| DBE GOAL FED |
| Lead Project: 737-90-0065 |
| Parish: LIVINGSTON, ST TAMMANY, TANGIPAHOA |
| Routes: I-12, I-55, I-59 |
| Description: DISTRICT 62 BRIDGE PREVENTIVE MAINTENANCE PROJECT |
| Type Const:
cleaning and sealing bridge deck joints, and related work.
|
| Estimated Construction Cost: $1,032,810.64 |
|
| Rank | License | Bidder | Construction Bid |
| 1 | 25652 |
TOPCOR SERVICES, INC | $377,031.00 |
| 2 | 21982 |
FORBY CONTRACTING, INC. | $580,855.00 |
| 3 | 46547 |
INTERSTATE IMPROVEMENT, INC. | $1,095,720.50 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - TOPCOR SERVICES, INC |
- 2 - FORBY CONTRACTING, INC. |
- 3 - INTERSTATE IMPROVEMENT, INC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 602-02 |
cleaning and resealing existing longitudinal and
transverse pavement joints |
10,921   |
LNFT |
15.00 |
163,815.00 |
15.00 |
163,815.00 |
28.50 |
311,248.50 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
35,000.00 |
35,000.00 |
80,000.00 |
80,000.00 |
145,000.00 |
145,000.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
35,000.00 |
35,000.00 |
50,000.00 |
50,000.00 |
120,000.00 |
120,000.00 |
|
|
| 805-09 |
expansion joint seal
|
10,921.60 |
LNFT |
10.00 |
109,216.00 |
25.00 |
273,040.00 |
45.00 |
491,472.00 |
|
|
| S-001 |
dynamic message sign unit
|
4   |
each |
8,500.00 |
34,000.00 |
3,500.00 |
14,000.00 |
7,000.00 |
28,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
377,031.00 |
|
580,855.00 |
|
1,095,720.50 |
|
|
|