Bid Tabulations
Letting of
06/23/2010
LA DOTD Headquarters
| Lead Project: 093-03-0015 | |
| Parish: Bienville | |
| Routes: LA 155 | |
| Description: Junction LA 4 - Junction LA 796 | |
| Type Const: GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPHALTIC PAVEMENT, PAVEMENT PATCHING, SUPERPAVE ASPHALTIC CONCRETE PAVEMENT, AND RELATED WORK. | |
| Estimated Construction Cost: $1,864,407.50 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 08584 | Madden Contracting Co., Inc. | $2,223,768.03 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Madden Contracting Co., Inc. |
|
| Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 856 | LNFT | 7.00 | 5,992.00 |
| 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) Sta. 30+72, Sta. 69+23, Sta.78+53, Sta. 88+10, Sta. 118+00, Sta. 266+40, Sta. 824+30, Sta. 337+36 | 47 | LNFT | 150.00 | 7,050.00 |
| 0003 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 23,000.00 | 23,000.00 |
| 0004 | 203-07-00100 | Borrow (Vehicular Measurement) | 7,000 | CUYD | 13.80 | 96,600.00 |
| 0005 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 60 | CUYD | 35.00 | 2,100.00 |
| 0006 | 502-01-00100 | Superpave Asphaltic Concrete | 17,738.8 | TON | 89.10 | 1,580,527.08 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 280 | TON | 62.00 | 17,360.00 |
| 0008 | 509-01-00100 | Cold Planing Asphaltic Pavement | 1,739 | SQYD | 4.30 | 7,477.70 |
| 0009 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,500 | SQYD | 81.00 | 121,500.00 |
| 0010 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 26 | LNFT | 200.00 | 5,200.00 |
| 0011 | 701-10-01080 | Reinforced Concrete Pipe (Extension) (30") | 12 | LNFT | 225.00 | 2,700.00 |
| 0012 | 701-10-01100 | Reinforced Concrete Pipe (Extension) (36") | 38 | LNFT | 250.00 | 9,500.00 |
| 0013 | 701-15-00100 | Concrete Collar | 13 | EACH | 1,250.00 | 16,250.00 |
| 0014 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 200 | LNFT | 46.00 | 9,200.00 |
| 0015 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 414 | LNFT | 61.00 | 25,254.00 |
| 0016 | 704-03-00100 | Blocked Out Guard Rail | 200 | LNFT | 18.00 | 3,600.00 |
| 0017 | 704-11-00100 | Guard Rail End Treatment (Flared) | 8 | EACH | 2,000.00 | 16,000.00 |
| 0018 | 712-04-00100 | Flexible Revetment | 39 | SQYD | 100.00 | 3,900.00 |
| 0019 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 86,000.00 | 86,000.00 |
| 0020 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 44 | LNFT | 0.10 | 4.40 |
| 0021 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 6.62 | MILE | 400.00 | 2,648.00 |
| 0022 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.7 | MILE | 1.00 | 1.70 |
| 0023 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 10.65 | MILE | 1.00 | 10.65 |
| 0024 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 1.00 | 2.00 |
| 0025 | 716-01-00100 | Mulch (Vegetative) | 14 | TON | 600.00 | 8,400.00 |
| 0026 | 717-01-00100 | Seeding | 280 | LB | 10.00 | 2,800.00 |
| 0027 | 718-01-00100 | Fertilizer | 7,000 | LB | 0.50 | 3,500.00 |
| 0028 | 727-01-00100 | Mobilization | 1 | LUMP | 86,000.00 | 86,000.00 |
| 0029 | 729-16-00300 | Object Marker Assembly (Type 3) | 13 | EACH | 75.00 | 975.00 |
| 0030 | 731-02-00100 | Reflectorized Raised Pavement Markers | 825 | EACH | 4.50 | 3,712.50 |
| 0031 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 44 | LNFT | 6.00 | 264.00 |
| 0032 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 23.15 | MILE | 2,300.00 | 53,245.00 |
| 0033 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 1.7 | MILE | 700.00 | 1,190.00 |
| 0034 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 400.00 | 800.00 |
| 0035 | 735-01-00100 | Mailboxes | 4 | EACH | 1.00 | 4.00 |
| 0036 | 735-02-00100 | Mailbox Supports (Single) | 4 | EACH | 250.00 | 1,000.00 |
| 0037 | 740-01-00100 | Construction Layout | 1 | LUMP | 20,000.00 | 20,000.00 |
| CONTRACTOR TOTAL | 2,223,768.03 | |||||