Letting of 5/20/2009 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 713-37-0126
Parish: OUACHITA
Routes:
Description: CAPLES ROAD BRIDGE OVER LONGS CREEK AND SAM HEAD ROAD BRIDGE
Type Const: grading, drainage structures, class ii base course, superpave asphaltic concrete
pavement, concrete slab span bridge, and related work.
Estimated Construction Cost: $794,924.60
 
RankLicenseBidderConstruction Bid
1 39580 GERACE CONSTRUCTION LLC $798,393.00
2 18546 C W & W CONTRACTORS, INC. $798,556.00
3 49864 TERRAL CONSTRUCTION L.L.C.� $799,993.93
4 23112 BEN ALLEN, INC. $830,809.20
5 12136 SHILOH CONTRACTORS, INC. $877,829.50
6 09090 GUINN BROTHERS, LLC. $1,132,854.75
 
Item Number Item Description Quantity Unit of Measure - 1 -
GERACE CONSTRUCTION LLC
- 2 -
C W & W CONTRACTORS, INC.
- 3 -
TERRAL CONSTRUCTION L.L.C.�
- 4 -
BEN ALLEN, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 8,500.00 8,500.00 20,000.00 20,000.00 7,205.00 7,205.00 20,000.00 20,000.00
202-02-A-01 removal of bridge (sta. 100+00, 23.04' wide x 62.11'
long timber bridge wit h wingwalls)
1      EACH 8,500.00 8,500.00 7,500.00 7,500.00 5,780.00 5,780.00 5,000.00 5,000.00
202-02-A-02 removal of bridge (sta. 100+00, 19.06' wide x 45.80'
long timber bridge)
1      EACH 6,500.00 6,500.00 7,500.00 7,500.00 5,780.00 5,780.00 5,000.00 5,000.00
202-02-G removal of surfacing & stabilized base 928.4    SQYD 10.00 9,284.00 5.00 4,642.00 10.24 9,506.82 8.00 7,427.20
203-05 excavation and embankment lump      LUMP 55,000.00 55,000.00 35,000.00 35,000.00 45,000.00 45,000.00 65,000.00 65,000.00
204-02 temporary hay or straw bales 30      EACH 20.00 600.00 10.00 300.00 10.00 300.00 0.00 0.00
204-03 temporary slope drains 200      LNFT 5.00 1,000.00 10.00 2,000.00 1.00 200.00 0.00 0.00
204-05-A temporary sediment check dams (hay) 8      EACH 100.00 800.00 100.00 800.00 100.00 800.00 0.00 0.00
204-06 temporary silt fencing 535      LNFT 2.50 1,337.50 3.00 1,605.00 2.00 1,070.00 3.00 1,605.00
302-01 class ii base course 276.3    CUYD 125.00 34,537.50 100.00 27,630.00 112.36 31,045.07 130.00 35,919.00
401-02 aggregate surface course (adjusted vehicular
measurement)
9      CUYD 100.00 900.00 100.00 900.00 112.36 1,011.24 130.00 1,170.00
502-01 superpave asphaltic concrete 215.8    TON 250.00 53,950.00 200.00 43,160.00 290.00 62,582.00 200.00 43,160.00
704-03 blocked out guard rail 50.0    LNFT 25.00 1,250.00 30.00 1,500.00 25.00 1,250.00 25.00 1,250.00
704-08-B guard rail transitions (double thrie beam) 100.0    LNFT 55.00 5,500.00 80.00 8,000.00 60.00 6,000.00 66.00 6,600.00
704-11-A guard rail end treatment (flared) 4      EACH 2,500.00 10,000.00 3,000.00 12,000.00 2,500.00 10,000.00 2,500.00 10,000.00
705-01 barbed wire fence 145      LNFT 10.00 1,450.00 15.00 2,175.00 12.00 1,740.00 15.00 2,175.00
711-01-C riprap (30 lb, 14" thick) 546      SQYD 75.00 40,950.00 90.00 49,140.00 60.00 32,760.00 85.00 46,410.00
711-04 geotextile fabric 546      SQYD 1.00 546.00 3.00 1,638.00 2.00 1,092.00 3.00 1,638.00
713-01 temporary signs & barricades lump      LUMP 15,000.00 15,000.00 18,000.00 18,000.00 12,000.00 12,000.00 12,000.00 12,000.00
716-01-A mulch (vegetative) 0.7    TON 1,000.00 700.00 4,000.00 2,800.00 1,500.00 1,050.00 1,000.00 700.00
717-01 seeding 16      LB 10.00 160.00 50.00 800.00 12.00 192.00 25.00 400.00
718-01 fertilizer 360      LB 0.50 180.00 5.00 1,800.00 1.00 360.00 2.00 720.00
726-01 bedding material 110.6    CUYD 100.00 11,060.00 125.00 13,825.00 300.00 33,180.00 130.00 14,378.00
727-01 mobilization lump      LUMP 75,000.00 75,000.00 60,000.00 60,000.00 50,000.00 50,000.00 75,000.00 75,000.00
729-16-B object marker assembly (type 2) 4      EACH 80.00 320.00 100.00 400.00 100.00 400.00 75.00 300.00
729-16-C object marker assembly (type 3) 4      EACH 80.00 320.00 100.00 400.00 100.00 400.00 95.00 380.00
740-01 construction layout lump      LUMP 25,000.00 25,000.00 12,000.00 12,000.00 8,000.00 8,000.00 10,000.00 10,000.00
804-01-B precast concrete piles (14") 840      LNFT 75.00 63,000.00 105.00 88,200.00 78.00 65,520.00 75.00 63,000.00
804-12 loading permanent piles 1      EACH 500.00 500.00 1.00 1.00 1.00 1.00 0.00 0.00
805-01-B class a concrete (box culvert headwalls) 54.97   CUYD 1,200.00 65,964.00 1,200.00 65,964.00 720.00 39,578.40 1,300.00 71,461.00
805-10-A bridge superstructure & substructure (28' clr. rdwy;
90 deg. xing, precast only)
4      SPAN 34,000.00 136,000.00 30,000.00 120,000.00 44,750.00 179,000.00 39,000.00 156,000.00
805-12-W-01 reinforced concrete box culverts (10'x 9') 120.0    LNFT 1,100.00 132,000.00 1,300.00 156,000.00 1,342.00 161,040.00 1,152.00 138,240.00
806-01 deformed reinforcing steel 4,292      LB 2.00 8,584.00 3.00 12,876.00 1.20 5,150.40 3.00 12,876.00
S-101 concrete approach slabs (28' clr. rdwy; 90 deg. xing,
without asphalt)
2      EACH 12,000.00 24,000.00 10,000.00 20,000.00 10,500.00 21,000.00 11,500.00 23,000.00
                       
 CONTRACTOR TOTAL       798,393.00   798,556.00   799,993.93   830,809.20
 
Item Number Item Description Quantity Unit of Measure - 5 -
SHILOH CONTRACTORS, INC.
- 6 -
GUINN BROTHERS, LLC.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 20,000.00 20,000.00 50,000.00 50,000.00        
202-02-A-01 removal of bridge (sta. 100+00, 23.04' wide x 62.11'
long timber bridge wit h wingwalls)
1      EACH 8,000.00 8,000.00 20,000.00 20,000.00        
202-02-A-02 removal of bridge (sta. 100+00, 19.06' wide x 45.80'
long timber bridge)
1      EACH 7,000.00 7,000.00 18,500.00 18,500.00        
202-02-G removal of surfacing & stabilized base 928.4    SQYD 5.00 4,642.00 10.00 9,284.00        
203-05 excavation and embankment lump      LUMP 72,000.00 72,000.00 55,000.00 55,000.00        
204-02 temporary hay or straw bales 30      EACH 10.00 300.00 50.00 1,500.00        
204-03 temporary slope drains 200      LNFT 1.00 200.00 10.00 2,000.00        
204-05-A temporary sediment check dams (hay) 8      EACH 40.00 320.00 250.00 2,000.00        
204-06 temporary silt fencing 535      LNFT 3.00 1,605.00 5.00 2,675.00        
302-01 class ii base course 276.3    CUYD 85.00 23,485.50 130.00 35,919.00        
401-02 aggregate surface course (adjusted vehicular
measurement)
9      CUYD 100.00 900.00 250.00 2,250.00        
502-01 superpave asphaltic concrete 215.8    TON 185.00 39,923.00 400.00 86,320.00        
704-03 blocked out guard rail 50.0    LNFT 20.00 1,000.00 30.00 1,500.00        
704-08-B guard rail transitions (double thrie beam) 100.0    LNFT 60.00 6,000.00 70.00 7,000.00        
704-11-A guard rail end treatment (flared) 4      EACH 2,250.00 9,000.00 3,000.00 12,000.00        
705-01 barbed wire fence 145      LNFT 12.00 1,740.00 25.00 3,625.00        
711-01-C riprap (30 lb, 14" thick) 546      SQYD 65.00 35,490.00 100.00 54,600.00        
711-04 geotextile fabric 546      SQYD 3.00 1,638.00 5.00 2,730.00        
713-01 temporary signs & barricades lump      LUMP 15,000.00 15,000.00 25,000.00 25,000.00        
716-01-A mulch (vegetative) 0.7    TON 1,000.00 700.00 7,200.00 5,040.00        
717-01 seeding 16      LB 1.00 16.00 25.00 400.00        
718-01 fertilizer 360      LB 1.00 360.00 1.00 360.00        
726-01 bedding material 110.6    CUYD 85.00 9,401.00 130.00 14,378.00        
727-01 mobilization lump      LUMP 146,000.00 146,000.00 148,000.00 148,000.00        
729-16-B object marker assembly (type 2) 4      EACH 85.00 340.00 100.00 400.00        
729-16-C object marker assembly (type 3) 4      EACH 85.00 340.00 100.00 400.00        
740-01 construction layout lump      LUMP 9,000.00 9,000.00 15,000.00 15,000.00        
804-01-B precast concrete piles (14") 840      LNFT 65.00 54,600.00 68.00 57,120.00        
804-12 loading permanent piles 1      EACH 1.00 1.00 1.00 1.00        
805-01-B class a concrete (box culvert headwalls) 54.97   CUYD 1,600.00 87,952.00 1,875.00 103,068.75        
805-10-A bridge superstructure & substructure (28' clr. rdwy;
90 deg. xing, precast only)
4      SPAN 26,000.00 104,000.00 45,000.00 180,000.00        
805-12-W-01 reinforced concrete box culverts (10'x 9') 120.0    LNFT 1,600.00 192,000.00 1,485.00 178,200.00        
806-01 deformed reinforcing steel 4,292      LB 3.00 12,876.00 2.00 8,584.00        
S-101 concrete approach slabs (28' clr. rdwy; 90 deg. xing,
without asphalt)
2      EACH 6,000.00 12,000.00 15,000.00 30,000.00        
                       
 CONTRACTOR TOTAL       877,829.50   1,132,854.75        