Bid Tabulations
Letting of
08/31/2011
LA DOTD Headquarters
| Lead Project: 112-07-0015 | |
| Parish: Red River | |
| Routes: LA 174 | |
| Description: BLACK BAYOU BRIDGE ON LA 174 | |
| Type Const: GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC PAVEMENT, LIME TREATMENT, CLASS II BASE COURSE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, REINFORCED CONCRETE BOX CULVERT AND RELATED WORK. | |
| Estimated Construction Cost: $873,703.48 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 48925 | David V. Temple | $668,973.92 |
| 2 | 49239 | W L Bass Construction Inc. | $713,361.90 |
| 3 | 28218 | F. J. Burnell, Inc. | $811,448.40 |
| 4 | 44289 | Jeff Mercer LLC | $821,930.75 |
| 5 | 12135 | Blount Bros. Construction, Inc. | $868,183.95 |
| 6 | 01012 | Cecil D. Gassiott, LLC | $880,608.60 |
| 7 | 51413 | Iverstine & Campbell LLC | $882,514.00 |
| 8 | 12312 | Gilchrist Construction Co. LLC | $924,120.16 |
| 9 | 18546 | C W & W Contractors, Inc. | $1,016,410.00 |
| 10 | 09090 | Guinn Brothers, LLC. | $1,070,927.60 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - David V. Temple |
- 2 - W L Bass Construction Inc. |
- 3 - F. J. Burnell, Inc. |
- 4 - Jeff Mercer LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 6,039.28 | 6,039.28 | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | 15,000.00 | 15,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge STA. 110+97.29 39' X 24' CONCRETE PRECAST SLAB UNITS | 1 | EACH | 4,290.00 | 4,290.00 | 5,000.00 | 5,000.00 | 22,000.00 | 22,000.00 | 10,000.00 | 10,000.00 |
| 0003 | 202-02-12000 | Removal of Fence | 554 | LNFT | 1.00 | 554.00 | 1.00 | 554.00 | 3.00 | 1,662.00 | 2.50 | 1,385.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 276 | LNFT | 3.00 | 828.00 | 5.00 | 1,380.00 | 10.00 | 2,760.00 | 5.00 | 1,380.00 |
| 0005 | 202-02-32120 | Removal of Pipe (Side Drain) 15" X 22' CMP | 22 | LNFT | 6.82 | 150.04 | 10.00 | 220.00 | 20.00 | 440.00 | 8.00 | 176.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 601 | SQYD | 10.00 | 6,010.00 | 5.00 | 3,005.00 | 10.00 | 6,010.00 | 11.00 | 6,611.00 |
| 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 26,876.00 | 26,876.00 | 25,000.00 | 25,000.00 | 21,000.00 | 21,000.00 | 30,000.00 | 30,000.00 |
| 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 10 | EACH | 110.00 | 1,100.00 | 0.00 | 0.00 | 100.00 | 1,000.00 | 100.00 | 1,000.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 946 | LNFT | 2.25 | 2,128.50 | 0.00 | 0.00 | 2.00 | 1,892.00 | 1.00 | 946.00 |
| 0010 | 302-02-04121 | Class II Base Course (8 1/2" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 577.8 | SQYD | 20.00 | 11,556.00 | 23.00 | 13,289.40 | 18.00 | 10,400.40 | 45.00 | 26,001.00 |
| 0011 | 304-05-00100 | Lime Treatment (Type E) | 8.19 | TON | 450.00 | 3,685.50 | 0.00 | 0.00 | 400.00 | 3,276.00 | 350.00 | 2,866.50 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 24.6 | CUYD | 59.85 | 1,472.31 | 80.00 | 1,968.00 | 80.00 | 1,968.00 | 75.00 | 1,845.00 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 50.44 | 5,044.00 | 0.00 | 0.00 | 40.00 | 4,000.00 | 45.00 | 4,500.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 124.3 | TON | 215.00 | 26,724.50 | 135.00 | 16,780.50 | 150.00 | 18,645.00 | 200.00 | 24,860.00 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 5.9 | TON | 265.00 | 1,563.50 | 135.00 | 796.50 | 300.00 | 1,770.00 | 250.00 | 1,475.00 |
| 0016 | 509-01-00100 | Cold Planing Asphaltic Pavement | 256 | SQYD | 3.75 | 960.00 | 42.00 | 10,752.00 | 15.00 | 3,840.00 | 1.00 | 256.00 |
| 0017 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -8 | CUYD | 1.00 | -8.00 | 25.00 | -200.00 | 1.00 | -8.00 | 0.00 | 0.00 |
| 0018 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 148 | LNFT | 40.25 | 5,957.00 | 50.00 | 7,400.00 | 50.00 | 7,400.00 | 100.00 | 14,800.00 |
| 0019 | 702-06-01000 | Side Drain End Treatment (1 Barrel, 18" RCP/PP or 24" CMP) | 3 | EACH | 685.00 | 2,055.00 | 1,300.00 | 3,900.00 | 1,200.00 | 3,600.00 | 2,500.00 | 7,500.00 |
| 0020 | 705-01-00100 | Barbed Wire Fence | 170 | LNFT | 8.75 | 1,487.50 | 7.00 | 1,190.00 | 7.00 | 1,190.00 | 3.00 | 510.00 |
| 0021 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 870 | LNFT | 9.50 | 8,265.00 | 8.00 | 6,960.00 | 10.00 | 8,700.00 | 3.00 | 2,610.00 |
| 0022 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 150.00 | 1,200.00 | 110.00 | 880.00 | 500.00 | 4,000.00 | 180.00 | 1,440.00 |
| 0023 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 150.00 | 1,200.00 | 110.00 | 880.00 | 500.00 | 4,000.00 | 105.00 | 840.00 |
| 0024 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 391 | SQYD | 62.00 | 24,242.00 | 66.00 | 25,806.00 | 75.00 | 29,325.00 | 75.00 | 29,325.00 |
| 0025 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 6,500.00 | 6,500.00 | 7,500.00 | 7,500.00 | 10,000.00 | 10,000.00 | 8,500.00 | 8,500.00 |
| 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.35 | MILE | 975.00 | 341.25 | 750.00 | 262.50 | 7,000.00 | 2,450.00 | 765.00 | 267.75 |
| 0027 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 8 | EACH | 77.00 | 616.00 | 5.00 | 40.00 | 50.00 | 400.00 | 5.50 | 44.00 |
| 0028 | 716-01-00100 | Mulch (Vegetative) | 3.5 | TON | 750.00 | 2,625.00 | 850.00 | 2,975.00 | 600.00 | 2,100.00 | 1,050.00 | 3,675.00 |
| 0029 | 717-01-00100 | Seeding | 53 | LB | 12.50 | 662.50 | 10.00 | 530.00 | 12.00 | 636.00 | 5.00 | 265.00 |
| 0030 | 718-01-00100 | Fertilizer | 1,770 | LB | 0.55 | 973.50 | 1.00 | 1,770.00 | 1.00 | 1,770.00 | 1.00 | 1,770.00 |
| 0031 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 58 | SQYD | 1.50 | 87.00 | 1.00 | 58.00 | 3.00 | 174.00 | 2.00 | 116.00 |
| 0032 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 163 | SQYD | 1.85 | 301.55 | 2.00 | 326.00 | 3.00 | 489.00 | 2.00 | 326.00 |
| 0033 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 234 | SQYD | 2.50 | 585.00 | 2.00 | 468.00 | 5.00 | 1,170.00 | 2.00 | 468.00 |
| 0034 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 7,500.00 | 7,500.00 | 5,000.00 | 5,000.00 | 500.00 | 500.00 | 500.00 | 500.00 |
| 0035 | 725-01-00100 | Temporary Detour Roads | 2,769.4 | SQYD | 73.93 | 204,741.74 | 80.00 | 221,552.00 | 75.00 | 207,705.00 | 65.00 | 180,011.00 |
| 0036 | 726-01-00100 | Bedding Material | 462.3 | CUYD | 65.00 | 30,049.50 | 0.00 | 0.00 | 90.00 | 41,607.00 | 125.00 | 57,787.50 |
| 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 53,000.00 | 53,000.00 | 67,000.00 | 67,000.00 | 60,000.00 | 60,000.00 | 60,000.00 | 60,000.00 |
| 0038 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 85.00 | 340.00 | 75.00 | 300.00 | 100.00 | 400.00 | 250.00 | 1,000.00 |
| 0039 | 731-02-00100 | Reflectorized Raised Pavement Markers | 16 | EACH | 77.00 | 1,232.00 | 25.00 | 400.00 | 50.00 | 800.00 | 26.00 | 416.00 |
| 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.275 | MILE | 7,500.00 | 2,062.50 | 12,000.00 | 3,300.00 | 10,000.00 | 2,750.00 | 12,500.00 | 3,437.50 |
| 0041 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.111 | MILE | 5,000.00 | 555.00 | 8,000.00 | 888.00 | 10,000.00 | 1,110.00 | 8,500.00 | 943.50 |
| 0042 | 732-05-00100 | Removal of Existing Markings | 0.162 | MILE | 5,000.00 | 810.00 | 6,000.00 | 972.00 | 10,000.00 | 1,620.00 | 8,500.00 | 1,377.00 |
| 0043 | 740-01-00100 | Construction Layout | 1 | LUMP | 5,500.00 | 5,500.00 | 7,000.00 | 7,000.00 | 5,000.00 | 5,000.00 | 6,600.00 | 6,600.00 |
| 0044 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 38.92 | CUYD | 1,130.00 | 43,979.60 | 1,150.00 | 44,758.00 | 1,000.00 | 38,920.00 | 1,050.00 | 40,866.00 |
| 0046 | 806-01-00100 | Deformed Reinforcing Steel | 3,257 | LB | 0.85 | 2,768.45 | 1.00 | 3,257.00 | 1.00 | 3,257.00 | 2.00 | 6,514.00 |
| 0047 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 144 | INLF | 5.30 | 763.20 | 1.00 | 144.00 | 5.00 | 720.00 | 5.00 | 720.00 |
| 0048 | 805-12-04000 | Reinforced Concrete Box Culverts (7' x 7') | 360 | LNFT | 435.00 | 156,600.00 | 565.00 | 203,400.00 | 650.00 | 234,000.00 | 700.00 | 252,000.00 |
| 0049 | 202-02-00010 | Removal of (Abandoned Oil Lines) | 6 | EACH | 500.00 | 3,000.00 | 150.00 | 900.00 | 2,500.00 | 15,000.00 | 1,500.00 | 9,000.00 |
| CONTRACTOR TOTAL | 668,973.92 | 713,361.90 | 811,448.40 | 821,930.75 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 5 - Blount Bros. Construction, Inc. |
- 6 - Cecil D. Gassiott, LLC |
- 7 - Iverstine & Campbell LLC |
- 8 - Gilchrist Construction Co. LLC |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 20,000.00 | 20,000.00 | 5,000.00 | 5,000.00 | 7,750.00 | 7,750.00 | 15,000.00 | 15,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge STA. 110+97.29 39' X 24' CONCRETE PRECAST SLAB UNITS | 1 | EACH | 25,000.00 | 25,000.00 | 10,000.00 | 10,000.00 | 13,625.00 | 13,625.00 | 10,000.00 | 10,000.00 |
| 0003 | 202-02-12000 | Removal of Fence | 554 | LNFT | 7.00 | 3,878.00 | 2.00 | 1,108.00 | 3.75 | 2,077.50 | 1.50 | 831.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 276 | LNFT | 7.00 | 1,932.00 | 10.00 | 2,760.00 | 17.50 | 4,830.00 | 9.50 | 2,622.00 |
| 0005 | 202-02-32120 | Removal of Pipe (Side Drain) 15" X 22' CMP | 22 | LNFT | 20.00 | 440.00 | 10.00 | 220.00 | 6.25 | 137.50 | 20.00 | 440.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 601 | SQYD | 10.00 | 6,010.00 | 3.50 | 2,103.50 | 13.75 | 8,263.75 | 8.00 | 4,808.00 |
| 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 3,000.00 | 3,000.00 | 34,000.00 | 34,000.00 | 31,625.00 | 31,625.00 | 40,000.00 | 40,000.00 |
| 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 10 | EACH | 200.00 | 2,000.00 | 120.00 | 1,200.00 | 50.00 | 500.00 | 275.00 | 2,750.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 946 | LNFT | 3.00 | 2,838.00 | 2.00 | 1,892.00 | 2.50 | 2,365.00 | 1.75 | 1,655.50 |
| 0010 | 302-02-04121 | Class II Base Course (8 1/2" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 577.8 | SQYD | 25.00 | 14,445.00 | 25.00 | 14,445.00 | 25.00 | 14,445.00 | 35.50 | 20,511.90 |
| 0011 | 304-05-00100 | Lime Treatment (Type E) | 8.19 | TON | 305.00 | 2,497.95 | 300.00 | 2,457.00 | 558.00 | 4,570.02 | 705.00 | 5,773.95 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 24.6 | CUYD | 80.00 | 1,968.00 | 85.00 | 2,091.00 | 55.00 | 1,353.00 | 155.00 | 3,813.00 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 80.00 | 8,000.00 | 50.00 | 5,000.00 | 15.00 | 1,500.00 | 60.00 | 6,000.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 124.3 | TON | 190.00 | 23,617.00 | 220.00 | 27,346.00 | 300.00 | 37,290.00 | 285.00 | 35,425.50 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 5.9 | TON | 200.00 | 1,180.00 | 280.00 | 1,652.00 | 331.20 | 1,954.08 | 500.00 | 2,950.00 |
| 0016 | 509-01-00100 | Cold Planing Asphaltic Pavement | 256 | SQYD | 20.00 | 5,120.00 | 13.00 | 3,328.00 | 47.50 | 12,160.00 | 27.00 | 6,912.00 |
| 0017 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -8 | CUYD | 1.00 | -8.00 | 1.00 | -8.00 | 1.00 | -8.00 | 0.01 | -0.08 |
| 0018 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 148 | LNFT | 40.00 | 5,920.00 | 67.00 | 9,916.00 | 45.60 | 6,748.80 | 43.00 | 6,364.00 |
| 0019 | 702-06-01000 | Side Drain End Treatment (1 Barrel, 18" RCP/PP or 24" CMP) | 3 | EACH | 2,500.00 | 7,500.00 | 1,700.00 | 5,100.00 | 2,500.00 | 7,500.00 | 1,730.00 | 5,190.00 |
| 0020 | 705-01-00100 | Barbed Wire Fence | 170 | LNFT | 11.00 | 1,870.00 | 10.00 | 1,700.00 | 8.75 | 1,487.50 | 9.50 | 1,615.00 |
| 0021 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 870 | LNFT | 11.00 | 9,570.00 | 10.00 | 8,700.00 | 18.75 | 16,312.50 | 10.00 | 8,700.00 |
| 0022 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 250.00 | 2,000.00 | 160.00 | 1,280.00 | 187.50 | 1,500.00 | 240.00 | 1,920.00 |
| 0023 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 200.00 | 1,600.00 | 60.00 | 480.00 | 250.00 | 2,000.00 | 240.00 | 1,920.00 |
| 0024 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 391 | SQYD | 80.00 | 31,280.00 | 45.00 | 17,595.00 | 65.00 | 25,415.00 | 51.00 | 19,941.00 |
| 0025 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 15,000.00 | 15,000.00 | 4,500.00 | 4,500.00 | 9,375.00 | 9,375.00 | 6,500.00 | 6,500.00 |
| 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.35 | MILE | 1,000.00 | 350.00 | 700.00 | 245.00 | 625.00 | 218.75 | 600.00 | 210.00 |
| 0027 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 8 | EACH | 10.00 | 80.00 | 25.00 | 200.00 | 1.25 | 10.00 | 5.50 | 44.00 |
| 0028 | 716-01-00100 | Mulch (Vegetative) | 3.5 | TON | 1,000.00 | 3,500.00 | 800.00 | 2,800.00 | 1,125.00 | 3,937.50 | 800.00 | 2,800.00 |
| 0029 | 717-01-00100 | Seeding | 53 | LB | 20.00 | 1,060.00 | 15.00 | 795.00 | 12.50 | 662.50 | 13.00 | 689.00 |
| 0030 | 718-01-00100 | Fertilizer | 1,770 | LB | 1.00 | 1,770.00 | 0.60 | 1,062.00 | 2.50 | 4,425.00 | 0.60 | 1,062.00 |
| 0031 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 58 | SQYD | 3.00 | 174.00 | 1.60 | 92.80 | 2.50 | 145.00 | 1.65 | 95.70 |
| 0032 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 163 | SQYD | 3.00 | 489.00 | 1.90 | 309.70 | 2.50 | 407.50 | 2.00 | 326.00 |
| 0033 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 234 | SQYD | 2.00 | 468.00 | 2.75 | 643.50 | 2.50 | 585.00 | 2.75 | 643.50 |
| 0034 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 20,000.00 | 20,000.00 | 12,000.00 | 12,000.00 | 6,250.00 | 6,250.00 | 2,300.00 | 2,300.00 |
| 0035 | 725-01-00100 | Temporary Detour Roads | 2,769.4 | SQYD | 85.00 | 235,399.00 | 134.00 | 371,099.60 | 101.90 | 282,201.86 | 92.00 | 254,784.80 |
| 0036 | 726-01-00100 | Bedding Material | 462.3 | CUYD | 80.00 | 36,984.00 | 105.00 | 48,541.50 | 71.90 | 33,239.37 | 117.00 | 54,089.10 |
| 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 30,000.00 | 30,000.00 | 45,000.00 | 45,000.00 | 28,750.00 | 28,750.00 | 100,000.00 | 100,000.00 |
| 0038 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 150.00 | 600.00 | 100.00 | 400.00 | 100.00 | 400.00 | 78.00 | 312.00 |
| 0039 | 731-02-00100 | Reflectorized Raised Pavement Markers | 16 | EACH | 10.00 | 160.00 | 80.00 | 1,280.00 | 6.25 | 100.00 | 5.50 | 88.00 |
| 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.275 | MILE | 4,000.00 | 1,100.00 | 8,000.00 | 2,200.00 | 25,000.00 | 6,875.00 | 3,300.00 | 907.50 |
| 0041 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.111 | MILE | 2,000.00 | 222.00 | 5,000.00 | 555.00 | 1,250.00 | 138.75 | 940.00 | 104.34 |
| 0042 | 732-05-00100 | Removal of Existing Markings | 0.162 | MILE | 8,000.00 | 1,296.00 | 5,000.00 | 810.00 | 25,000.00 | 4,050.00 | 5,500.00 | 891.00 |
| 0043 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 5,500.00 | 5,500.00 | 9,375.00 | 9,375.00 | 10,000.00 | 10,000.00 |
| 0044 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 38.92 | CUYD | 1,000.00 | 38,920.00 | 1,000.00 | 38,920.00 | 1,238.00 | 48,182.96 | 1,050.00 | 40,866.00 |
| 0046 | 806-01-00100 | Deformed Reinforcing Steel | 3,257 | LB | 2.00 | 6,514.00 | 1.00 | 3,257.00 | 1.88 | 6,123.16 | 0.85 | 2,768.45 |
| 0047 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 144 | INLF | 10.00 | 1,440.00 | 3.00 | 432.00 | 1.25 | 180.00 | 9.00 | 1,296.00 |
| 0048 | 805-12-04000 | Reinforced Concrete Box Culverts (7' x 7') | 360 | LNFT | 700.00 | 252,000.00 | 460.00 | 165,600.00 | 593.00 | 213,480.00 | 620.00 | 223,200.00 |
| 0049 | 202-02-00010 | Removal of (Abandoned Oil Lines) | 6 | EACH | 4,000.00 | 24,000.00 | 2,500.00 | 15,000.00 | 3,000.00 | 18,000.00 | 2,500.00 | 15,000.00 |
| CONTRACTOR TOTAL | 868,183.95 | 880,608.60 | 882,514.00 | 924,120.16 | ||||||||
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 9 - C W & W Contractors, Inc. |
- 10 - Guinn Brothers, LLC. |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 30,000.00 | 30,000.00 | 15,000.00 | 15,000.00 |
| 0002 | 202-02-04000 | Removal of Bridge STA. 110+97.29 39' X 24' CONCRETE PRECAST SLAB UNITS | 1 | EACH | 18,000.00 | 18,000.00 | 12,500.00 | 12,500.00 |
| 0003 | 202-02-12000 | Removal of Fence | 554 | LNFT | 2.00 | 1,108.00 | 5.00 | 2,770.00 |
| 0004 | 202-02-14500 | Removal of Guard Rail | 276 | LNFT | 7.00 | 1,932.00 | 3.00 | 828.00 |
| 0005 | 202-02-32120 | Removal of Pipe (Side Drain) 15" X 22' CMP | 22 | LNFT | 10.00 | 220.00 | 10.00 | 220.00 |
| 0006 | 202-02-38500 | Removal of Surfacing and Stablized Base | 601 | SQYD | 7.00 | 4,207.00 | 6.00 | 3,606.00 |
| 0007 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 61,000.00 | 61,000.00 | 35,000.00 | 35,000.00 |
| 0008 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 10 | EACH | 150.00 | 1,500.00 | 100.00 | 1,000.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 946 | LNFT | 3.00 | 2,838.00 | 3.00 | 2,838.00 |
| 0010 | 302-02-04121 | Class II Base Course (8 1/2" Thick) (Stone or Recycled Portland Cement Concrete, or Blended Calcium Sulfate) | 577.8 | SQYD | 55.00 | 31,779.00 | 22.00 | 12,711.60 |
| 0011 | 304-05-00100 | Lime Treatment (Type E) | 8.19 | TON | 200.00 | 1,638.00 | 1,000.00 | 8,190.00 |
| 0012 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 24.6 | CUYD | 60.00 | 1,476.00 | 100.00 | 2,460.00 |
| 0013 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 30.00 | 3,000.00 | 50.00 | 5,000.00 |
| 0014 | 502-01-00100 | Superpave Asphaltic Concrete | 124.3 | TON | 180.00 | 22,374.00 | 250.00 | 31,075.00 |
| 0015 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 5.9 | TON | 185.00 | 1,091.50 | 500.00 | 2,950.00 |
| 0016 | 509-01-00100 | Cold Planing Asphaltic Pavement | 256 | SQYD | 40.00 | 10,240.00 | 40.00 | 10,240.00 |
| 0017 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -8 | CUYD | 1.00 | -8.00 | 0.00 | 0.00 |
| 0018 | 701-05-01040 | Side Drain Pipe (18" RCP/PP/CMP) | 148 | LNFT | 45.00 | 6,660.00 | 60.00 | 8,880.00 |
| 0019 | 702-06-01000 | Side Drain End Treatment (1 Barrel, 18" RCP/PP or 24" CMP) | 3 | EACH | 1,000.00 | 3,000.00 | 1,600.00 | 4,800.00 |
| 0020 | 705-01-00100 | Barbed Wire Fence | 170 | LNFT | 10.00 | 1,700.00 | 10.00 | 1,700.00 |
| 0021 | 705-02-00100 | Combination Mesh & Barbed Wire Fence | 870 | LNFT | 12.00 | 10,440.00 | 15.00 | 13,050.00 |
| 0022 | 708-01-00100 | Right-of-Way Monument | 8 | EACH | 50.00 | 400.00 | 300.00 | 2,400.00 |
| 0023 | 708-02-00100 | Right-of-Way Monument Witness Post | 8 | EACH | 150.00 | 1,200.00 | 300.00 | 2,400.00 |
| 0024 | 711-01-03000 | Riprap (30 lb, 14" Thick) | 391 | SQYD | 45.00 | 17,595.00 | 80.00 | 31,280.00 |
| 0025 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,000.00 | 7,000.00 | 15,000.00 | 15,000.00 |
| 0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.35 | MILE | 1,750.00 | 612.50 | 1,000.00 | 350.00 |
| 0027 | 713-06-00100 | Temporary Reflectorized Raised Pavement Markers | 8 | EACH | 5.00 | 40.00 | 100.00 | 800.00 |
| 0028 | 716-01-00100 | Mulch (Vegetative) | 3.5 | TON | 1,500.00 | 5,250.00 | 1,000.00 | 3,500.00 |
| 0029 | 717-01-00100 | Seeding | 53 | LB | 10.00 | 530.00 | 25.00 | 1,325.00 |
| 0030 | 718-01-00100 | Fertilizer | 1,770 | LB | 1.00 | 1,770.00 | 1.00 | 1,770.00 |
| 0031 | 720-01-01000 | Erosion Control System (Slope Protection) (Type A) | 58 | SQYD | 4.00 | 232.00 | 10.00 | 580.00 |
| 0032 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 163 | SQYD | 4.00 | 652.00 | 6.00 | 978.00 |
| 0033 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 234 | SQYD | 4.00 | 936.00 | 6.00 | 1,404.00 |
| 0034 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 2,500.00 | 2,500.00 | 15,000.00 | 15,000.00 |
| 0035 | 725-01-00100 | Temporary Detour Roads | 2,769.4 | SQYD | 125.00 | 346,175.00 | 130.00 | 360,022.00 |
| 0036 | 726-01-00100 | Bedding Material | 462.3 | CUYD | 60.00 | 27,738.00 | 85.00 | 39,295.50 |
| 0037 | 727-01-00100 | Mobilization | 1 | LUMP | 100,000.00 | 100,000.00 | 75,000.00 | 75,000.00 |
| 0038 | 729-16-00300 | Object Marker Assembly (Type 3) | 4 | EACH | 85.00 | 340.00 | 100.00 | 400.00 |
| 0039 | 731-02-00100 | Reflectorized Raised Pavement Markers | 16 | EACH | 60.00 | 960.00 | 100.00 | 1,600.00 |
| 0040 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.275 | MILE | 6,000.00 | 1,650.00 | 8,000.00 | 2,200.00 |
| 0041 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.111 | MILE | 4,000.00 | 444.00 | 6,500.00 | 721.50 |
| 0042 | 732-05-00100 | Removal of Existing Markings | 0.162 | MILE | 4,000.00 | 648.00 | 6,000.00 | 972.00 |
| 0043 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 9,000.00 | 9,000.00 |
| 0044 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 38.92 | CUYD | 1,300.00 | 50,596.00 | 1,500.00 | 58,380.00 |
| 0046 | 806-01-00100 | Deformed Reinforcing Steel | 3,257 | LB | 2.00 | 6,514.00 | 3.00 | 9,771.00 |
| 0047 | NS-500-00340 | Saw Cutting Asphaltic Concrete Pavement | 144 | INLF | 3.00 | 432.00 | 15.00 | 2,160.00 |
| 0048 | 805-12-04000 | Reinforced Concrete Box Culverts (7' x 7') | 360 | LNFT | 575.00 | 207,000.00 | 580.00 | 208,800.00 |
| 0049 | 202-02-00010 | Removal of (Abandoned Oil Lines) | 6 | EACH | 1,000.00 | 6,000.00 | 8,500.00 | 51,000.00 |
| CONTRACTOR TOTAL | 1,016,410.00 | 1,070,927.60 | ||||||