| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC |
- 2 - BOH BROS. CONSTRUCTION CO., LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
301   |
SQYD |
18.00 |
5,418.00 |
25.00 |
7,525.00 |
|
|
|
|
| 202-02-F |
removal of concrete combination curb & gutter
|
530.0 |
LNFT |
22.50 |
11,925.00 |
7.00 |
3,710.00 |
|
|
|
|
| 203-07 |
borrow (vehicular measurement)
|
370   |
CUYD |
60.00 |
22,200.00 |
50.00 |
18,500.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
10   |
EACH |
28.00 |
280.00 |
15.00 |
150.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
200   |
LNFT |
5.50 |
1,100.00 |
3.00 |
600.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
250.0 |
CUYD |
20.00 |
5,000.00 |
20.00 |
5,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
5,076.8 |
TON |
100.00 |
507,680.00 |
100.00 |
507,680.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
418.6 |
TON |
125.00 |
52,325.00 |
100.00 |
41,860.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
15,956   |
SQYD |
6.00 |
95,736.00 |
6.00 |
95,736.00 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
178   |
SQYD |
90.00 |
16,020.00 |
200.00 |
35,600.00 |
|
|
|
|
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
200   |
LNFT |
150.00 |
30,000.00 |
125.00 |
25,000.00 |
|
|
|
|
| 701-14 |
cleaning existing pipes
|
2,875   |
LNFT |
9.00 |
25,875.00 |
8.00 |
23,000.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
1   |
EACH |
9,850.00 |
9,850.00 |
4,400.00 |
4,400.00 |
|
|
|
|
| 702-03-C |
catch basins (cb-06)
|
1   |
EACH |
9,850.00 |
9,850.00 |
4,500.00 |
4,500.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
2   |
EACH |
2,000.00 |
4,000.00 |
1,500.00 |
3,000.00 |
|
|
|
|
| 702-04-B |
adjusting catch basins
|
17   |
EACH |
2,600.00 |
44,200.00 |
3,000.00 |
51,000.00 |
|
|
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
81.3 |
LNFT |
100.00 |
8,130.00 |
115.00 |
9,349.50 |
|
|
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
25.0 |
LNFT |
65.00 |
1,625.00 |
72.00 |
1,800.00 |
|
|
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
8.5 |
LNFT |
100.00 |
850.00 |
114.00 |
969.00 |
|
|
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
1   |
EACH |
3,600.00 |
3,600.00 |
4,000.00 |
4,000.00 |
|
|
|
|
| 706-01-A |
concrete walk (4" thick)
|
76.4 |
SQYD |
108.00 |
8,251.20 |
90.00 |
6,876.00 |
|
|
|
|
| 706-02-E |
concrete drive (8" thick)
|
301.4 |
SQYD |
81.00 |
24,413.40 |
100.00 |
30,140.00 |
|
|
|
|
| 707-01-A |
concrete curb (pinned)
|
4,377.9 |
LNFT |
31.00 |
135,714.90 |
12.00 |
52,534.80 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
522.2 |
LNFT |
59.50 |
31,070.90 |
45.00 |
23,499.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
154,000.00 |
154,000.00 |
315,000.00 |
315,000.00 |
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
300   |
LNFT |
1.10 |
330.00 |
1.00 |
300.00 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line) (4" width)
(10' length) |
2.409 |
MILE |
300.00 |
722.70 |
300.00 |
722.70 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line) (4" width)
|
2.816 |
MILE |
400.00 |
1,126.40 |
400.00 |
1,126.40 |
|
|
|
|
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
12   |
EACH |
83.00 |
996.00 |
75.00 |
900.00 |
|
|
|
|
| 713-05-C |
temporary pavement legends and symbols (only)
|
12   |
EACH |
83.00 |
996.00 |
75.00 |
900.00 |
|
|
|
|
| 717-01 |
seeding
|
20   |
LB |
33.00 |
660.00 |
50.00 |
1,000.00 |
|
|
|
|
| 718-01 |
fertilizer
|
120   |
LB |
5.00 |
600.00 |
5.00 |
600.00 |
|
|
|
|
| 726-01 |
bedding material
|
40.0 |
CUYD |
55.00 |
2,200.00 |
40.00 |
1,600.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
154,000.00 |
154,000.00 |
165,000.00 |
165,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
251   |
EACH |
6.00 |
1,506.00 |
6.00 |
1,506.00 |
|
|
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
377   |
LNFT |
2.75 |
1,036.75 |
3.00 |
1,131.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
150   |
LNFT |
5.00 |
750.00 |
5.00 |
750.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
1.369 |
MILE |
2,700.00 |
3,696.30 |
2,700.00 |
3,696.30 |
|
|
|
|
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
0.199 |
MILE |
6,400.00 |
1,273.60 |
6,500.00 |
1,293.50 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.056 |
MILE |
900.00 |
950.40 |
950.00 |
1,003.20 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
6   |
EACH |
235.00 |
1,410.00 |
250.00 |
1,500.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
6   |
EACH |
235.00 |
1,410.00 |
250.00 |
1,500.00 |
|
|
|
|
| 736-09 |
loop detector
|
200   |
LNFT |
13.00 |
2,600.00 |
30.00 |
6,000.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
24,000.00 |
24,000.00 |
45,000.00 |
45,000.00 |
|
|
|
|
| 741-06 |
relocating fire hydrant
|
1   |
EACH |
7,000.00 |
7,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| S-001 |
roadway reinforcement mesh (complete road system)
|
15,956   |
SQYD |
7.10 |
113,287.60 |
8.00 |
127,648.00 |
|
|
|
|
| S-002 |
saw cutting asphaltic concrete pavement
|
785   |
INFT |
0.75 |
588.75 |
1.00 |
785.00 |
|
|
|
|
| S-003 |
cleaning and resealing random cracks in asphaltic
concrete pavement |
999   |
LNFT |
10.00 |
9,990.00 |
20.00 |
19,980.00 |
|
|
|
|
| S-004 |
saw cutting portland cement concrete pavement (full
depth) |
370   |
LNFT |
1.50 |
555.00 |
10.00 |
3,700.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,540,799.90 |
|
1,664,071.40 |
|
|
|
|
|