Bid Tabulations
Letting of
07/27/2011
LA DOTD Headquarters
| Lead Project: 116-03-0006 | |
| Parish: Natchitoches | |
| Routes: LA 478 | |
| Description: JCT. LA 117 - JCT. LA 120 | |
| Type Const: GRADING, DRAINAGE STRUCTURES, LIME TREATMENT, IN-PLACE CEMENT TREATED BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $2,425,729.83 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08815 | W. E. Mcdonald & Son, LLC. | $1,923,793.56 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $2,056,560.22 |
| 3 | 12487 | Diamond B Construction Co., L.L.C. | $2,129,814.14 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - W. E. Mcdonald & Son, LLC. |
- 2 - Gilchrist Construction Co. LLC |
- 3 - Diamond B Construction Co., L.L.C. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 3,000.00 | 3,000.00 | 7,000.00 | 7,000.00 | 5,000.00 | 5,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 6 | SQYD | 125.00 | 750.00 | 100.00 | 600.00 | 36.00 | 216.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 1,000 | CUYD | 5.00 | 5,000.00 | 12.50 | 12,500.00 | 14.00 | 14,000.00 |
| 0004 | 203-07-00200 | Borrow (Vehicular Measurement) (Selected Soils) | 4,000 | CUYD | 5.00 | 20,000.00 | 16.50 | 66,000.00 | 12.50 | 50,000.00 |
| 0005 | 304-05-00100 | Lime Treatment (Type E) | 725.7 | TON | 400.00 | 290,280.00 | 290.00 | 210,453.00 | 500.00 | 362,850.00 |
| 0006 | 308-01-00100 | In-Place Cement Treated Base Course (12" Thick) | 92,151 | SQYD | 5.73 | 528,025.23 | 5.20 | 479,185.20 | 4.85 | 446,932.35 |
| 0007 | 308-02-00100 | Removal of Existing Patches | 2,000 | SQYD | 15.00 | 30,000.00 | 3.00 | 6,000.00 | 15.00 | 30,000.00 |
| 0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 2,665 | CUYD | 1.00 | 2,665.00 | 45.00 | 119,925.00 | 70.00 | 186,550.00 |
| 0009 | 502-01-00100 | Superpave Asphaltic Concrete | 9,655.1 | TON | 83.00 | 801,373.30 | 88.00 | 849,648.80 | 81.00 | 782,063.10 |
| 0010 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 168.2 | TON | 150.00 | 25,230.00 | 200.00 | 33,640.00 | 145.00 | 24,389.00 |
| 0011 | 701-01-02000 | Cross Drain Pipe (24" RCP/PP or 30" CMP) | 72 | LNFT | 100.00 | 7,200.00 | 130.00 | 9,360.00 | 176.00 | 12,672.00 |
| 0012 | 701-01-02040 | Cross Drain Pipe (30" RCP/PP or 36" CMP) | 32 | LNFT | 145.00 | 4,640.00 | 160.00 | 5,120.00 | 176.00 | 5,632.00 |
| 0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,000.00 | 6,000.00 | 25,000.00 | 25,000.00 | 14,000.00 | 14,000.00 |
| 0014 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 7.78 | MILE | 400.00 | 3,112.00 | 350.00 | 2,723.00 | 165.00 | 1,283.70 |
| 0015 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 6.207 | MILE | 250.00 | 1,551.75 | 1.00 | 6.21 | 260.00 | 1,613.82 |
| 0016 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 21.306 | MILE | 300.00 | 6,391.80 | 1.00 | 21.31 | 320.00 | 6,817.92 |
| 0017 | 716-01-00100 | Mulch (Vegetative) | 10.8 | TON | 500.00 | 5,400.00 | 550.00 | 5,940.00 | 525.00 | 5,670.00 |
| 0018 | 717-01-00100 | Seeding | 162 | LB | 7.00 | 1,134.00 | 7.80 | 1,263.60 | 7.50 | 1,215.00 |
| 0019 | 718-01-00100 | Fertilizer | 5,400 | LB | 0.45 | 2,430.00 | 0.50 | 2,700.00 | 0.46 | 2,484.00 |
| 0020 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 3,000.00 | 3,000.00 | 5,000.00 | 5,000.00 | 10,000.00 | 10,000.00 |
| 0021 | 726-01-00100 | Bedding Material | 28.1 | CUYD | 100.00 | 2,810.00 | 150.00 | 4,215.00 | 83.00 | 2,332.30 |
| 0022 | 727-01-00100 | Mobilization | 1 | LUMP | 100,000.00 | 100,000.00 | 120,000.00 | 120,000.00 | 81,000.00 | 81,000.00 |
| 0023 | 729-16-00300 | Object Marker Assembly (Type 3) | 6 | EACH | 125.00 | 750.00 | 115.00 | 690.00 | 130.00 | 780.00 |
| 0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,027 | EACH | 5.00 | 5,135.00 | 5.50 | 5,648.50 | 5.25 | 5,391.75 |
| 0025 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 30 | LNFT | 6.00 | 180.00 | 22.00 | 660.00 | 6.50 | 195.00 |
| 0026 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 21.306 | MILE | 2,525.00 | 53,797.65 | 3,100.00 | 66,048.60 | 2,700.00 | 57,526.20 |
| 0027 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 6.207 | MILE | 975.00 | 6,051.83 | 1,000.00 | 6,207.00 | 1,000.00 | 6,207.00 |
| 0028 | 735-01-00100 | Mailboxes | 11 | EACH | 1.00 | 11.00 | 10.00 | 110.00 | 1.00 | 11.00 |
| 0029 | 735-02-00100 | Mailbox Supports (Single) | 5 | EACH | 155.00 | 775.00 | 155.00 | 775.00 | 160.00 | 800.00 |
| 0030 | 735-03-00100 | Mailbox Supports (Double) | 2 | EACH | 195.00 | 390.00 | 195.00 | 390.00 | 200.00 | 400.00 |
| 0031 | 735-04-00100 | Mailbox Supports (Multiple) | 1 | EACH | 350.00 | 350.00 | 300.00 | 300.00 | 350.00 | 350.00 |
| 0032 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,500.00 | 4,500.00 | 7,000.00 | 7,000.00 | 9,200.00 | 9,200.00 |
| 0033 | NS-200-00020 | Cleaning Existing Ditches | 100 | LNFT | 10.00 | 1,000.00 | 20.00 | 2,000.00 | 12.00 | 1,200.00 |
| 0034 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 43 | INLF | 20.00 | 860.00 | 10.00 | 430.00 | 24.00 | 1,032.00 |
| CONTRACTOR TOTAL | 1,923,793.56 | 2,056,560.22 | 2,129,814.14 | |||||||