DBE GOAL FED
Lead Project: 149-01-0012
Parish: RAPIDES
Routes: LA 623
Description: HICKORY HILL EXTENSION
Type Const: grading, drainage structures, class ii base course, superpave asphaltic concrete
pavement, pcc pavement, precast concrete girder bridge and related work
Estimated Construction Cost: $10,132,608.35
 
RankLicenseBidderConstruction Bid
1 34567 JAMES CONSTRUCTION GROUP LLC $7,829,259.09
2 12312 GILCHRIST CONSTRUCTION CO. LLC $8,290,939.03
3 39462 JB JAMES CONSTRUCTION LLC $8,620,180.78
4 14422 T. L. WALLACE CONSTRUCTION, INC. $8,915,428.01
 
Item Number Item Description Quantity Unit of Measure - 1 -
JAMES CONSTRUCTION GROUP LLC
- 2 -
GILCHRIST CONSTRUCTION CO. LLC
- 3 -
JB JAMES CONSTRUCTION LLC
- 4 -
T. L. WALLACE CONSTRUCTION, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 500,000.00 500,000.00 225,000.00 225,000.00 600,000.00 600,000.00 135,000.00 135,000.00
202-01 removal of structures & obstructions lump      LUMP 90,000.00 90,000.00 25,000.00 25,000.00 52,000.00 52,000.00 35,000.00 35,000.00
202-02-D removal of concrete walks & drives 1,243      SQYD 6.00 7,458.00 8.00 9,944.00 10.00 12,430.00 3.00 3,729.00
202-02-F removal of combination curb & gutter 202.0    LNFT 5.00 1,010.00 14.00 2,828.00 7.00 1,414.00 3.75 757.50
202-02-G removal of surfacing & stabilized base 7,394.7    SQYD 1.10 8,134.17 7.00 51,762.90 3.40 25,141.98 5.00 36,973.50
202-02-01 removal of building (wood frame residence on piers;
lt.of sta.117+56; 25'x 40'
1      EACH 1,800.00 1,800.00 100.00 100.00 1.00 1.00 5,000.00 5,000.00
202-02-02 removal of building (wood frame shed on dirt; lt. of
sta. 118+00;10'x10')
1      EACH 150.00 150.00 100.00 100.00 1.00 1.00 600.00 600.00
202-02-03 removal of building (wood frame residence on piers;lt.
of sta.122+00; 35'x50')
1      EACH 3,000.00 3,000.00 100.00 100.00 1.00 1.00 5,000.00 5,000.00
202-02-04 removal of building (wood frame garage on dirt;lt. of
sta.122+25; 20'x 28')
1      EACH 800.00 800.00 100.00 100.00 1.00 1.00 1,500.00 1,500.00
202-02-05 removal of sign (rt. of sta. 52+50; 1'x2' metal drug
free zone sign)
1      EACH 50.00 50.00 50.00 50.00 1.00 1.00 50.00 50.00
202-02-06 removal of sign (rt. of sta. 52+50; 1'x 2' metal fire
arm free zone sign)
1      EACH 50.00 50.00 50.00 50.00 1.00 1.00 50.00 50.00
202-02-07 removal of sign (rt. of sta. 52+55; 8' x 10' on slab
foundation)
1      EACH 400.00 400.00 50.00 50.00 1.00 1.00 1,500.00 1,500.00
202-02-08 removal of sign (rt. of sta. 52+60; 1'x 2' metal no
parking sign)
1      EACH 50.00 50.00 50.00 50.00 1.00 1.00 50.00 50.00
202-02-09 removal of sign (lt. of sta. 141+60; 1' x 2' metal
sign)
1      EACH 50.00 50.00 50.00 50.00 1.00 1.00 50.00 50.00
203-01 general excavation 8,674      CUYD 6.00 52,044.00 7.25 62,886.50 12.00 104,088.00 7.25 62,886.50
203-03 embankment 33,719      CUYD 12.00 404,628.00 17.25 581,652.75 15.00 505,785.00 17.75 598,512.25
204-02 temporary hay or straw bales 200      EACH 15.00 3,000.00 22.00 4,400.00 10.00 2,000.00 21.25 4,250.00
204-03 temporary slope drains 400      LNFT 12.00 4,800.00 15.00 6,000.00 20.00 8,000.00 4.75 1,900.00
204-05-A temporary sediment check dams (hay) 3      EACH 170.00 510.00 400.00 1,200.00 150.00 450.00 176.50 529.50
204-05-B temporary sediment check dams (stone) 2      EACH 315.00 630.00 650.00 1,300.00 800.00 1,600.00 1,265.00 2,530.00
204-06 temporary silt fencing 4,000      LNFT 2.40 9,600.00 2.00 8,000.00 2.00 8,000.00 1.75 7,000.00
204-07 temporary stone construction entrance 2      EACH 4,000.00 8,000.00 2,500.00 5,000.00 2,500.00 5,000.00 5,882.00 11,764.00
302-02-C class ii base course (8" thick) 18,327.7    SQYD 20.00 366,554.00 20.00 366,554.00 22.00 403,209.40 33.00 604,814.10
302-02-D class ii base course (8 1/2" thick) 4,038.7    SQYD 23.00 92,890.10 22.00 88,851.40 24.00 96,928.80 34.25 138,325.48
304-01 lime 259.80   TON 165.00 42,867.00 100.00 25,980.00 150.00 38,970.00 200.00 51,960.00
304-04-D lime treatment (type d)(12" thick) 18,328      SQYD 1.00 18,328.00 2.00 36,656.00 1.50 27,492.00 4.75 87,058.00
401-01 aggregate surface course(net section) 123.2    CUYD 40.00 4,928.00 90.00 11,088.00 80.00 9,856.00 176.50 21,744.80
402-01 traffic maintenance aggregate (vehicular measurement) 1,000.0    CUYD 26.00 26,000.00 30.00 30,000.00 60.00 60,000.00 64.75 64,750.00
502-01 superpave asphaltic concrete 563.5    TON 108.00 60,858.00 135.00 76,072.50 130.00 73,255.00 159.00 89,596.50
502-01-A superpave asphaltic concrete drives, turnouts and
miscellaneous
94.5    TON 136.00 12,852.00 300.00 28,350.00 250.00 23,625.00 235.50 22,254.75
601-01-K portland cement concrete pavement (10" thick) 14,797.0    SQYD 63.00 932,211.00 65.00 961,805.00 60.00 887,820.00 64.00 947,008.00
601-02-K portland cement concrete pavement (10" thick)
(crossovers & turnouts)
2,770.3    SQYD 75.00 207,772.50 95.00 263,178.50 70.00 193,921.00 90.50 250,712.15
601-04 portland cement concrete pavement coring 30      EACH 90.00 2,700.00 130.00 3,900.00 100.00 3,000.00 77.25 2,317.50
701-01-I cross drain pipe (24" rcp/pcp) 48      LNFT 117.00 5,616.00 200.00 9,600.00 110.00 5,280.00 147.25 7,068.00
701-01-K cross drain pipe (30" rcp/pcp) 49      LNFT 144.00 7,056.00 225.00 11,025.00 130.00 6,370.00 194.25 9,518.25
701-03-F storm drain pipe (15" rcp/pcp) 4,257      LNFT 42.00 178,794.00 62.00 263,934.00 49.00 208,593.00 80.00 340,560.00
701-03-G storm drain pipe (18" rcp/pcp) 1,619      LNFT 47.00 76,093.00 72.00 116,568.00 55.00 89,045.00 86.00 139,234.00
701-03-I storm drain pipe (24" rcp/pcp) 127      LNFT 67.00 8,509.00 88.00 11,176.00 80.00 10,160.00 100.00 12,700.00
701-03-K storm drain pipe (30" rcp/pcp) 153      LNFT 82.00 12,546.00 125.00 19,125.00 95.00 14,535.00 129.50 19,813.50
701-03-M-01 storm drain pipe (36" pcp)(outfall) 10      LNFT 120.00 1,200.00 250.00 2,500.00 200.00 2,000.00 206.00 2,060.00
702-03-A catch basins (cb-01) 23      EACH 2,430.00 55,890.00 2,800.00 64,400.00 2,500.00 57,500.00 3,883.00 89,309.00
702-03-B catch basins (cb-02) 1      EACH 5,540.00 5,540.00 3,000.00 3,000.00 3,800.00 3,800.00 6,471.00 6,471.00
702-03-C catch basins (cb-06) 33      EACH 4,800.00 158,400.00 4,000.00 132,000.00 4,000.00 132,000.00 6,471.00 213,543.00
702-03-D catch basins (cb-07) 11      EACH 5,200.00 57,200.00 5,500.00 60,500.00 4,500.00 49,500.00 7,647.00 84,117.00
702-03-F catch basins (cb-08) 11      EACH 9,660.00 106,260.00 8,500.00 93,500.00 6,000.00 66,000.00 9,176.00 100,936.00
702-03-G catch basins (cb-09) 1      EACH 4,960.00 4,960.00 8,600.00 8,600.00 4,000.00 4,000.00 7,294.00 7,294.00
705-01 barbed wire fence 165      LNFT 8.75 1,443.75 8.00 1,320.00 9.00 1,485.00 7.25 1,196.25
705-06-A chain link fence (4-foot height) 1,448      LNFT 24.00 34,752.00 21.00 30,408.00 24.00 34,752.00 21.25 30,770.00
705-06-B chain link fence (5-foot height) 90      LNFT 26.00 2,340.00 25.00 2,250.00 26.00 2,340.00 23.75 2,137.50
705-06-C chain link fence (6-foot height) 487      LNFT 32.00 15,584.00 30.00 14,610.00 32.00 15,584.00 28.25 13,757.75
705-06-D chain link fence (7-foot height) 652      LNFT 73.00 47,596.00 32.00 20,864.00 70.00 45,640.00 33.00 21,516.00
705-07-A 4-foot single gates for chain link fence (4-foot
height)
1      EACH 950.00 950.00 800.00 800.00 1,000.00 1,000.00 588.25 588.25
705-08-A 8-foot double gates for chain link fence (4-foot
height)
2      DBGT 1,450.00 2,900.00 1,000.00 2,000.00 1,500.00 3,000.00 941.25 1,882.50
705-09-A rebuilt fence (wooden 5-foot height) 311      LNFT 20.00 6,220.00 35.00 10,885.00 20.00 6,220.00 29.50 9,174.50
705-09-B rebuilt fence (pipe 2-foot height) 219      LNFT 15.00 3,285.00 58.00 12,702.00 15.00 3,285.00 59.00 12,921.00
706-01-A concrete walk (4" thick) 4,237.6    SQYD 41.00 173,741.60 45.00 190,692.00 40.00 169,504.00 37.00 156,791.20
706-02-C concrete drive (6" thick) 1,714.7    SQYD 45.00 77,161.50 70.00 120,029.00 50.00 85,735.00 54.00 92,593.80
706-04 handicapped curb ramps 12.0    EACH 675.00 8,100.00 800.00 9,600.00 1,000.00 12,000.00 965.50 11,586.00
707-01 concrete curb 6,697.3    LNFT 1.00 6,697.30 6.25 41,858.13 6.00 40,183.80 8.50 56,927.05
708-01 right-of-way monument 62      EACH 204.55 12,682.35 350.00 21,700.00 200.00 12,400.00 223.75 13,872.50
712-01-A concrete cast-in-place revetment (4" thick) 645      SQYD 70.00 45,150.00 72.00 46,440.00 65.00 41,925.00 79.50 51,277.50
713-01 temporary signs & barricades lump      LUMP 30,000.00 30,000.00 180,000.00 180,000.00 150,000.00 150,000.00 16,000.00 16,000.00
713-02-A temporary pavement markings (4" width) 21,100      LNFT 0.25 5,275.00 0.25 5,275.00 0.25 5,275.00 0.30 6,330.00
716-01-A mulch (vegetative) 14.00   TON 490.00 6,860.00 500.00 7,000.00 500.00 7,000.00 530.00 7,420.00
717-01 seeding 140      LB 7.00 980.00 10.00 1,400.00 7.00 980.00 10.00 1,400.00
718-01 fertilizer 1,050      LB 0.80 840.00 0.80 840.00 0.80 840.00 0.40 420.00
722-01 project site laboratory 1      EACH 15,000.00 15,000.00 35,000.00 35,000.00 10,000.00 10,000.00 13,500.00 13,500.00
726-01 bedding material 300.0    CUYD 74.90 22,472.82 120.00 36,000.00 70.00 21,000.00 105.00 31,500.00
727-01 mobilization lump      LUMP 720,000.00 720,000.00 820,000.00 820,000.00 890,000.00 890,000.00 800,000.00 800,000.00
729-01 sign (type a) 12.5    SQFT 40.00 500.00 45.00 562.50 80.00 1,000.00 47.25 590.63
729-16-C object marker assembly (type 3) 2      EACH 75.00 150.00 95.00 190.00 100.00 200.00 88.25 176.50
729-19-B dead end road installations(type b)(turn installations) 2      EACH 2,200.00 4,400.00 3,500.00 7,000.00 2,500.00 5,000.00 2,600.00 5,200.00
731-02 reflectorized raised pavement markers 375      EACH 5.00 1,875.00 5.80 2,175.00 5.00 1,875.00 6.00 2,250.00
732-01-C plastic pavement striping (8" width) 1,261      LNFT 1.00 1,261.00 1.25 1,576.25 1.00 1,261.00 1.25 1,576.25
732-01-D plastic pavement striping (12" width) 363      LNFT 1.50 544.50 2.20 798.60 1.50 544.50 2.00 726.00
732-01-E plastic pavement striping (24" width) 191      LNFT 3.00 573.00 4.50 859.50 3.00 573.00 3.75 716.25
732-02-A plastic pavement striping (solid line) (4" width) 3.341  MILE 2,700.00 9,020.70 3,500.00 11,693.50 2,700.00 9,020.70 3,177.00 10,614.36
732-03-A plastic pavement striping (broken line)(4" width) 1.270  MILE 800.00 1,016.00 960.00 1,219.20 800.00 1,016.00 941.25 1,195.39
732-04-A plastic pavement legends & symbols (arrow) 25      EACH 200.00 5,000.00 230.00 5,750.00 200.00 5,000.00 235.50 5,887.50
732-04-C plastic pavement legends & symbols (only) 5      EACH 200.00 1,000.00 240.00 1,200.00 200.00 1,000.00 235.50 1,177.50
735-01 mailboxes 32      EACH 1.00 32.00 5.00 160.00 1.00 32.00 1.25 40.00
735-02 mailbox supports (single) 32      EACH 110.00 3,520.00 130.00 4,160.00 150.00 4,800.00 129.50 4,144.00
740-01 construction layout lump      LUMP 90,000.00 90,000.00 165,000.00 165,000.00 250,000.00 250,000.00 105,522.00 105,522.00
805-01-F class a concrete (bents) 533.08   CUYD 560.00 298,524.80 900.00 479,772.00 660.00 351,832.80 950.00 506,426.00
805-03 class aa concrete 1,032.60   CUYD 570.00 588,582.00 680.00 702,168.00 650.00 671,190.00 800.00 826,080.00
805-08-C precast-prestressed concrete girders (type iii) 4,021.3    LNFT 160.00 643,408.00 90.00 361,917.00 90.00 361,917.00 99.50 400,119.35
805-11 strip seal joints 224.00   LNFT 190.00 42,560.00 145.00 32,480.00 160.00 35,840.00 147.25 32,984.00
806-01 deformed reinforcing steel 404,578      LB 0.80 323,662.40 0.60 242,746.80 1.10 445,035.80 0.90 364,120.20
807-08 structural metalwork lump      LUMP 6,000.00 6,000.00 15,000.00 15,000.00 6,000.00 6,000.00 5,200.00 5,200.00
810-05 pipe & concrete railing 1,350.00   LNFT 200.00 270,000.00 130.00 175,500.00 200.00 270,000.00 199.00 268,650.00
813-01 concrete approach slabs 480.00   SQYD 220.00 105,600.00 250.00 120,000.00 240.00 115,200.00 235.50 113,040.00
814-01-B drilled shaft (24") 172.0    LNFT 100.00 17,200.00 155.00 26,660.00 135.00 23,220.00 110.00 18,920.00
814-01-M drilled shaft (42") 1,216.0    LNFT 300.00 364,800.00 300.00 364,800.00 360.00 437,760.00 300.00 364,800.00
814-02-M trial shaft (42") 61.0    LNFT 380.00 23,180.00 800.00 48,800.00 400.00 24,400.00 300.00 18,300.00
814-04-M crosshole sonic logging (42") 22      EACH 3,000.00 66,000.00 2,000.00 44,000.00 2,000.00 44,000.00 2,941.00 64,702.00
S-001 1-1/2" h.d.p.e. dr11 sewer force main (p.e. 3408)(with
14 gauge locator wire)
413      LNFT 5.80 2,395.40 11.50 4,749.50 5.00 2,065.00 7.00 2,891.00
S-002 2" h.d.p.e. dr11 sewer force main (p.e. 3408)(with
14 gauge locator wire)
3,104      LNFT 7.50 23,280.00 11.50 35,696.00 8.00 24,832.00 9.00 27,936.00
S-003 3" h.d.p.e. dr11 sewer force main (p.e. 3408)(with
14 gauge locator wire)
999      LNFT 10.55 10,539.45 12.50 12,487.50 11.00 10,989.00 12.50 12,487.50
S-004 sewage combination air/vacuum release valve assembly 1      EACH 5,580.00 5,580.00 5,200.00 5,200.00 3,000.00 3,000.00 6,565.00 6,565.00
S-005 2" flushing assembly (dead end) 1      EACH 1,460.00 1,460.00 1,800.00 1,800.00 1,200.00 1,200.00 1,718.00 1,718.00
S-006 3" flushing assembly (dead end) 1      EACH 1,610.00 1,610.00 2,000.00 2,000.00 1,500.00 1,500.00 1,894.00 1,894.00
S-007 2"x 2"x 2" h.d.p.e. dr11 tee 1      EACH 120.00 120.00 57.00 57.00 300.00 300.00 141.25 141.25
S-008 3"x 2" h.d.p.e. dr11 reducer 1      EACH 120.00 120.00 50.00 50.00 200.00 200.00 141.25 141.25
S-009 1 1/2" lateral connection assembly 8      EACH 565.00 4,520.00 750.00 6,000.00 600.00 4,800.00 664.75 5,318.00
S-010 2" h.d.p.e. dr11 sewer force main connection to
existing city of pineville sewer manhole
1      EACH 3,110.00 3,110.00 2,000.00 2,000.00 1,200.00 1,200.00 3,659.00 3,659.00
S-011 p.e. sewer force main testing lump      LUMP 5,250.00 5,250.00 5,000.00 5,000.00 500.00 500.00 6,177.00 6,177.00
S-012 warning signs 14      each 56.50 791.00 75.00 1,050.00 300.00 4,200.00 66.50 931.00
S-013 furnish and install by bore and jack 6" x 0.25" w.t.
steel casing under r/r (incl insulators,casing
spcrs,endseal,etc.)
275      LNFT 57.65 15,853.75 120.00 33,000.00 90.00 24,750.00 68.00 18,700.00
S-014 simplex residential sewer grinder pumping unit
(simplex pre-packaged pump unit complete)
8      EACH 13,000.00 104,000.00 10,000.00 80,000.00 15,000.00 120,000.00 15,294.00 122,352.00
                       
 CONTRACTOR TOTAL       7,829,259.09   8,290,939.03   8,620,180.78   8,915,428.01