| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GILCHRIST CONSTRUCTION CO. LLC |
- 2 - JB JAMES CONSTRUCTION LLC |
- 3 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
42,000.00 |
42,000.00 |
260,000.00 |
260,000.00 |
500,000.00 |
500,000.00 |
|
|
| 202-02-B |
removal of concrete box culverts (sta. 128+92.00,
3-4'x4'x38' long) |
1   |
EACH |
5,000.00 |
5,000.00 |
12,000.00 |
12,000.00 |
25,000.00 |
25,000.00 |
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
913   |
SQYD |
25.00 |
22,825.00 |
12.00 |
10,956.00 |
20.00 |
18,260.00 |
|
|
| 202-02-D |
removal of concrete walks & drives
|
2,041   |
SQYD |
8.00 |
16,328.00 |
9.00 |
18,369.00 |
41.00 |
83,681.00 |
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
36,967.9 |
SQYD |
3.25 |
120,145.68 |
4.50 |
166,355.55 |
6.50 |
240,291.35 |
|
|
| 202-02-I |
removal of traffic signal equipment
|
lump |
LUMP |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
3,000.00 |
3,000.00 |
|
|
| 202-02-J |
removal of asphalt drives
|
1,825   |
SQYD |
7.00 |
12,775.00 |
8.00 |
14,600.00 |
15.00 |
27,375.00 |
|
|
| 202-03-01 |
relocation of 8' wide concrete walkway w/ pipe
railings (sta. -1 +72.00 - 19.90' lt) |
1   |
EACH |
3,500.00 |
3,500.00 |
5,000.00 |
5,000.00 |
30,000.00 |
30,000.00 |
|
|
| 203-01 |
general excavation
|
41,608   |
CUYD |
6.80 |
282,934.40 |
10.00 |
416,080.00 |
8.50 |
353,668.00 |
|
|
| 203-02 |
drainage excavation
|
352   |
CUYD |
18.00 |
6,336.00 |
30.00 |
10,560.00 |
25.00 |
8,800.00 |
|
|
| 203-03 |
embankment
|
44,343   |
CUYD |
13.50 |
598,630.50 |
19.00 |
842,517.00 |
16.00 |
709,488.00 |
|
|
| 204-02 |
temporary hay or straw bales
|
2,013   |
EACH |
17.00 |
34,221.00 |
10.00 |
20,130.00 |
22.00 |
44,286.00 |
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
79   |
EACH |
200.00 |
15,800.00 |
110.00 |
8,690.00 |
175.00 |
13,825.00 |
|
|
| 204-06 |
temporary silt fencing
|
19,935   |
LNFT |
2.80 |
55,818.00 |
1.80 |
35,883.00 |
10.00 |
199,350.00 |
|
|
| 302-02-B-01 |
class ii base course (6" thick) (stone or recycled
pccp) |
109,087.2 |
SQYD |
13.00 |
1,418,133.60 |
15.00 |
1,636,308.00 |
15.50 |
1,690,851.60 |
|
|
| 302-02-D-01 |
class ii base course (8 1/2" thick) (stone or recycled
pccp) |
487.8 |
SQYD |
29.25 |
14,268.15 |
28.00 |
13,658.40 |
33.00 |
16,097.40 |
|
|
| 304-01 |
lime (9% by volume)
|
500.00 |
TON |
160.00 |
80,000.00 |
270.00 |
135,000.00 |
450.00 |
225,000.00 |
|
|
| 304-03-D |
lime treatment (type c) (12" thick)
|
61,361   |
SQYD |
5.00 |
306,805.00 |
3.00 |
184,083.00 |
1.25 |
76,701.25 |
|
|
| 304-04-D |
lime treatment (type d) (12" thick)
|
35,274   |
SQYD |
1.00 |
35,274.00 |
2.00 |
70,548.00 |
1.25 |
44,092.50 |
|
|
| 305-01-D-01 |
subgrade layer (12" thick)(cement treated)
|
109,087   |
SQYD |
7.50 |
818,152.50 |
9.00 |
981,783.00 |
10.25 |
1,118,141.75 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
264   |
CUYD |
55.00 |
14,520.00 |
85.00 |
22,440.00 |
100.00 |
26,400.00 |
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
8,000.0 |
CUYD |
32.00 |
256,000.00 |
35.00 |
280,000.00 |
80.00 |
640,000.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
3,505.1 |
TON |
100.00 |
350,510.00 |
110.00 |
385,561.00 |
110.00 |
385,561.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts & misc.
|
22.7 |
TON |
165.00 |
3,745.50 |
160.00 |
3,632.00 |
200.00 |
4,540.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
2,626   |
SQYD |
2.50 |
6,565.00 |
14.00 |
36,764.00 |
18.00 |
47,268.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 109   |
CUYD |
0.01 |
- 1.09 |
0.01 |
- 1.09 |
0.10 |
- 10.90 |
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
583   |
SQYD |
125.00 |
72,875.00 |
140.00 |
81,620.00 |
190.00 |
110,770.00 |
|
|
| 510-02 |
pavement widening (8" thick)
|
871.0 |
SQYD |
60.00 |
52,260.00 |
120.00 |
104,520.00 |
92.00 |
80,132.00 |
|
|
| 601-04 |
portland cement concrete pavement coring
|
126   |
EACH |
120.00 |
15,120.00 |
100.00 |
12,600.00 |
0.01 |
1.26 |
|
|
| 701-01-I |
cross drain pipe (24" rcp/pcp)
|
676   |
LNFT |
80.00 |
54,080.00 |
86.00 |
58,136.00 |
125.00 |
84,500.00 |
|
|
| 701-01-M |
cross drain pipe (36" rcp/pcp)
|
120   |
LNFT |
180.00 |
21,600.00 |
110.00 |
13,200.00 |
165.00 |
19,800.00 |
|
|
| 701-02-D |
cross drain pipe arch (24" equiv. rcpa or cmpa)
|
96   |
LNFT |
120.00 |
11,520.00 |
90.00 |
8,640.00 |
140.00 |
13,440.00 |
|
|
| 701-02-E/F |
cross drain pipe arch (30" equiv. rcpa or 36" equiv.
cmpa) |
184   |
LNFT |
93.00 |
17,112.00 |
88.00 |
16,192.00 |
150.00 |
27,600.00 |
|
|
| 701-02-F/G |
cross drain pipe arch (36" equiv. rcpa or 42" equiv.
cmpa) |
468   |
LNFT |
118.00 |
55,224.00 |
107.00 |
50,076.00 |
175.00 |
81,900.00 |
|
|
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
2,318   |
LNFT |
48.00 |
111,264.00 |
65.00 |
150,670.00 |
80.00 |
185,440.00 |
|
|
| 701-03-G |
storm drain pipe (18" rcp/pcp)
|
3,371   |
LNFT |
50.00 |
168,550.00 |
60.00 |
202,260.00 |
85.00 |
286,535.00 |
|
|
| 701-03-I |
storm drain pipe (24" rcp/pcp)
|
2,103   |
LNFT |
70.00 |
147,210.00 |
80.00 |
168,240.00 |
100.00 |
210,300.00 |
|
|
| 701-03-K |
storm drain pipe (30" rcp/pcp)
|
1,920   |
LNFT |
100.00 |
192,000.00 |
90.00 |
172,800.00 |
120.00 |
230,400.00 |
|
|
| 701-03-M |
storm drain pipe (36" rcp/pcp)
|
1,059   |
LNFT |
125.00 |
132,375.00 |
110.00 |
116,490.00 |
140.00 |
148,260.00 |
|
|
| 701-03-N |
storm drain pipe (42" rcp/pcp)
|
1,183   |
LNFT |
160.00 |
189,280.00 |
120.00 |
141,960.00 |
165.00 |
195,195.00 |
|
|
| 701-03-O |
storm drain pipe (48" rcp/pcp)
|
2,574   |
LNFT |
180.00 |
463,320.00 |
150.00 |
386,100.00 |
185.00 |
476,190.00 |
|
|
| 701-03-P |
storm drain pipe (54" rcp/pcp)
|
1,968   |
LNFT |
200.00 |
393,600.00 |
170.00 |
334,560.00 |
210.00 |
413,280.00 |
|
|
| 701-03-S |
storm drain pipe (72" rcp/pcp)
|
48   |
LNFT |
415.00 |
19,920.00 |
280.00 |
13,440.00 |
300.00 |
14,400.00 |
|
|
| 701-04-E |
storm drain pipe arch (30" equiv. rcpa)
|
417   |
LNFT |
121.00 |
50,457.00 |
88.00 |
36,696.00 |
130.00 |
54,210.00 |
|
|
| 701-04-F |
storm drain pipe arch (36" equiv. rcpa)
|
95   |
LNFT |
159.00 |
15,105.00 |
102.00 |
9,690.00 |
155.00 |
14,725.00 |
|
|
| 701-04-G |
storm drain pipe arch (42" equiv. rcpa)
|
412   |
LNFT |
145.00 |
59,740.00 |
130.00 |
53,560.00 |
200.00 |
82,400.00 |
|
|
| 701-05-G |
side drain pipe (18")
|
206   |
LNFT |
40.00 |
8,240.00 |
52.00 |
10,712.00 |
60.00 |
12,360.00 |
|
|
| 701-05-I |
side drain pipe (24")
|
124   |
LNFT |
88.00 |
10,912.00 |
60.00 |
7,440.00 |
70.00 |
8,680.00 |
|
|
| 701-05-K |
side drain pipe (30")
|
270   |
LNFT |
68.00 |
18,360.00 |
69.00 |
18,630.00 |
80.00 |
21,600.00 |
|
|
| 701-05-M |
side drain pipe (36")
|
92   |
LNFT |
71.00 |
6,532.00 |
85.00 |
7,820.00 |
100.00 |
9,200.00 |
|
|
| 701-06-D |
side drain pipe arch (24" equiv.)
|
110   |
LNFT |
85.00 |
9,350.00 |
56.00 |
6,160.00 |
82.00 |
9,020.00 |
|
|
| 701-06-E |
side drain pipe arch (30" equiv.)
|
522   |
LNFT |
78.00 |
40,716.00 |
65.00 |
33,930.00 |
92.00 |
48,024.00 |
|
|
| 701-06-F |
side drain pipe arch (36" equiv.)
|
186   |
LNFT |
123.00 |
22,878.00 |
80.00 |
14,880.00 |
130.00 |
24,180.00 |
|
|
| 701-06-G |
side drain pipe arch (42" equiv.)
|
62   |
LNFT |
175.00 |
10,850.00 |
100.00 |
6,200.00 |
175.00 |
10,850.00 |
|
|
| 701-06-H |
side drain pipe arch (48" equiv.)
|
46   |
LNFT |
255.00 |
11,730.00 |
150.00 |
6,900.00 |
200.00 |
9,200.00 |
|
|
| 702-03-A |
catch basins (cb-01)
|
121   |
EACH |
2,100.00 |
254,100.00 |
2,300.00 |
278,300.00 |
2,600.00 |
314,600.00 |
|
|
| 702-03-B |
catch basins (cb-02)
|
5   |
EACH |
3,350.00 |
16,750.00 |
3,000.00 |
15,000.00 |
4,500.00 |
22,500.00 |
|
|
| 702-03-C |
catch basins (cb-06)
|
136   |
EACH |
4,000.00 |
544,000.00 |
4,200.00 |
571,200.00 |
5,000.00 |
680,000.00 |
|
|
| 702-03-D |
catch basins (cb-07)
|
29   |
EACH |
7,500.00 |
217,500.00 |
5,500.00 |
159,500.00 |
6,500.00 |
188,500.00 |
|
|
| 702-03-F |
catch basins (cb-08)
|
4   |
EACH |
10,000.00 |
40,000.00 |
8,000.00 |
32,000.00 |
7,250.00 |
29,000.00 |
|
|
| 702-03-G |
catch basins (cb-09)
|
7   |
EACH |
9,000.00 |
63,000.00 |
6,200.00 |
43,400.00 |
7,000.00 |
49,000.00 |
|
|
| 702-04-B |
adjusting catch basins
|
2   |
EACH |
2,400.00 |
4,800.00 |
2,000.00 |
4,000.00 |
3,000.00 |
6,000.00 |
|
|
| 702-08-A |
side drain safety end (type 1)
|
2   |
EACH |
3,400.00 |
6,800.00 |
1,500.00 |
3,000.00 |
1,750.00 |
3,500.00 |
|
|
| 703-01 |
shoulder underdrain systems
|
16,958   |
LNFT |
8.00 |
135,664.00 |
8.00 |
135,664.00 |
8.00 |
135,664.00 |
|
|
| 703-02 |
shoulder outlet underdrains
|
111   |
EACH |
750.00 |
83,250.00 |
500.00 |
55,500.00 |
1,100.00 |
122,100.00 |
|
|
| 703-03 |
preforated pipe underdrains
|
13,727   |
LNFT |
9.00 |
123,543.00 |
13.00 |
178,451.00 |
7.50 |
102,952.50 |
|
|
| 706-01-A |
concrete walk (4" thick)
|
32.3 |
SQYD |
70.00 |
2,261.00 |
100.00 |
3,230.00 |
60.00 |
1,938.00 |
|
|
| 706-02-C |
concrete drive (6" thick)
|
3,446.6 |
SQYD |
60.00 |
206,796.00 |
50.00 |
172,330.00 |
60.00 |
206,796.00 |
|
|
| 706-03-C |
incidental concrete paving (6" thick)
|
103.6 |
SQYD |
85.00 |
8,806.00 |
62.00 |
6,423.20 |
45.00 |
4,662.00 |
|
|
| 710-01 |
flowable fill
|
1,297   |
CUYD |
100.00 |
129,700.00 |
140.00 |
181,580.00 |
115.00 |
149,155.00 |
|
|
| 712-02-A-01 |
sacked concrete revetment (4" thick) (dry batched)
|
1,110   |
SQYD |
75.00 |
83,250.00 |
50.00 |
55,500.00 |
95.00 |
105,450.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
310,000.00 |
310,000.00 |
400,000.00 |
400,000.00 |
900,000.00 |
900,000.00 |
|
|
| 713-02-E-01 |
temporary pavement markings (24" width) (type
1 removable) |
114   |
LNFT |
7.00 |
798.00 |
6.00 |
684.00 |
13.00 |
1,482.00 |
|
|
| 713-03-B-01 |
temporary pvmt. markings (broken line)(4" width) (10'
length) (type i removable) |
0.039 |
MILE |
4,500.00 |
175.50 |
4,400.00 |
171.60 |
3,500.00 |
136.50 |
|
|
| 713-04-A-01 |
temporary pavement markings (solid line)(4" width)
(type i removable) |
11.209 |
MILE |
7,500.00 |
84,067.50 |
7,000.00 |
78,463.00 |
13,000.00 |
145,717.00 |
|
|
| 716-01-A |
mulch (vegetative)
|
43.3 |
TON |
350.00 |
15,155.00 |
450.00 |
19,485.00 |
800.00 |
34,640.00 |
|
|
| 717-01 |
seeding
|
649   |
LB |
7.50 |
4,867.50 |
8.00 |
5,192.00 |
11.00 |
7,139.00 |
|
|
| 718-01 |
fertilizier
|
21,630   |
LB |
0.50 |
10,815.00 |
0.45 |
9,733.50 |
0.35 |
7,570.50 |
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
40,000.00 |
40,000.00 |
20,000.00 |
20,000.00 |
35,000.00 |
35,000.00 |
|
|
| 725-01 |
temporary detour roads
|
4,039.5 |
SQYD |
70.00 |
282,765.00 |
65.00 |
262,567.50 |
75.00 |
302,962.50 |
|
|
| 726-01 |
bedding material
|
664.6 |
CUYD |
72.00 |
47,851.20 |
100.00 |
66,460.00 |
110.00 |
73,106.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
1,250,000.00 |
1,250,000.00 |
1,900,000.00 |
1,900,000.00 |
2,290,000.00 |
2,290,000.00 |
|
|
| 729-01-A |
sign (type a) (ground mounted)(w3-3) (36"x36")
|
36.0 |
SQFT |
60.00 |
2,160.00 |
55.00 |
1,980.00 |
60.00 |
2,160.00 |
|
|
| 729-06-A |
sign (overhead mounted)(type a)(r10-12)(24"x30")
|
20.0 |
SQFT |
60.00 |
1,200.00 |
55.00 |
1,100.00 |
60.00 |
1,200.00 |
|
|
| 729-06-B |
sign (overhead mounted) (type a)(r3-5l) (30"x36")
|
30.0 |
SQFT |
60.00 |
1,800.00 |
55.00 |
1,650.00 |
60.00 |
1,800.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
28   |
EACH |
60.00 |
1,680.00 |
60.00 |
1,680.00 |
160.00 |
4,480.00 |
|
|
| 729-21 |
u-channel post
|
4   |
EACH |
100.00 |
400.00 |
100.00 |
400.00 |
100.00 |
400.00 |
|
|
| 730-08 |
electric service point (existing pole)
|
1   |
EACH |
880.00 |
880.00 |
1,000.00 |
1,000.00 |
800.00 |
800.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
3,778   |
EACH |
5.50 |
20,779.00 |
5.50 |
20,779.00 |
6.00 |
22,668.00 |
|
|
| 732-01-A |
plastic pavement striping (4" width)
|
67,319   |
LNFT |
0.50 |
33,659.50 |
0.48 |
32,313.12 |
0.70 |
47,123.30 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
2,285   |
LNFT |
1.20 |
2,742.00 |
1.10 |
2,513.50 |
1.35 |
3,084.75 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
2,019   |
LNFT |
5.00 |
10,095.00 |
4.50 |
9,085.50 |
4.50 |
9,085.50 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
7.654 |
MILE |
925.00 |
7,079.95 |
830.00 |
6,352.82 |
1,100.00 |
8,419.40 |
|
|
| 732-03-C |
plastic pavement striping (broken line)(8" width)
|
0.738 |
MILE |
1,800.00 |
1,328.40 |
1,600.00 |
1,180.80 |
5,000.00 |
3,690.00 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
73   |
EACH |
225.00 |
16,425.00 |
220.00 |
16,060.00 |
250.00 |
18,250.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
31   |
EACH |
225.00 |
6,975.00 |
220.00 |
6,820.00 |
250.00 |
7,750.00 |
|
|
| 732-04-E |
plastic pavement legends & symbols (school crossing)
|
2   |
EACH |
400.00 |
800.00 |
400.00 |
800.00 |
450.00 |
900.00 |
|
|
| 732-05 |
removal of existing markings
|
0.068 |
MILE |
5,500.00 |
374.00 |
5,200.00 |
353.60 |
6,000.00 |
408.00 |
|
|
| 735-01 |
mailboxes
|
21   |
EACH |
5.00 |
105.00 |
1.00 |
21.00 |
14.00 |
294.00 |
|
|
| 735-02 |
mailbox supports (single)
|
21   |
EACH |
175.00 |
3,675.00 |
140.00 |
2,940.00 |
300.00 |
6,300.00 |
|
|
| 736-01 |
trenching and backfilling
|
910   |
LNFT |
4.25 |
3,867.50 |
4.00 |
3,640.00 |
4.00 |
3,640.00 |
|
|
| 736-03-A |
jacked or bored conduit (2" pec, schedule 80)
|
20   |
LNFT |
25.00 |
500.00 |
21.00 |
420.00 |
23.00 |
460.00 |
|
|
| 736-03-B |
jacked or bored conduit (3" pec, schedule 80)
|
460   |
LNFT |
30.00 |
13,800.00 |
26.00 |
11,960.00 |
30.00 |
13,800.00 |
|
|
| 736-04-B |
signal support (50' mast arm)
|
2   |
EACH |
12,000.00 |
24,000.00 |
11,000.00 |
22,000.00 |
12,000.00 |
24,000.00 |
|
|
| 736-04-C |
signal support (55' mast arm)
|
2   |
EACH |
12,000.00 |
24,000.00 |
11,000.00 |
22,000.00 |
13,000.00 |
26,000.00 |
|
|
| 736-05-B |
signal heads (3 section, 12" lenses, ryg)
|
8   |
EACH |
1,400.00 |
11,200.00 |
1,210.00 |
9,680.00 |
1,400.00 |
11,200.00 |
|
|
| 736-05-C |
signal heads (5 section, 12" led lenses, r, left y,y,
left g,g) |
4   |
EACH |
2,400.00 |
9,600.00 |
2,100.00 |
8,400.00 |
2,400.00 |
9,600.00 |
|
|
| 736-06-A |
signal service (pedestal required)
|
1   |
EACH |
2,500.00 |
2,500.00 |
2,100.00 |
2,100.00 |
2,500.00 |
2,500.00 |
|
|
| 736-08-A |
signal controller (ts-2, type 2 in type 6 cabinet)
|
1   |
EACH |
24,000.00 |
24,000.00 |
21,000.00 |
21,000.00 |
24,000.00 |
24,000.00 |
|
|
| 736-09 |
loop detector
|
180   |
LNFT |
15.00 |
2,700.00 |
12.00 |
2,160.00 |
13.00 |
2,340.00 |
|
|
| 736-10-A |
underground junction box (type d)
|
4   |
EACH |
12.00 |
48.00 |
10.00 |
40.00 |
12.00 |
48.00 |
|
|
| 736-10-B |
underground junction box (type e)
|
4   |
EACH |
500.00 |
2,000.00 |
430.00 |
1,720.00 |
500.00 |
2,000.00 |
|
|
| 736-10-C |
underground junction box (type f)
|
3   |
EACH |
650.00 |
1,950.00 |
560.00 |
1,680.00 |
600.00 |
1,800.00 |
|
|
| 736-10-D |
underground junction box (type h)
|
1   |
EACH |
1,300.00 |
1,300.00 |
1,200.00 |
1,200.00 |
1,200.00 |
1,200.00 |
|
|
| 736-11-A |
conduit (1/2" pec, schedule 80)
|
45   |
LNFT |
1.15 |
51.75 |
1.00 |
45.00 |
1.10 |
49.50 |
|
|
| 736-11-B |
conduit (1" pec, schedule 80)
|
620   |
LNFT |
1.25 |
775.00 |
1.20 |
744.00 |
1.35 |
837.00 |
|
|
| 736-11-C |
conduit (2" pec, schedule 80)
|
165   |
LNFT |
1.50 |
247.50 |
1.40 |
231.00 |
1.50 |
247.50 |
|
|
| 736-12-A |
conductor 2c (#14 awg stranded, imsa 50-2)
|
940   |
LNFT |
1.30 |
1,222.00 |
1.10 |
1,034.00 |
1.15 |
1,081.00 |
|
|
| 736-12-B |
conductor 3c,(power, 6 gauge/#6 awg)
|
150   |
LNFT |
4.00 |
600.00 |
3.60 |
540.00 |
4.00 |
600.00 |
|
|
| 736-12-C |
conductor (6c, signal #14 awg)
|
1,580   |
LNFT |
1.60 |
2,528.00 |
1.40 |
2,212.00 |
1.50 |
2,370.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
290,000.00 |
290,000.00 |
300,000.00 |
300,000.00 |
350,000.00 |
350,000.00 |
|
|
| 741-09 |
adjusting water house connections
|
55   |
EACH |
200.00 |
11,000.00 |
400.00 |
22,000.00 |
325.00 |
17,875.00 |
|
|
| 741-10 |
adjusting water service lines
|
660   |
LNFT |
5.00 |
3,300.00 |
30.00 |
19,800.00 |
18.00 |
11,880.00 |
|
|
| 803-05 |
temporary sheeting
|
lump |
LUMP |
6,500.00 |
6,500.00 |
1,000.00 |
1,000.00 |
110,000.00 |
110,000.00 |
|
|
| 805-01-A |
class a concrete (pipe headwalls)
|
23.85 |
CUYD |
1,228.82 |
29,307.36 |
1,300.00 |
31,005.00 |
1,000.00 |
23,850.00 |
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
47.08 |
CUYD |
1,000.00 |
47,080.00 |
1,300.00 |
61,204.00 |
1,300.00 |
61,204.00 |
|
|
| 805-12-E |
reinforced concrete box culverts (4'x 4') (3 barrels)
|
198.0 |
LNFT |
400.00 |
79,200.00 |
270.00 |
53,460.00 |
375.00 |
74,250.00 |
|
|
| 805-12-P |
reinforced concrete box culverts (7'x 7') (2 barrels)
|
358.0 |
LNFT |
575.00 |
205,850.00 |
500.00 |
179,000.00 |
600.00 |
214,800.00 |
|
|
| 806-01 |
deformed reinforcing steel
|
4,973   |
LB |
2.00 |
9,946.00 |
2.20 |
10,940.60 |
3.25 |
16,162.25 |
|
|
| S-001 |
cleaning existing ditches
|
2,000   |
LNFT |
10.00 |
20,000.00 |
16.00 |
32,000.00 |
12.00 |
24,000.00 |
|
|
| S-003 |
reinforced concrete support pads for storm drain pipe
|
121.3 |
SQYD |
55.00 |
6,671.50 |
90.00 |
10,917.00 |
75.00 |
9,097.50 |
|
|
| S-004 |
video detection system
|
1.0 |
EACH |
4,400.00 |
4,400.00 |
4,000.00 |
4,000.00 |
4,500.00 |
4,500.00 |
|
|
| S-005 |
video detection device and connection
|
4.0 |
EACH |
7,000.00 |
28,000.00 |
6,500.00 |
26,000.00 |
7,000.00 |
28,000.00 |
|
|
| S-006 |
sawcutting of existing hardsurfacing
|
16,579.0 |
INFT |
1.50 |
24,868.50 |
2.00 |
33,158.00 |
1.10 |
18,236.90 |
|
|
| S-007 |
dynamic message sign unit
|
2.0 |
EACH |
12,500.00 |
25,000.00 |
20,000.00 |
40,000.00 |
22,000.00 |
44,000.00 |
|
|
| | SUBTOTAL GENERAL |
|
|
|
11,902,951.90 |
|
13,522,193.60 |
|
16,608,271.81 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A |
pavement options
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A1 |
portland cement concrete pavement
|
|
|
|
|
|
|
|
|
|
|
| 502-01-A-01 |
superpave asphaltic concrete,drives,turnouts and misc.
(alternate a1) |
731.1 |
TON |
150.00 |
109,665.00 |
150.00 |
109,665.00 |
0.00 |
0.00 |
|
|
| 502-01-01 |
superpave asphaltic concrete (alternate a1)
|
7,699.0 |
TON |
100.00 |
769,900.00 |
100.00 |
769,900.00 |
0.00 |
0.00 |
|
|
| 601-01-K-01 |
portland cement concrete pavement (10" thick)
(alternate a1) |
98,081.4 |
SQYD |
52.00 |
5,100,232.80 |
49.00 |
4,805,988.60 |
0.00 |
0.00 |
|
|
| 601-02-K-01 |
portland cement concrete pavement (10" thick)
(crossovers & turnouts) (alternate a1) |
4,870.5 |
SQYD |
69.00 |
336,064.50 |
60.00 |
292,230.00 |
0.00 |
0.00 |
|
|
| 707-01-01 |
concrete curb (alternate a1)
|
13,451.6 |
LNFT |
5.00 |
67,258.00 |
5.00 |
67,258.00 |
0.00 |
0.00 |
|
|
| S-008-01 |
portland cement concrete pavement (10" thick)
(0.40 water / cement ratio, 658 lb / cy type 1) (alternate a1) |
770.0 |
SQYD |
70.00 |
53,900.00 |
90.00 |
69,300.00 |
0.00 |
0.00 |
|
|
| | SUBTOTAL ALT A1 |
|
|
|
6,437,020.30 |
|
6,114,341.60 |
|
|
|
|
| |
(alternate a1) |
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A2 |
superpave asphaltic concrete pavement
(alternate a1) |
|
|
|
|
|
|
|
|
|
|
| 502-01-A-02 |
superpave asphaltic concrete,drives,turnouts and
misc.(alternate a2) |
3,026.1 |
TON |
0.00 |
0.00 |
0.00 |
0.00 |
110.00 |
332,871.00 |
|
|
| 502-01-02 |
superpave asphaltic concrete (alternate a2)
|
62,948.9 |
TON |
0.00 |
0.00 |
0.00 |
0.00 |
90.00 |
5,665,401.00 |
|
|
| 601-02-K-02 |
portland cement concrete pavement (10" thick)
(crossovers & turnouts) (alternate a2) |
721.4 |
SQYD |
0.00 |
0.00 |
0.00 |
0.00 |
80.00 |
57,712.00 |
|
|
| 707-03-02 |
combination concrete curb and gutter (alternate a2)
|
13,451.6 |
LNFT |
0.00 |
0.00 |
0.00 |
0.00 |
20.00 |
269,032.00 |
|
|
| | SUBTOTAL ALT A2 |
|
|
|
|
|
|
|
6,325,016.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
18,339,972.20 |
|
19,636,535.20 |
|
22,933,287.81 |
|
|
| | NUMBER OF DAYS BID AT $3,000 PER DAY. |
|
|
|
1,215,000.00 |
|
1,350,000.00 |
|
1,800,000.00 |
|
|
| | LIFE CYCLE COST |
|
|
|
366,100.00 |
|
366,100.00 |
|
1,515,600.00 |
|
|
| | TOTAL BID |
|
|
|
19,921,072.20 |
|
21,352,635.20 |
|
26,248,887.81 |
|
|
|