete Pavement 1,130      INLF 1.00 1,130.00
0083 202-02-02020 Removal of Asphalt Pavement 5,855      SQYD 7.00 40,985.00
             
    ITEM TOTAL (CONSTRUCTION BID)       14,700,007.40
    NUMBER OF DAYS BID AT $3000 PER DAY.       2,340,000.00
    TOTAL BID       17,040,007.40