Bid Tabulations
Letting of
07/28/2010
LA DOTD Headquarters
| Lead Project: 094-01-0045 | |
| Parish: Caddo | |
| Routes: LA 173 | |
| Description: LA 173 IMPROVEMENTS | |
| Type Const: GRADING, CLASS II BASE COURSE, COLD PLANING ASPHALTIC CONCRETE, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $721,215.09 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 36374 | Best-Yet Builders, LLC | $403,666.56 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Best-Yet Builders, LLC |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-06100 | Removal of Concrete Walks and Drives | 55 | SQYD | 10.00 | 550.00 |
| 0002 | 202-02-06140 | Removal of Curbs (Concrete) | 600 | LNFT | 10.00 | 6,000.00 |
| 0003 | 202-02-26300 | Removal of Median / Island | 204 | SQYD | 10.00 | 2,040.00 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 2,073.1 | SQYD | 4.50 | 9,328.95 |
| 0005 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 5,000.00 | 5,000.00 |
| 0006 | 204-06-00100 | Temporary Silt Fencing | 2,162 | LNFT | 2.50 | 5,405.00 |
| 0007 | 502-01-00100 | Superpave Asphaltic Concrete | 2,567.4 | TON | 96.00 | 246,470.40 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 6,041.1 | SQYD | 2.50 | 15,102.75 |
| 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 100 | SQYD | 100.00 | 10,000.00 |
| 0010 | 702-07-00300 | Cross Drain Safety End (Type 3) | 1 | EACH | 2,500.00 | 2,500.00 |
| 0011 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 468.25 | LNFT | 33.00 | 15,452.25 |
| 0012 | 704-06-00100 | Guard Rail Anchor Sections (Trailing End) | 6.25 | LNFT | 125.00 | 781.25 |
| 0013 | 704-11-00100 | Guard Rail End Treatment (Flared) | 1 | EACH | 2,400.00 | 2,400.00 |
| 0014 | 707-03-00100 | Combination Concrete Curb and Gutter Mountable | 1,176 | LNFT | 20.00 | 23,520.00 |
| 0015 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 7,500.00 | 7,500.00 |
| 0016 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 1.685 | MILE | 1,000.00 | 1,685.00 |
| 0017 | 716-01-00100 | Mulch (Vegetative) | 1 | TON | 1,000.00 | 1,000.00 |
| 0018 | 717-01-00100 | Seeding | 18 | LB | 20.00 | 360.00 |
| 0019 | 718-01-00100 | Fertilizer | 600 | LB | 2.00 | 1,200.00 |
| 0020 | 727-01-00100 | Mobilization | 1 | LUMP | 30,000.00 | 30,000.00 |
| 0021 | 731-02-00100 | Reflectorized Raised Pavement Markers | 71 | EACH | 10.00 | 710.00 |
| 0022 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 163.8 | LNFT | 1.00 | 163.80 |
| 0023 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 89.4 | LNFT | 3.00 | 268.20 |
| 0024 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.295 | MILE | 3,000.00 | 3,885.00 |
| 0025 | 732-02-02040 | Plastic Pavement Striping (Solid Line) (8" Width) (Thermoplastic 90 mil) | 0.107 | MILE | 5,280.00 | 564.96 |
| 0026 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.047 | MILE | 5,000.00 | 235.00 |
| 0027 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 3 | EACH | 200.00 | 600.00 |
| 0028 | 732-04-15020 | Plastic Pavement Legends and Symbols (ONLY) | 3 | EACH | 200.00 | 600.00 |
| 0029 | 732-05-00100 | Removal of Existing Markings | 0.948 | MILE | 3,000.00 | 2,844.00 |
| 0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 7,500.00 | 7,500.00 |
| CONTRACTOR TOTAL | 403,666.56 | |||||