Bid Tabulations
Letting of
09/29/2010
LA DOTD Headquarters
| Lead Project: 127-02-0028 | |
| Parish: LaSalle | |
| Routes: LA 127 | |
| Description: US 165 - LA 125 | |
| Type Const: COLD PLANING ASPHALTIC PAVEMENT, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE OVERLAY AND RELATED WORK. | |
| Estimated Construction Cost: $395,930.32 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 12487 | Diamond B Construction Co., L.L.C. | $332,279.88 |
| 2 | 05789 | D & J Construction Co., Inc. | $332,291.50 |
| 3 | 12312 | Gilchrist Construction Co. LLC | $392,759.30 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Diamond B Construction Co., L.L.C. |
- 2 - D & J Construction Co., Inc. |
- 3 - Gilchrist Construction Co. LLC |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 203-07-00100 | Borrow (Vehicular Measurement) | 10 | CUYD | 60.00 | 600.00 | 40.00 | 400.00 | 30.00 | 300.00 |
| 0002 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 341 | CUYD | 41.00 | 13,981.00 | 28.00 | 9,548.00 | 55.00 | 18,755.00 |
| 0003 | 502-01-00100 | Superpave Asphaltic Concrete | 1,962.5 | TON | 74.00 | 145,225.00 | 78.00 | 153,075.00 | 83.00 | 162,887.50 |
| 0004 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 362.9 | TON | 135.00 | 48,991.50 | 122.00 | 44,273.80 | 110.00 | 39,919.00 |
| 0005 | 509-01-00100 | Cold Planing Asphaltic Pavement | 10,426 | SQYD | 2.50 | 26,065.00 | 1.50 | 15,639.00 | 1.80 | 18,766.80 |
| 0006 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -288 | CUYD | 0.10 | -28.80 | 0.10 | -28.80 | 0.10 | -28.80 |
| 0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 520 | SQYD | 73.00 | 37,960.00 | 85.00 | 44,200.00 | 94.00 | 48,880.00 |
| 0008 | 701-01-01000 | Cross Drain Pipe (24" RCP/PP) | 40 | LNFT | 135.00 | 5,400.00 | 85.00 | 3,400.00 | 150.00 | 6,000.00 |
| 0009 | 701-02-02040 | Cross Drain Pipe Arch (30" Equiv. RCPA or 36" Equiv. CMPA) | 38 | LNFT | 150.00 | 5,700.00 | 100.00 | 3,800.00 | 170.00 | 6,460.00 |
| 0010 | 701-03-01000 | Storm Drain Pipe (15" RCP/PP) | 4 | LNFT | 160.00 | 640.00 | 75.00 | 300.00 | 320.00 | 1,280.00 |
| 0011 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 4 | LNFT | 160.00 | 640.00 | 75.00 | 300.00 | 360.00 | 1,440.00 |
| 0012 | 701-15-00100 | Concrete Collar | 1 | EACH | 650.00 | 650.00 | 750.00 | 750.00 | 700.00 | 700.00 |
| 0013 | 702-03-00100 | Catch Basins (CB-01) | 2 | EACH | 3,200.00 | 6,400.00 | 2,500.00 | 5,000.00 | 3,700.00 | 7,400.00 |
| 0014 | 702-04-00150 | Adjusting Manholes w/Manhole Adjustment Rings | 7 | EACH | 1,100.00 | 7,700.00 | 1,200.00 | 8,400.00 | 500.00 | 3,500.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 3,500.00 | 3,500.00 | 2,750.00 | 2,750.00 | 25,000.00 | 25,000.00 |
| 0016 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 2.22 | MILE | 150.00 | 333.00 | 225.00 | 499.50 | 1.00 | 2.22 |
| 0017 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.491 | MILE | 725.00 | 1,080.98 | 800.00 | 1,192.80 | 1.00 | 1.49 |
| 0018 | 716-01-00100 | Mulch (Vegetative) | 0.1 | TON | 1,100.00 | 110.00 | 5,000.00 | 500.00 | 265.00 | 26.50 |
| 0019 | 717-01-00100 | Seeding | 4 | LB | 10.00 | 40.00 | 100.00 | 400.00 | 9.50 | 38.00 |
| 0020 | 718-01-00100 | Fertilizer | 60 | LB | 1.00 | 60.00 | 10.00 | 600.00 | 0.35 | 21.00 |
| 0021 | 726-01-00100 | Bedding Material | 20.7 | CUYD | 65.00 | 1,345.50 | 100.00 | 2,070.00 | 125.00 | 2,587.50 |
| 0022 | 727-01-00100 | Mobilization | 1 | LUMP | 17,725.00 | 17,725.00 | 22,000.00 | 22,000.00 | 35,000.00 | 35,000.00 |
| 0023 | 731-02-00100 | Reflectorized Raised Pavement Markers | 99 | EACH | 5.00 | 495.00 | 10.00 | 990.00 | 5.80 | 574.20 |
| 0024 | 732-01-01000 | Plastic Pavement Striping (4" Width) (Thermoplastic 90 mil) | 162 | LNFT | 1.00 | 162.00 | 5.00 | 810.00 | 0.55 | 89.10 |
| 0025 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 24 | LNFT | 6.50 | 156.00 | 25.00 | 600.00 | 5.00 | 120.00 |
| 0026 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.497 | MILE | 3,100.00 | 1,540.70 | 3,800.00 | 1,888.60 | 2,750.00 | 1,366.75 |
| 0027 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.612 | MILE | 1,000.00 | 612.00 | 2,800.00 | 1,713.60 | 920.00 | 563.04 |
| 0028 | 732-04-01040 | Plastic Pavement Legends and Symbols (Arrow - Double) | 2 | EACH | 350.00 | 700.00 | 550.00 | 1,100.00 | 250.00 | 500.00 |
| 0029 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 2 | EACH | 275.00 | 550.00 | 400.00 | 800.00 | 240.00 | 480.00 |
| 0030 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 1 | EACH | 450.00 | 450.00 | 1,200.00 | 1,200.00 | 450.00 | 450.00 |
| 0031 | 740-01-00100 | Construction Layout | 1 | LUMP | 1,000.00 | 1,000.00 | 1,000.00 | 1,000.00 | 5,000.00 | 5,000.00 |
| 0032 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 31,200 | INLF | 0.08 | 2,496.00 | 0.10 | 3,120.00 | 0.15 | 4,680.00 |
| CONTRACTOR TOTAL | 332,279.88 | 332,291.50 | 392,759.30 | |||||||