| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BOH BROS. CONSTRUCTION CO., LLC. |
- 2 - WALLACE C. DRENNAN, INC. |
- 3 - FLEMING CONSTRUCTION CO., INC. |
- 4 - PHYLWAY CONSTRUCTION LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
45,000.00 |
45,000.00 |
200,000.00 |
200,000.00 |
95,000.00 |
95,000.00 |
270,000.00 |
270,000.00 |
| 202-02-C |
removal of portland cement concrete pavement
|
6,296   |
SQYD |
6.00 |
37,776.00 |
10.00 |
62,960.00 |
18.00 |
113,328.00 |
9.00 |
56,664.00 |
| 202-02-D |
removal of concrete walks & drives
|
5,336   |
SQYD |
5.00 |
26,680.00 |
15.00 |
80,040.00 |
14.00 |
74,704.00 |
6.00 |
32,016.00 |
| 202-02-I |
removal of asphalt pavement (8" thick)
|
14,031.7 |
SQYD |
5.00 |
70,158.50 |
1.00 |
14,031.70 |
11.00 |
154,348.70 |
3.50 |
49,110.95 |
| 202-02-L |
removal of existing manholes
|
32   |
EACH |
500.00 |
16,000.00 |
10.00 |
320.00 |
600.00 |
19,200.00 |
260.00 |
8,320.00 |
| 203-05 |
excavation and embankment
|
lump |
LUMP |
200,000.00 |
200,000.00 |
200,000.00 |
200,000.00 |
466,000.00 |
466,000.00 |
150,000.00 |
150,000.00 |
| 203-08 |
geotextile fabric
|
28,642   |
SQYD |
1.50 |
42,963.00 |
2.00 |
57,284.00 |
1.20 |
34,370.40 |
1.10 |
31,506.20 |
| 204-02 |
temporary hay or straw bales
|
1,176   |
EACH |
11.00 |
12,936.00 |
5.00 |
5,880.00 |
10.00 |
11,760.00 |
8.00 |
9,408.00 |
| 302-02-C |
class ii base course (8" thick)
|
23,794.4 |
SQYD |
15.00 |
356,916.00 |
14.00 |
333,121.60 |
22.00 |
523,476.80 |
18.00 |
428,299.20 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
407.4 |
CUYD |
70.00 |
28,518.00 |
20.00 |
8,148.00 |
50.00 |
20,370.00 |
40.00 |
16,296.00 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
200.9 |
TON |
200.00 |
40,180.00 |
270.00 |
54,243.00 |
235.00 |
47,211.50 |
240.00 |
48,216.00 |
| 601-01-I |
portland cement concrete pavement (9" thick)
|
18,141.8 |
SQYD |
50.00 |
907,090.00 |
60.00 |
1,088,508.00 |
75.00 |
1,360,635.00 |
59.00 |
1,070,366.20 |
| 601-04 |
portland cement concrete pavement coring
|
25   |
EACH |
88.00 |
2,200.00 |
100.00 |
2,500.00 |
165.00 |
4,125.00 |
150.00 |
3,750.00 |
| 701-03-E |
storm drain pipe (12" rcp)
|
2,124   |
LNFT |
75.00 |
159,300.00 |
84.00 |
178,416.00 |
130.00 |
276,120.00 |
95.00 |
201,780.00 |
| 701-03-F |
storm drain pipe (15" rcp)
|
3,789   |
LNFT |
78.00 |
295,542.00 |
94.00 |
356,166.00 |
135.00 |
511,515.00 |
150.00 |
568,350.00 |
| 701-03-G |
storm drain pipe (18" rcp)
|
177   |
LNFT |
125.00 |
22,125.00 |
124.00 |
21,948.00 |
310.00 |
54,870.00 |
155.00 |
27,435.00 |
| 701-03-I |
storm drain pipe (24" rcp)
|
312   |
LNFT |
155.00 |
48,360.00 |
134.00 |
41,808.00 |
260.00 |
81,120.00 |
160.00 |
49,920.00 |
| 701-03-K |
storm drain pipe (30" rcp)
|
976   |
LNFT |
125.00 |
122,000.00 |
164.00 |
160,064.00 |
190.00 |
185,440.00 |
190.00 |
185,440.00 |
| 701-04-E |
storm drain pipe arch (30" equiv. rcpa)
|
887   |
LNFT |
225.00 |
199,575.00 |
174.00 |
154,338.00 |
540.00 |
478,980.00 |
200.00 |
177,400.00 |
| 706-02-C |
concrete drive (6" thick)
|
1,134.2 |
SQYD |
62.00 |
70,320.40 |
82.00 |
93,004.40 |
80.00 |
90,736.00 |
60.00 |
68,052.00 |
| 707-01 |
concrete curb
|
13,039.8 |
LNFT |
10.00 |
130,398.00 |
8.50 |
110,838.30 |
5.50 |
71,718.90 |
5.00 |
65,199.00 |
| 707-03 |
combination concrete curb & gutter
|
89.6 |
LNFT |
65.00 |
5,824.00 |
70.00 |
6,272.00 |
50.00 |
4,480.00 |
30.00 |
2,688.00 |
| 710-01 |
flowable fill
|
200   |
CUYD |
150.00 |
30,000.00 |
75.00 |
15,000.00 |
180.00 |
36,000.00 |
100.00 |
20,000.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
90,000.00 |
90,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
130,000.00 |
130,000.00 |
| 713-03-A-01 |
temporary pvmt. markings (broken line)(4"w)(4'l)(type
i removable) |
2.826 |
MILE |
300.00 |
847.80 |
2,600.00 |
7,347.60 |
200.00 |
565.20 |
5,000.00 |
14,130.00 |
| 714-01 |
slab sodding
|
8,147   |
SQYD |
4.50 |
36,661.50 |
7.00 |
57,029.00 |
5.00 |
40,735.00 |
5.00 |
40,735.00 |
| 715-01 |
topsoil
|
1,358   |
CUYD |
31.00 |
42,098.00 |
15.00 |
20,370.00 |
45.00 |
61,110.00 |
25.00 |
33,950.00 |
| 717-01 |
seeding
|
76   |
LB |
4.50 |
342.00 |
20.00 |
1,520.00 |
31.00 |
2,356.00 |
13.00 |
988.00 |
| 718-01 |
fertilizer
|
2,534   |
LB |
1.00 |
2,534.00 |
0.50 |
1,267.00 |
1.00 |
2,534.00 |
0.45 |
1,140.30 |
| 722-01 |
project site laboratory
|
1   |
EACH |
10,000.00 |
10,000.00 |
20,000.00 |
20,000.00 |
18,000.00 |
18,000.00 |
20,000.00 |
20,000.00 |
| 723-01 |
granular material (net section)
|
7,840   |
CUYD |
28.00 |
219,520.00 |
5.00 |
39,200.00 |
32.00 |
250,880.00 |
25.00 |
196,000.00 |
| 725-01 |
temporary detour roads
|
270.6 |
SQYD |
70.00 |
18,942.00 |
110.00 |
29,766.00 |
100.00 |
27,060.00 |
100.00 |
27,060.00 |
| 726-01 |
bedding material
|
1,014.0 |
CUYD |
100.00 |
101,400.00 |
5.00 |
5,070.00 |
75.00 |
76,050.00 |
57.00 |
57,798.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
745,000.00 |
745,000.00 |
888,000.00 |
888,000.00 |
750,000.00 |
750,000.00 |
1,300,000.00 |
1,300,000.00 |
| 728-01-01 |
jacked or bored pipe (12" d water main)
|
128.0 |
LNFT |
590.00 |
75,520.00 |
600.00 |
76,800.00 |
525.00 |
67,200.00 |
500.00 |
64,000.00 |
| 728-01-02 |
jacked or bored pipe (20" d sewer force main)
|
128.0 |
LNFT |
750.00 |
96,000.00 |
800.00 |
102,400.00 |
670.00 |
85,760.00 |
700.00 |
89,600.00 |
| 728-01-03 |
jacked or bored pipe (18" d gravity sewer)
|
140.0 |
LNFT |
1,100.00 |
154,000.00 |
1,500.00 |
210,000.00 |
1,400.00 |
196,000.00 |
900.00 |
126,000.00 |
| 728-01-04 |
jacked or bored pipe (12" d gravity sewer)
|
50.9 |
LNFT |
1,500.00 |
76,350.00 |
1,500.00 |
76,350.00 |
1,020.00 |
51,918.00 |
1,100.00 |
55,990.00 |
| 729-01 |
sign (type a)
|
615.3 |
SQFT |
27.00 |
16,613.10 |
16.00 |
9,844.80 |
27.50 |
16,920.75 |
16.00 |
9,844.80 |
| 729-08-A |
mounting (2 1/2" post)
|
69   |
EACH |
1,800.00 |
124,200.00 |
130.00 |
8,970.00 |
1,800.00 |
124,200.00 |
130.00 |
8,970.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
626   |
LNFT |
4.00 |
2,504.00 |
4.00 |
2,504.00 |
4.35 |
2,723.10 |
4.00 |
2,504.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.184 |
MILE |
3,000.00 |
6,552.00 |
3,000.00 |
6,552.00 |
3,200.00 |
6,988.80 |
3,100.00 |
6,770.40 |
| 732-02-B |
plastic pavement striping (solid line) (6" width)
|
0.186 |
MILE |
4,300.00 |
799.80 |
4,300.00 |
799.80 |
4,665.00 |
867.69 |
4,400.00 |
818.40 |
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
0.035 |
MILE |
5,300.00 |
185.50 |
5,300.00 |
185.50 |
5,800.00 |
203.00 |
5,600.00 |
196.00 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
220.00 |
440.00 |
150.00 |
300.00 |
240.00 |
480.00 |
220.00 |
440.00 |
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
2   |
EACH |
240.00 |
480.00 |
200.00 |
400.00 |
220.00 |
440.00 |
240.00 |
480.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
230.00 |
230.00 |
160.00 |
160.00 |
231.00 |
231.00 |
230.00 |
230.00 |
| 735-01 |
mailboxes
|
33   |
EACH |
7.00 |
231.00 |
0.50 |
16.50 |
65.00 |
2,145.00 |
1.00 |
33.00 |
| 735-02 |
mailbox supports (single)
|
33   |
EACH |
175.00 |
5,775.00 |
50.00 |
1,650.00 |
200.00 |
6,600.00 |
130.00 |
4,290.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
125,000.00 |
125,000.00 |
10,000.00 |
10,000.00 |
50,000.00 |
50,000.00 |
80,000.00 |
80,000.00 |
| 802-06 |
well-point system
|
lump |
LUMP |
50,000.00 |
50,000.00 |
100,000.00 |
100,000.00 |
80,000.00 |
80,000.00 |
350,000.00 |
350,000.00 |
| S-001 |
utility exploration
|
5   |
EACH |
2,500.00 |
12,500.00 |
2,500.00 |
12,500.00 |
1,500.00 |
7,500.00 |
1,200.00 |
6,000.00 |
| S-002 |
removal of existing sewer force main with valves
|
3,246.7 |
LNFT |
2.00 |
6,493.40 |
0.00 |
0.00 |
15.00 |
48,700.50 |
3.00 |
9,740.10 |
| S-003 |
new 8"d water main with main line fittings
|
5,022.0 |
LNFT |
55.00 |
276,210.00 |
85.00 |
426,870.00 |
75.00 |
376,650.00 |
55.00 |
276,210.00 |
| S-004 |
new 12"d water main with main line fittings
|
3,533.4 |
LNFT |
80.00 |
282,672.00 |
95.00 |
335,673.00 |
80.00 |
282,672.00 |
68.00 |
240,271.20 |
| S-005 |
replace 3/4" water house connection (from main to
meter & from meter to property line) |
10   |
EACH |
500.00 |
5,000.00 |
10.00 |
100.00 |
1,100.00 |
11,000.00 |
525.00 |
5,250.00 |
| S-006 |
replace 1" water house connection
|
23   |
EACH |
400.00 |
9,200.00 |
200.00 |
4,600.00 |
1,200.00 |
27,600.00 |
550.00 |
12,650.00 |
| S-007 |
new fire hydrants
|
22   |
EACH |
4,500.00 |
99,000.00 |
5,000.00 |
110,000.00 |
3,400.00 |
74,800.00 |
4,200.00 |
92,400.00 |
| S-008 |
replace broken water meter box (1")
|
33   |
EACH |
300.00 |
9,900.00 |
300.00 |
9,900.00 |
550.00 |
18,150.00 |
500.00 |
16,500.00 |
| S-009 |
new 8"d water valves with water valve manhole
|
26   |
EACH |
10,000.00 |
260,000.00 |
8,000.00 |
208,000.00 |
10,500.00 |
273,000.00 |
7,800.00 |
202,800.00 |
| S-010 |
new 12"d water valves with water valve manhole
|
6   |
EACH |
14,000.00 |
84,000.00 |
11,000.00 |
66,000.00 |
12,300.00 |
73,800.00 |
10,600.00 |
63,600.00 |
| S-011 |
install 8"d sewer mains (8.1' - 10.0')
|
284.0 |
LNFT |
228.00 |
64,752.00 |
260.00 |
73,840.00 |
220.00 |
62,480.00 |
240.00 |
68,160.00 |
| S-012 |
install 8"d sewer mains (10.1'+)
|
2,100.0 |
LNFT |
230.00 |
483,000.00 |
270.00 |
567,000.00 |
220.00 |
462,000.00 |
620.00 |
1,302,000.00 |
| S-013 |
install 10"d sewer mains (10.1'+)
|
300.0 |
LNFT |
270.00 |
81,000.00 |
289.00 |
86,700.00 |
260.00 |
78,000.00 |
620.00 |
186,000.00 |
| S-014 |
install 12"d sewer mains (10.1'+)
|
2,700.0 |
LNFT |
280.00 |
756,000.00 |
320.00 |
864,000.00 |
485.00 |
1,309,500.00 |
660.00 |
1,782,000.00 |
| S-015 |
install 15"d sewer mains (10.1'+)
|
300.0 |
LNFT |
390.00 |
117,000.00 |
400.00 |
120,000.00 |
540.00 |
162,000.00 |
1,130.00 |
339,000.00 |
| S-016 |
install 16"d sewer mains (10.1'+)
|
48.0 |
LNFT |
395.00 |
18,960.00 |
1,000.00 |
48,000.00 |
690.00 |
33,120.00 |
1,140.00 |
54,720.00 |
| S-017 |
install 18"d sewer mains (10.1'+)
|
380.0 |
LNFT |
400.00 |
152,000.00 |
800.00 |
304,000.00 |
630.00 |
239,400.00 |
1,170.00 |
444,600.00 |
| S-018 |
install sewer manhole (s&wb dwg. no. 6178-b6)(8.1' -
10.0') |
3   |
EACH |
9,000.00 |
27,000.00 |
6,000.00 |
18,000.00 |
10,150.00 |
30,450.00 |
7,000.00 |
21,000.00 |
| S-019 |
install sewer manhole (s&wb dwg. no. 6178-b6)(10.1'+)
|
21   |
EACH |
10,500.00 |
220,500.00 |
15,000.00 |
315,000.00 |
15,000.00 |
315,000.00 |
9,000.00 |
189,000.00 |
| S-020 |
new sewer house connection (from main to back of curb)
(6") |
33   |
EACH |
400.00 |
13,200.00 |
880.00 |
29,040.00 |
3,000.00 |
99,000.00 |
2,700.00 |
89,100.00 |
| S-021 |
new sewer force main (18" c905 pvc)
|
3,199.0 |
LNFT |
145.00 |
463,855.00 |
133.00 |
425,467.00 |
125.00 |
399,875.00 |
130.00 |
415,870.00 |
| S-022 |
tie into existing d.i. sewer force main at veterans
blvd. |
lump |
LUMP |
25,000.00 |
25,000.00 |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
10,000.00 |
10,000.00 |
| S-023 |
tie into existing d.i. sewer force main at 32nd street
|
lump |
LUMP |
10,000.00 |
10,000.00 |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
9,400.00 |
9,400.00 |
| S-024 |
drain house connection (8" d) w/ 4" d or 6" d pvc
reducer |
355.0 |
LNFT |
55.00 |
19,525.00 |
43.00 |
15,265.00 |
45.00 |
15,975.00 |
17.00 |
6,035.00 |
| S-025 |
drain house connection (8" d) from yard drain to catch
basins stubouts |
1,396.0 |
LNFT |
30.00 |
41,880.00 |
33.00 |
46,068.00 |
45.00 |
62,820.00 |
15.00 |
20,940.00 |
| S-026 |
no. 1 std. drain manhole (s&wb dwg. d-870)
|
77.2 |
VFH |
650.00 |
50,180.00 |
400.00 |
30,880.00 |
525.00 |
40,530.00 |
750.00 |
57,900.00 |
| S-027 |
no. 2 std. drain manhole (s&wb dwg. d-870)
|
280.7 |
VFH |
660.00 |
185,262.00 |
410.00 |
115,087.00 |
525.00 |
147,367.50 |
775.00 |
217,542.50 |
| S-028 |
single mountable catch basin (s&wb dwg. d-3431-a)
|
84   |
EACH |
3,750.00 |
315,000.00 |
4,000.00 |
336,000.00 |
3,500.00 |
294,000.00 |
4,800.00 |
403,200.00 |
| S-029 |
24" x 30" clear opening std. drop inlet (s&wb dwg.
d-3264) |
45   |
EACH |
2,750.00 |
123,750.00 |
3,666.00 |
164,970.00 |
3,500.00 |
157,500.00 |
5,200.00 |
234,000.00 |
| S-030 |
yard drain inlet
|
39   |
EACH |
2,300.00 |
89,700.00 |
1,777.00 |
69,303.00 |
1,500.00 |
58,500.00 |
565.00 |
22,035.00 |
| S-031 |
gravel bed and filter cloth over tree roots
|
lump |
LUMP |
1,250.00 |
1,250.00 |
1,500.00 |
1,500.00 |
1,000.00 |
1,000.00 |
1,300.00 |
1,300.00 |
| S-032 |
landscaping
|
lump |
LUMP |
44,000.00 |
44,000.00 |
10,000.00 |
10,000.00 |
2,500.00 |
2,500.00 |
0.00 |
0.00 |
| S-033 |
tree trimming
|
lump |
LUMP |
23,000.00 |
23,000.00 |
44,000.00 |
44,000.00 |
13,000.00 |
13,000.00 |
13,000.00 |
13,000.00 |
| S-034 |
root pruning
|
lump |
LUMP |
21,000.00 |
21,000.00 |
25,000.00 |
25,000.00 |
15,000.00 |
15,000.00 |
16,000.00 |
16,000.00 |
| S-035 |
vibration monitoring
|
lump |
LUMP |
11,000.00 |
11,000.00 |
7,700.00 |
7,700.00 |
60,000.00 |
60,000.00 |
105,000.00 |
105,000.00 |
| S-036 |
saw cutting 7" thick pcc pavement (full depth)
|
985.0 |
LNFT |
10.00 |
9,850.00 |
8.00 |
7,880.00 |
6.00 |
5,910.00 |
10.00 |
9,850.00 |
| S-037 |
project signs
|
2   |
EACH |
2,400.00 |
4,800.00 |
2,500.00 |
5,000.00 |
5,000.00 |
10,000.00 |
1,100.00 |
2,200.00 |
| S-038 |
30"x30"x12" reinforced concrete wye
|
34   |
EACH |
1,600.00 |
54,400.00 |
1,188.00 |
40,392.00 |
1,400.00 |
47,600.00 |
1,700.00 |
57,800.00 |
| S-039 |
24"x24"x12" reinforced concrete wye
|
4   |
EACH |
1,200.00 |
4,800.00 |
800.00 |
3,200.00 |
1,000.00 |
4,000.00 |
1,300.00 |
5,200.00 |
| S-040 |
18"x18"x12" reinforced concrete wye
|
2   |
EACH |
650.00 |
1,300.00 |
400.00 |
800.00 |
565.00 |
1,130.00 |
900.00 |
1,800.00 |
| S-041 |
video and photographic survey
|
lump |
LUMP |
27,000.00 |
27,000.00 |
11,880.00 |
11,880.00 |
25,000.00 |
25,000.00 |
100,000.00 |
100,000.00 |
| S-042 |
street name sign on new post
|
44   |
EACH |
450.00 |
19,800.00 |
150.00 |
6,600.00 |
500.00 |
22,000.00 |
160.00 |
7,040.00 |
| S-043 |
reinforced concrete sidewalk (4" thick)
|
2,640.8 |
SQYD |
55.00 |
145,244.00 |
82.00 |
216,545.60 |
75.00 |
198,060.00 |
45.00 |
118,836.00 |
| S-044 |
sidewalk @ intersection (incl. handicapped ramps)(6"
thick) |
699.8 |
SQYD |
100.00 |
69,980.00 |
120.00 |
83,976.00 |
160.00 |
111,968.00 |
85.00 |
59,483.00 |
| S-045 |
sidewalk in median (incl. handicapped ramps)
|
560.6 |
SQYD |
100.00 |
56,060.00 |
150.00 |
84,090.00 |
160.00 |
89,696.00 |
85.00 |
47,651.00 |
| S-046 |
portland cement concrete pavement (reinforced
w/6x12-w7.5xw6.5 wwf) |
1,782.0 |
SQYD |
95.00 |
169,290.00 |
77.00 |
137,214.00 |
85.00 |
151,470.00 |
64.00 |
114,048.00 |
| S-047 |
portland cement concrete pavement (reinforced w/#3@18"
o.c.e.w.) |
2,132.6 |
SQYD |
95.00 |
202,597.00 |
77.00 |
164,210.20 |
85.00 |
181,271.00 |
67.00 |
142,884.20 |
| S-048 |
temporary sanitary sewer diversion(@ 12th street)
|
lump |
LUMP |
15,000.00 |
15,000.00 |
44,000.00 |
44,000.00 |
100,000.00 |
100,000.00 |
400,000.00 |
400,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
10,054,998.00 |
|
10,737,644.00 |
|
12,968,471.84 |
|
14,162,200.45 |
| | NUMBER OF DAYS BID AT $3,000 PER DAY. |
|
|
|
750,000.00 |
|
780,000.00 |
|
840,000.00 |
|
840,000.00 |
| | TOTAL BID |
|
|
|
10,804,998.00 |
|
11,517,644.00 |
|
13,808,471.84 |
|
15,002,200.45 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - CYCLE CONSTRUCTION CO. L.L.C. |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
250,000.00 |
250,000.00 |
|
|
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
6,296   |
SQYD |
10.00 |
62,960.00 |
|
|
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
5,336   |
SQYD |
11.00 |
58,696.00 |
|
|
|
|
|
|
| 202-02-I |
removal of asphalt pavement (8" thick)
|
14,031.7 |
SQYD |
10.00 |
140,317.00 |
|
|
|
|
|
|
| 202-02-L |
removal of existing manholes
|
32   |
EACH |
1,400.00 |
44,800.00 |
|
|
|
|
|
|
| 203-05 |
excavation and embankment
|
lump |
LUMP |
250,000.00 |
250,000.00 |
|
|
|
|
|
|
| 203-08 |
geotextile fabric
|
28,642   |
SQYD |
2.00 |
57,284.00 |
|
|
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
1,176   |
EACH |
30.00 |
35,280.00 |
|
|
|
|
|
|
| 302-02-C |
class ii base course (8" thick)
|
23,794.4 |
SQYD |
22.00 |
523,476.80 |
|
|
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
407.4 |
CUYD |
52.00 |
21,184.80 |
|
|
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
200.9 |
TON |
260.00 |
52,234.00 |
|
|
|
|
|
|
| 601-01-I |
portland cement concrete pavement (9" thick)
|
18,141.8 |
SQYD |
74.00 |
1,342,493.20 |
|
|
|
|
|
|
| 601-04 |
portland cement concrete pavement coring
|
25   |
EACH |
170.00 |
4,250.00 |
|
|
|
|
|
|
| 701-03-E |
storm drain pipe (12" rcp)
|
2,124   |
LNFT |
235.00 |
499,140.00 |
|
|
|
|
|
|
| 701-03-F |
storm drain pipe (15" rcp)
|
3,789   |
LNFT |
150.00 |
568,350.00 |
|
|
|
|
|
|
| 701-03-G |
storm drain pipe (18" rcp)
|
177   |
LNFT |
185.00 |
32,745.00 |
|
|
|
|
|
|
| 701-03-I |
storm drain pipe (24" rcp)
|
312   |
LNFT |
190.00 |
59,280.00 |
|
|
|
|
|
|
| 701-03-K |
storm drain pipe (30" rcp)
|
976   |
LNFT |
195.00 |
190,320.00 |
|
|
|
|
|
|
| 701-04-E |
storm drain pipe arch (30" equiv. rcpa)
|
887   |
LNFT |
240.00 |
212,880.00 |
|
|
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
1,134.2 |
SQYD |
65.00 |
73,723.00 |
|
|
|
|
|
|
| 707-01 |
concrete curb
|
13,039.8 |
LNFT |
7.00 |
91,278.60 |
|
|
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
89.6 |
LNFT |
60.00 |
5,376.00 |
|
|
|
|
|
|
| 710-01 |
flowable fill
|
200   |
CUYD |
255.00 |
51,000.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
100,000.00 |
100,000.00 |
|
|
|
|
|
|
| 713-03-A-01 |
temporary pvmt. markings (broken line)(4"w)(4'l)(type
i removable) |
2.826 |
MILE |
600.00 |
1,695.60 |
|
|
|
|
|
|
| 714-01 |
slab sodding
|
8,147   |
SQYD |
7.00 |
57,029.00 |
|
|
|
|
|
|
| 715-01 |
topsoil
|
1,358   |
CUYD |
45.00 |
61,110.00 |
|
|
|
|
|
|
| 717-01 |
seeding
|
76   |
LB |
10.00 |
760.00 |
|
|
|
|
|
|
| 718-01 |
fertilizer
|
2,534   |
LB |
0.50 |
1,267.00 |
|
|
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
17,000.00 |
17,000.00 |
|
|
|
|
|
|
| 723-01 |
granular material (net section)
|
7,840   |
CUYD |
25.00 |
196,000.00 |
|
|
|
|
|
|
| 725-01 |
temporary detour roads
|
270.6 |
SQYD |
200.00 |
54,120.00 |
|
|
|
|
|
|
| 726-01 |
bedding material
|
1,014.0 |
CUYD |
75.00 |
76,050.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
1,500,000.00 |
1,500,000.00 |
|
|
|
|
|
|
| 728-01-01 |
jacked or bored pipe (12" d water main)
|
128.0 |
LNFT |
1,500.00 |
192,000.00 |
|
|
|
|
|
|
| 728-01-02 |
jacked or bored pipe (20" d sewer force main)
|
128.0 |
LNFT |
1,500.00 |
192,000.00 |
|
|
|
|
|
|
| 728-01-03 |
jacked or bored pipe (18" d gravity sewer)
|
140.0 |
LNFT |
1,800.00 |
252,000.00 |
|
|
|
|
|
|
| 728-01-04 |
jacked or bored pipe (12" d gravity sewer)
|
50.9 |
LNFT |
900.00 |
45,810.00 |
|
|
|
|
|
|
| 729-01 |
sign (type a)
|
615.3 |
SQFT |
18.00 |
11,075.40 |
|
|
|
|
|
|
| 729-08-A |
mounting (2 1/2" post)
|
69   |
EACH |
150.00 |
10,350.00 |
|
|
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
626   |
LNFT |
5.00 |
3,130.00 |
|
|
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.184 |
MILE |
3,500.00 |
7,644.00 |
|
|
|
|
|
|
| 732-02-B |
plastic pavement striping (solid line) (6" width)
|
0.186 |
MILE |
5,200.00 |
967.20 |
|
|
|
|
|
|
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
0.035 |
MILE |
5,400.00 |
189.00 |
|
|
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
250.00 |
500.00 |
|
|
|
|
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
2   |
EACH |
260.00 |
520.00 |
|
|
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
250.00 |
250.00 |
|
|
|
|
|
|
| 735-01 |
mailboxes
|
33   |
EACH |
60.00 |
1,980.00 |
|
|
|
|
|
|
| 735-02 |
mailbox supports (single)
|
33   |
EACH |
90.00 |
2,970.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
160,000.00 |
160,000.00 |
|
|
|
|
|
|
| 802-06 |
well-point system
|
lump |
LUMP |
350,000.00 |
350,000.00 |
|
|
|
|
|
|
| S-001 |
utility exploration
|
5   |
EACH |
4,200.00 |
21,000.00 |
|
|
|
|
|
|
| S-002 |
removal of existing sewer force main with valves
|
3,246.7 |
LNFT |
42.00 |
136,361.40 |
|
|
|
|
|
|
| S-003 |
new 8"d water main with main line fittings
|
5,022.0 |
LNFT |
135.00 |
677,970.00 |
|
|
|
|
|
|
| S-004 |
new 12"d water main with main line fittings
|
3,533.4 |
LNFT |
145.00 |
512,343.00 |
|
|
|
|
|
|
| S-005 |
replace 3/4" water house connection (from main to
meter & from meter to property line) |
10   |
EACH |
900.00 |
9,000.00 |
|
|
|
|
|
|
| S-006 |
replace 1" water house connection
|
23   |
EACH |
900.00 |
20,700.00 |
|
|
|
|
|
|
| S-007 |
new fire hydrants
|
22   |
EACH |
4,900.00 |
107,800.00 |
|
|
|
|
|
|
| S-008 |
replace broken water meter box (1")
|
33   |
EACH |
450.00 |
14,850.00 |
|
|
|
|
|
|
| S-009 |
new 8"d water valves with water valve manhole
|
26   |
EACH |
7,600.00 |
197,600.00 |
|
|
|
|
|
|
| S-010 |
new 12"d water valves with water valve manhole
|
6   |
EACH |
11,000.00 |
66,000.00 |
|
|
|
|
|
|
| S-011 |
install 8"d sewer mains (8.1' - 10.0')
|
284.0 |
LNFT |
570.00 |
161,880.00 |
|
|
|
|
|
|
| S-012 |
install 8"d sewer mains (10.1'+)
|
2,100.0 |
LNFT |
720.00 |
1,512,000.00 |
|
|
|
|
|
|
| S-013 |
install 10"d sewer mains (10.1'+)
|
300.0 |
LNFT |
765.00 |
229,500.00 |
|
|
|
|
|
|
| S-014 |
install 12"d sewer mains (10.1'+)
|
2,700.0 |
LNFT |
785.00 |
2,119,500.00 |
|
|
|
|
|
|
| S-015 |
install 15"d sewer mains (10.1'+)
|
300.0 |
LNFT |
800.00 |
240,000.00 |
|
|
|
|
|
|
| S-016 |
install 16"d sewer mains (10.1'+)
|
48.0 |
LNFT |
920.00 |
44,160.00 |
|
|
|
|
|
|
| S-017 |
install 18"d sewer mains (10.1'+)
|
380.0 |
LNFT |
920.00 |
349,600.00 |
|
|
|
|
|
|
| S-018 |
install sewer manhole (s&wb dwg. no. 6178-b6)(8.1' -
10.0') |
3   |
EACH |
8,800.00 |
26,400.00 |
|
|
|
|
|
|
| S-019 |
install sewer manhole (s&wb dwg. no. 6178-b6)(10.1'+)
|
21   |
EACH |
12,000.00 |
252,000.00 |
|
|
|
|
|
|
| S-020 |
new sewer house connection (from main to back of curb)
(6") |
33   |
EACH |
1,500.00 |
49,500.00 |
|
|
|
|
|
|
| S-021 |
new sewer force main (18" c905 pvc)
|
3,199.0 |
LNFT |
170.00 |
543,830.00 |
|
|
|
|
|
|
| S-022 |
tie into existing d.i. sewer force main at veterans
blvd. |
lump |
LUMP |
35,000.00 |
35,000.00 |
|
|
|
|
|
|
| S-023 |
tie into existing d.i. sewer force main at 32nd street
|
lump |
LUMP |
35,000.00 |
35,000.00 |
|
|
|
|
|
|
| S-024 |
drain house connection (8" d) w/ 4" d or 6" d pvc
reducer |
355.0 |
LNFT |
40.00 |
14,200.00 |
|
|
|
|
|
|
| S-025 |
drain house connection (8" d) from yard drain to catch
basins stubouts |
1,396.0 |
LNFT |
40.00 |
55,840.00 |
|
|
|
|
|
|
| S-026 |
no. 1 std. drain manhole (s&wb dwg. d-870)
|
77.2 |
VFH |
820.00 |
63,304.00 |
|
|
|
|
|
|
| S-027 |
no. 2 std. drain manhole (s&wb dwg. d-870)
|
280.7 |
VFH |
950.00 |
266,665.00 |
|
|
|
|
|
|
| S-028 |
single mountable catch basin (s&wb dwg. d-3431-a)
|
84   |
EACH |
3,600.00 |
302,400.00 |
|
|
|
|
|
|
| S-029 |
24" x 30" clear opening std. drop inlet (s&wb dwg.
d-3264) |
45   |
EACH |
1,200.00 |
54,000.00 |
|
|
|
|
|
|
| S-030 |
yard drain inlet
|
39   |
EACH |
1,200.00 |
46,800.00 |
|
|
|
|
|
|
| S-031 |
gravel bed and filter cloth over tree roots
|
lump |
LUMP |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| S-032 |
landscaping
|
lump |
LUMP |
60,000.00 |
60,000.00 |
|
|
|
|
|
|
| S-033 |
tree trimming
|
lump |
LUMP |
26,000.00 |
26,000.00 |
|
|
|
|
|
|
| S-034 |
root pruning
|
lump |
LUMP |
25,000.00 |
25,000.00 |
|
|
|
|
|
|
| S-035 |
vibration monitoring
|
lump |
LUMP |
300,000.00 |
300,000.00 |
|
|
|
|
|
|
| S-036 |
saw cutting 7" thick pcc pavement (full depth)
|
985.0 |
LNFT |
12.00 |
11,820.00 |
|
|
|
|
|
|
| S-037 |
project signs
|
2   |
EACH |
1,250.00 |
2,500.00 |
|
|
|
|
|
|
| S-038 |
30"x30"x12" reinforced concrete wye
|
34   |
EACH |
1,500.00 |
51,000.00 |
|
|
|
|
|
|
| S-039 |
24"x24"x12" reinforced concrete wye
|
4   |
EACH |
1,100.00 |
4,400.00 |
|
|
|
|
|
|
| S-040 |
18"x18"x12" reinforced concrete wye
|
2   |
EACH |
650.00 |
1,300.00 |
|
|
|
|
|
|
| S-041 |
video and photographic survey
|
lump |
LUMP |
75,000.00 |
75,000.00 |
|
|
|
|
|
|
| S-042 |
street name sign on new post
|
44   |
EACH |
200.00 |
8,800.00 |
|
|
|
|
|
|
| S-043 |
reinforced concrete sidewalk (4" thick)
|
2,640.8 |
SQYD |
65.00 |
171,652.00 |
|
|
|
|
|
|
| S-044 |
sidewalk @ intersection (incl. handicapped ramps)(6"
thick) |
699.8 |
SQYD |
220.00 |
153,956.00 |
|
|
|
|
|
|
| S-045 |
sidewalk in median (incl. handicapped ramps)
|
560.6 |
SQYD |
220.00 |
123,332.00 |
|
|
|
|
|
|
| S-046 |
portland cement concrete pavement (reinforced
w/6x12-w7.5xw6.5 wwf) |
1,782.0 |
SQYD |
85.00 |
151,470.00 |
|
|
|
|
|
|
| S-047 |
portland cement concrete pavement (reinforced w/#3@18"
o.c.e.w.) |
2,132.6 |
SQYD |
85.00 |
181,271.00 |
|
|
|
|
|
|
| S-048 |
temporary sanitary sewer diversion(@ 12th street)
|
lump |
LUMP |
175,000.00 |
175,000.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
17,621,190.00 |
|
|
|
|
|
|
| | NUMBER OF DAYS BID AT $3,000 PER DAY. |
|
|
|
840,000.00 |
|
|
|
|
|
|
| | TOTAL BID |
|
|
|
18,461,190.00 |
|
|
|
|
|
|
|