Bid Tabulations
Letting of
09/22/2010
LA DOTD Headquarters
| Lead Project: 106-01-0010-R1 | |
| Parish: Desoto | |
| Routes: | |
| Description: LA 175 TO LA 346 | |
| Type Const: GRADING, COLD PLANING ASPHALTIC CONCRETE PAVEMENT, PAVEMENT PATCHING, DRAINAGE STRUCTURES, SUPERPAVE ASPHALTIC CONCRETE OVERLAY, AND RELATED WORK | |
| Estimated Construction Cost: $2,389,818.72 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $2,454,355.12 |
| 2 | 36374 | Best-Yet Builders, Llc | $2,623,007.40 |
| 3 | 17464 | Benton & Brown, LLC. | $3,325,823.52 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
- 2 - Best-Yet Builders, Llc |
- 3 - Benton & Brown, LLC. |
|||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-06040 | Removal of Concrete Box Headwall (Station 306+64, 3 Barrel 10' x 10') | 2 | EACH | 3,000.00 | 6,000.00 | 750.00 | 1,500.00 | 1,000.00 | 2,000.00 |
| 0002 | 202-02-06100 | Removal of Concrete Walks and Drives | 81 | SQYD | 15.00 | 1,215.00 | 15.00 | 1,215.00 | 25.00 | 2,025.00 |
| 0003 | 202-02-32100 | Removal of Pipe (Cross Drain) Stations 80+55, 125+65, 201+65, 253+40, 300+77, 316+42, and 345+55 | 40 | LNFT | 150.00 | 6,000.00 | 50.00 | 2,000.00 | 15.00 | 600.00 |
| 0004 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 75,000.00 | 75,000.00 |
| 0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 5,000 | CUYD | 13.25 | 66,250.00 | 10.00 | 50,000.00 | 25.00 | 125,000.00 |
| 0006 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 200 | CUYD | 10.00 | 2,000.00 | 50.00 | 10,000.00 | 75.00 | 15,000.00 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 22,619.8 | TON | 80.00 | 1,809,584.00 | 90.00 | 2,035,782.00 | 100.00 | 2,261,980.00 |
| 0008 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 450 | TON | 60.00 | 27,000.00 | 95.00 | 42,750.00 | 140.00 | 63,000.00 |
| 0009 | 509-01-00100 | Cold Planing Asphaltic Pavement | 1,266 | SQYD | 4.00 | 5,064.00 | 4.00 | 5,064.00 | 8.50 | 10,761.00 |
| 0010 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -26 | CUYD | 1.00 | -26.00 | 1.00 | -26.00 | 1.00 | -26.00 |
| 0011 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 500 | SQYD | 70.00 | 35,000.00 | 99.00 | 49,500.00 | 100.00 | 50,000.00 |
| 0012 | 701-08-00100 | Relaying Pipe | 20 | LNFT | 150.00 | 3,000.00 | 50.00 | 1,000.00 | 160.00 | 3,200.00 |
| 0013 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 94 | LNFT | 200.00 | 18,800.00 | 57.50 | 5,405.00 | 220.00 | 20,680.00 |
| 0014 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 6 | LNFT | 225.00 | 1,350.00 | 80.00 | 480.00 | 300.00 | 1,800.00 |
| 0015 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 14 | LNFT | 250.00 | 3,500.00 | 112.50 | 1,575.00 | 310.00 | 4,340.00 |
| 0016 | 701-10-01140 | Reinforced Concrete Pipe (Extension) (48") | 8 | LNFT | 300.00 | 2,400.00 | 193.75 | 1,550.00 | 325.00 | 2,600.00 |
| 0017 | 701-15-00100 | Concrete Collar | 12 | EACH | 1,250.00 | 15,000.00 | 1,000.00 | 12,000.00 | 1,000.00 | 12,000.00 |
| 0018 | 712-04-00100 | Flexible Revetment | 200 | SQYD | 80.00 | 16,000.00 | 100.00 | 20,000.00 | 92.00 | 18,400.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 67,500.00 | 67,500.00 | 10,000.00 | 10,000.00 | 80,000.00 | 80,000.00 |
| 0020 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 14.608 | MILE | 325.00 | 4,747.60 | 800.00 | 11,686.40 | 250.00 | 3,652.00 |
| 0021 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 43.824 | MILE | 1.00 | 43.82 | 300.00 | 13,147.20 | 1.00 | 43.82 |
| 0022 | 716-01-00100 | Mulch (Vegetative) | 36 | TON | 600.00 | 21,600.00 | 800.00 | 28,800.00 | 1,700.00 | 61,200.00 |
| 0023 | 717-01-00100 | Seeding | 707 | LB | 10.00 | 7,070.00 | 7.25 | 5,125.75 | 18.00 | 12,726.00 |
| 0024 | 718-01-00100 | Fertilizer | 17,673 | LB | 0.50 | 8,836.50 | 0.45 | 7,952.85 | 0.50 | 8,836.50 |
| 0025 | 726-01-00100 | Bedding Material | 4.2 | CUYD | 100.00 | 420.00 | 200.00 | 840.00 | 315.00 | 1,323.00 |
| 0026 | 727-01-00100 | Mobilization | 1 | LUMP | 67,500.00 | 67,500.00 | 100,000.00 | 100,000.00 | 80,000.00 | 80,000.00 |
| 0027 | 729-16-00200 | Object Marker Assembly (Type 2) | 13 | EACH | 75.00 | 975.00 | 60.00 | 780.00 | 80.00 | 1,040.00 |
| 0028 | 731-02-00100 | Reflectorized Raised Pavement Markers | 965 | EACH | 5.50 | 5,307.50 | 5.50 | 5,307.50 | 5.50 | 5,307.50 |
| 0029 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 247 | LNFT | 3.00 | 741.00 | 3.00 | 741.00 | 3.00 | 741.00 |
| 0030 | 732-01-02060 | Plastic Pavement Striping (12" Width) (Thermoplastic 125 mil) | 135 | LNFT | 4.50 | 607.50 | 4.50 | 607.50 | 4.50 | 607.50 |
| 0031 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 44 | LNFT | 9.00 | 396.00 | 9.00 | 396.00 | 9.00 | 396.00 |
| 0032 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 29.216 | MILE | 2,200.00 | 64,275.20 | 2,200.00 | 64,275.20 | 2,200.00 | 64,275.20 |
| 0033 | 735-01-00100 | Mailboxes | 25 | EACH | 1.00 | 25.00 | 50.00 | 1,250.00 | 11.00 | 275.00 |
| 0034 | 735-02-00100 | Mailbox Supports (Single) | 25 | EACH | 137.00 | 3,425.00 | 75.00 | 1,875.00 | 115.00 | 2,875.00 |
| 0035 | 740-01-00100 | Construction Layout | 1 | LUMP | 15,000.00 | 15,000.00 | 20,000.00 | 20,000.00 | 40,000.00 | 40,000.00 |
| 0036 | 805-01-00300 | Class A Concrete (Box Culvert Headwalls) | 64.36 | CUYD | 1,000.00 | 64,360.00 | 400.00 | 25,744.00 | 1,600.00 | 102,976.00 |
| 0037 | 805-12-07000 | Reinforced Concrete Box Culverts (10' x 10') | 42 | LNFT | 1,500.00 | 63,000.00 | 1,000.00 | 42,000.00 | 3,000.00 | 126,000.00 |
| 0038 | 806-01-00100 | Deformed Reinforcing Steel | 5,828 | LB | 3.00 | 17,484.00 | 1.00 | 5,828.00 | 1.25 | 7,285.00 |
| 0039 | NS-500-00280 | Surface Preparation | 1 | LUMP | 10,000.00 | 10,000.00 | 12,500.00 | 12,500.00 | 55,000.00 | 55,000.00 |
| 0040 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 1,452 | INLF | 2.00 | 2,904.00 | 3.00 | 4,356.00 | 2.00 | 2,904.00 |
| CONTRACTOR TOTAL | 2,454,355.12 | 2,623,007.40 | 3,325,823.52 | |||||||