| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC |
- 2 - BOH BROS. CONSTRUCTION CO., LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
600   |
SQYD |
18.00 |
10,800.00 |
16.00 |
9,600.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
2,000   |
LNFT |
0.50 |
1,000.00 |
2.00 |
4,000.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
800.0 |
CUYD |
18.00 |
14,400.00 |
15.00 |
12,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
42,520.6 |
TON |
77.00 |
3,274,086.20 |
95.00 |
4,039,457.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
2,019.1 |
TON |
145.00 |
292,769.50 |
95.00 |
191,814.50 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
289,219   |
SQYD |
2.00 |
578,438.00 |
4.00 |
1,156,876.00 |
|
|
|
|
| 510-01-C |
pavement patching (18" minimum depth)
|
3,643   |
SQYD |
100.00 |
364,300.00 |
190.00 |
692,170.00 |
|
|
|
|
| 602-02 |
cleaning and resealing existing longitudinal and
transverse pavement joints |
1,400   |
LNFT |
4.50 |
6,300.00 |
5.00 |
7,000.00 |
|
|
|
|
| 701-03-I |
storm drain pipe (24" rcp)
|
42   |
LNFT |
200.00 |
8,400.00 |
230.00 |
9,660.00 |
|
|
|
|
| 701-03-K |
storm drain pipe (30" rcp)
|
24   |
LNFT |
250.00 |
6,000.00 |
520.00 |
12,480.00 |
|
|
|
|
| 706-01-A |
concrete walk (4" thick)
|
600.0 |
SQYD |
77.00 |
46,200.00 |
65.00 |
39,000.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
575,000.00 |
575,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
20.890 |
MILE |
150.00 |
3,133.50 |
200.00 |
4,178.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
12.302 |
MILE |
150.00 |
1,845.30 |
200.00 |
2,460.40 |
|
|
|
|
| 713-05-E |
temporary pavement legends and symbols (school
crossing) |
5   |
EACH |
50.00 |
250.00 |
50.00 |
250.00 |
|
|
|
|
| 714-01 |
slab sodding
|
200   |
SQYD |
12.00 |
2,400.00 |
20.00 |
4,000.00 |
|
|
|
|
| 717-01 |
seeding
|
1,000   |
LB |
6.00 |
6,000.00 |
7.00 |
7,000.00 |
|
|
|
|
| 718-01 |
fertilizer
|
1,000   |
LB |
1.00 |
1,000.00 |
1.50 |
1,500.00 |
|
|
|
|
| 723-01 |
granular material (net section)
|
2,000   |
CUYD |
30.00 |
60,000.00 |
25.00 |
50,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
950,000.00 |
950,000.00 |
1,000,000.00 |
1,000,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
800   |
EACH |
5.00 |
4,000.00 |
5.10 |
4,080.00 |
|
|
|
|
| 732-01-B |
plastic pavement striping (6" width)
|
15,670   |
LNFT |
0.75 |
11,752.50 |
0.75 |
11,752.50 |
|
|
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
1,904   |
LNFT |
2.00 |
3,808.00 |
2.00 |
3,808.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
20.890 |
MILE |
2,350.00 |
49,091.50 |
2,350.00 |
49,091.50 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
12.302 |
MILE |
800.00 |
9,841.60 |
800.00 |
9,841.60 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
1   |
EACH |
205.00 |
205.00 |
210.00 |
210.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
215.00 |
215.00 |
215.00 |
215.00 |
|
|
|
|
| 732-04-E |
plastic pavement legends & symbols (school crossing)
|
5   |
EACH |
375.00 |
1,875.00 |
400.00 |
2,000.00 |
|
|
|
|
| 736-09 |
loop detector
|
500   |
LNFT |
12.00 |
6,000.00 |
12.00 |
6,000.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
40,000.00 |
40,000.00 |
50,000.00 |
50,000.00 |
|
|
|
|
| S-001 |
concrete walks (handicapped ramp-type a)
|
148   |
EACH |
1,900.00 |
281,200.00 |
1,600.00 |
236,800.00 |
|
|
|
|
| S-002 |
concrete walks (handicapped ramp-type b)
|
126   |
EACH |
1,900.00 |
239,400.00 |
1,600.00 |
201,600.00 |
|
|
|
|
| S-004 |
reconstruction of concrete curb and gutterbottom
(barrier curb) |
4,295   |
LNFT |
92.00 |
395,140.00 |
43.00 |
184,685.00 |
|
|
|
|
| S-005 |
reconstruction of concrete curb and gutterbottom
(mountable curb) |
55   |
LNFT |
90.00 |
4,950.00 |
78.00 |
4,290.00 |
|
|
|
|
| S-007 |
doweled barrier concrete curb
|
2,847   |
LNFT |
28.00 |
79,716.00 |
15.00 |
42,705.00 |
|
|
|
|
| S-007A |
doweled mountable concrete curb
|
1,897   |
LNFT |
31.00 |
58,807.00 |
15.00 |
28,455.00 |
|
|
|
|
| S-008 |
concrete pavement repair (18.0 sq.yd and under)
|
1,120.1 |
SQYD |
185.00 |
207,218.50 |
250.00 |
280,025.00 |
|
|
|
|
| S-009 |
concrete pavement repair (18.1 sq.yd. to 48.0 sq.yd.)
|
2,793.8 |
SQYD |
141.00 |
393,925.80 |
185.00 |
516,853.00 |
|
|
|
|
| S-010 |
concrete pavement repair (48.1 sq.yd and over)
|
11,361.9 |
SQYD |
117.00 |
1,329,342.30 |
160.00 |
1,817,904.00 |
|
|
|
|
| S-011 |
tree protection
|
lump |
LUMP |
20,000.00 |
20,000.00 |
1,200.00 |
1,200.00 |
|
|
|
|
| S-012 |
tree trimming
|
lump |
LUMP |
18,000.00 |
18,000.00 |
30,000.00 |
30,000.00 |
|
|
|
|
| S-013 |
root pruining
|
lump |
LUMP |
6,500.00 |
6,500.00 |
1,000.00 |
1,000.00 |
|
|
|
|
| S-014 |
hand formed and poured in-place concrete curb within
the limits of the tree dripline |
100   |
LNFT |
71.00 |
7,100.00 |
78.00 |
7,800.00 |
|
|
|
|
| S-015 |
gravel bed and filter cloth over tree roots
|
100   |
SQYD |
25.00 |
2,500.00 |
20.00 |
2,000.00 |
|
|
|
|
| S-016A |
catch basin adjustment type a
|
18   |
EACH |
2,200.00 |
39,600.00 |
1,200.00 |
21,600.00 |
|
|
|
|
| S-017 |
manhole adjustment
|
31   |
EACH |
1,400.00 |
43,400.00 |
1,700.00 |
52,700.00 |
|
|
|
|
| S-017A |
drain and water manhole adjustment with rings
|
15   |
EACH |
350.00 |
5,250.00 |
1,700.00 |
25,500.00 |
|
|
|
|
| S-017B |
sewer manhole adjustment with rings
|
15   |
EACH |
350.00 |
5,250.00 |
700.00 |
10,500.00 |
|
|
|
|
| S-019 |
reset drainage manhole and cover
|
7   |
EACH |
1,400.00 |
9,800.00 |
1,700.00 |
11,900.00 |
|
|
|
|
| S-023 |
catch basin frame and cover
|
11   |
EACH |
2,600.00 |
28,600.00 |
1,700.00 |
18,700.00 |
|
|
|
|
| S-024 |
submerged roads program project sign
|
8   |
EACH |
600.00 |
4,800.00 |
500.00 |
4,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
9,509,610.70 |
|
10,980,661.50 |
|
|
|
|
| | NUMBER OF DAYS BID AT $5,000 PER DAY. |
|
|
|
1,000,000.00 |
|
1,250,000.00 |
|
|
|
|
| | TOTAL BID |
|
|
|
10,509,610.70 |
|
12,230,661.50 |
|
|
|
|
|