| DBE GOAL FED |
| Lead Project: 713-17-0040 |
| Parish: E BATON ROUGE |
| Routes: |
| Description: CHANEY ROAD BRIDGE OVER LATERAL OF LITTLE SANDY CREEK |
Type Const:
grading, class ii base course, superpave asphaltic concrete pavement, reinforced
concrete box culverts and related work. |
| Estimated Construction Cost: $274,521.75 |
|
| |
| Rank | License | Bidder | Construction Bid |
| 1 | 49239 |
W L BASS CONSTRUCTION INC. | $189,353.00 |
| 2 | 43238 |
ON GRADE CONSTRUCTION | $194,980.00 |
| 3 | 02109 |
CHAMBERS CONSTRUCTION CO., INC. | $212,121.44 |
| 4 | 12198 |
BYRON E. TALBOT CONTRACTOR, INC. | $228,689.00 |
| 5 | 42466 |
BEARD CONSTRUCTION GROUP LLC | $230,942.37 |
| 6 | 25088 |
RCS CONTRACTORS, INC. | $240,569.22 |
| 7 | 50336 |
KWC SERVICES LLC | $248,168.74 |
| 8 | 39580 |
GERACE CONSTRUCTION LLC | $280,826.50 |
| 9 | 43371 |
RMD HOLDINGS LTD | $316,439.00 |
|
| |
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - W L BASS CONSTRUCTION INC. |
- 2 - ON GRADE CONSTRUCTION |
- 3 - CHAMBERS CONSTRUCTION CO., INC. |
- 4 - BYRON E. TALBOT CONTRACTOR, INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
10,000.00 |
10,000.00 |
6,367.50 |
6,367.50 |
1,450.00 |
1,450.00 |
1.00 |
1.00 |
| 202-02-A-01 |
removal of bridge(sta. 15+00 - 31 ft. x 37.9 ft.)
|
1   |
EACH |
18,000.00 |
18,000.00 |
15,000.00 |
15,000.00 |
10,250.00 |
10,250.00 |
22,000.00 |
22,000.00 |
| 202-02-G |
removal of surfacing & stabilized base
|
104.1 |
SQYD |
20.00 |
2,082.00 |
25.00 |
2,602.50 |
23.70 |
2,467.17 |
10.00 |
1,041.00 |
| 203-05 |
excavation and embankment
|
lump |
LUMP |
7,500.00 |
7,500.00 |
5,893.00 |
5,893.00 |
11,895.00 |
11,895.00 |
10,500.00 |
10,500.00 |
| 204-02 |
temporary hay or straw bales
|
2   |
EACH |
20.00 |
40.00 |
20.00 |
40.00 |
103.00 |
206.00 |
25.00 |
50.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
4   |
EACH |
200.00 |
800.00 |
95.00 |
380.00 |
253.50 |
1,014.00 |
200.00 |
800.00 |
| 204-06 |
temporary silt fencing
|
160   |
LNFT |
1.00 |
160.00 |
1.65 |
264.00 |
4.30 |
688.00 |
4.85 |
776.00 |
| 302-01 |
class ii base course
|
52.9 |
CUYD |
125.00 |
6,612.50 |
50.00 |
2,645.00 |
157.00 |
8,305.30 |
114.50 |
6,057.05 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
8   |
CUYD |
125.00 |
1,000.00 |
50.00 |
400.00 |
165.75 |
1,326.00 |
146.00 |
1,168.00 |
| 502-01 |
superpave asphaltic concrete
|
43.5 |
TON |
225.00 |
9,787.50 |
200.00 |
8,700.00 |
291.38 |
12,675.03 |
170.00 |
7,395.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
5,300.00 |
5,300.00 |
6,050.00 |
6,050.00 |
10,235.00 |
10,235.00 |
6,000.00 |
6,000.00 |
| 716-01-A |
mulch (vegetative)
|
0.1 |
TON |
3,000.00 |
300.00 |
2,000.00 |
200.00 |
7,350.00 |
735.00 |
15,000.00 |
1,500.00 |
| 717-01 |
seeding
|
1   |
LB |
100.00 |
100.00 |
50.00 |
50.00 |
122.00 |
122.00 |
10.00 |
10.00 |
| 718-01 |
fertilizer
|
20   |
LB |
5.00 |
100.00 |
1.75 |
35.00 |
10.75 |
215.00 |
1.00 |
20.00 |
| 726-01 |
bedding material
|
79.7 |
CUYD |
100.00 |
7,970.00 |
50.00 |
3,985.00 |
77.16 |
6,149.65 |
98.50 |
7,850.45 |
| 727-01 |
mobilization
|
lump |
LUMP |
6,000.00 |
6,000.00 |
20,000.00 |
20,000.00 |
13,065.00 |
13,065.00 |
19,000.00 |
19,000.00 |
| 729-16-B |
object marker assembly (type 2)
|
4   |
EACH |
125.00 |
500.00 |
75.00 |
300.00 |
138.50 |
554.00 |
105.00 |
420.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
4,000.00 |
4,000.00 |
6,500.00 |
6,500.00 |
2,515.00 |
2,515.00 |
5,000.00 |
5,000.00 |
| 805-01-B |
class a concrete (box culvert headwalls)
|
26.43 |
CUYD |
1,225.00 |
32,376.75 |
1,000.00 |
26,430.00 |
1,325.00 |
35,019.75 |
1,300.00 |
34,359.00 |
| 805-12-M |
reinforced concrete box culverts (6'x 6')
|
200.0 |
LNFT |
350.00 |
70,000.00 |
425.00 |
85,000.00 |
449.00 |
89,800.00 |
487.50 |
97,500.00 |
| 806-01 |
deformed reinforcing steel
|
2,069   |
LB |
3.25 |
6,724.25 |
2.00 |
4,138.00 |
1.66 |
3,434.54 |
3.50 |
7,241.50 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
189,353.00 |
|
194,980.00 |
|
212,121.44 |
|
228,689.00 |
|
| |
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - BEARD CONSTRUCTION GROUP LLC |
- 6 - RCS CONTRACTORS, INC. |
- 7 - KWC SERVICES LLC |
- 8 - GERACE CONSTRUCTION LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
878.00 |
878.00 |
1,000.00 |
1,000.00 |
10,000.00 |
10,000.00 |
2,000.00 |
2,000.00 |
| 202-02-A-01 |
removal of bridge(sta. 15+00 - 31 ft. x 37.9 ft.)
|
1   |
EACH |
15,600.00 |
15,600.00 |
17,500.00 |
17,500.00 |
11,900.00 |
11,900.00 |
25,000.00 |
25,000.00 |
| 202-02-G |
removal of surfacing & stabilized base
|
104.1 |
SQYD |
42.00 |
4,372.20 |
5.50 |
572.55 |
11.30 |
1,176.33 |
50.00 |
5,205.00 |
| 203-05 |
excavation and embankment
|
lump |
LUMP |
18,755.00 |
18,755.00 |
10,000.00 |
10,000.00 |
12,600.00 |
12,600.00 |
12,000.00 |
12,000.00 |
| 204-02 |
temporary hay or straw bales
|
2   |
EACH |
25.00 |
50.00 |
50.00 |
100.00 |
20.00 |
40.00 |
200.00 |
400.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
4   |
EACH |
30.00 |
120.00 |
250.00 |
1,000.00 |
125.00 |
500.00 |
250.00 |
1,000.00 |
| 204-06 |
temporary silt fencing
|
160   |
LNFT |
3.25 |
520.00 |
3.30 |
528.00 |
3.00 |
480.00 |
3.00 |
480.00 |
| 302-01 |
class ii base course
|
52.9 |
CUYD |
85.00 |
4,496.50 |
198.00 |
10,474.20 |
183.25 |
9,693.93 |
145.00 |
7,670.50 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
8   |
CUYD |
115.00 |
920.00 |
198.00 |
1,584.00 |
183.25 |
1,466.00 |
100.00 |
800.00 |
| 502-01 |
superpave asphaltic concrete
|
43.5 |
TON |
246.00 |
10,701.00 |
250.00 |
10,875.00 |
300.00 |
13,050.00 |
300.00 |
13,050.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
6,500.00 |
6,500.00 |
8,040.00 |
8,040.00 |
7,850.00 |
7,850.00 |
12,000.00 |
12,000.00 |
| 716-01-A |
mulch (vegetative)
|
0.1 |
TON |
2,200.00 |
220.00 |
5,500.00 |
550.00 |
1,000.00 |
100.00 |
6,000.00 |
600.00 |
| 717-01 |
seeding
|
1   |
LB |
54.00 |
54.00 |
110.00 |
110.00 |
50.00 |
50.00 |
400.00 |
400.00 |
| 718-01 |
fertilizer
|
20   |
LB |
5.40 |
108.00 |
6.00 |
120.00 |
5.00 |
100.00 |
20.00 |
400.00 |
| 726-01 |
bedding material
|
79.7 |
CUYD |
75.00 |
5,977.50 |
65.00 |
5,180.50 |
183.25 |
14,605.03 |
110.00 |
8,767.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
26,480.00 |
26,480.00 |
14,500.00 |
14,500.00 |
31,000.00 |
31,000.00 |
25,000.00 |
25,000.00 |
| 729-16-B |
object marker assembly (type 2)
|
4   |
EACH |
75.00 |
300.00 |
100.00 |
400.00 |
100.00 |
400.00 |
300.00 |
1,200.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
1,500.00 |
1,500.00 |
5,000.00 |
5,000.00 |
2,500.00 |
2,500.00 |
9,000.00 |
9,000.00 |
| 805-01-B |
class a concrete (box culvert headwalls)
|
26.43 |
CUYD |
1,625.00 |
42,948.75 |
2,129.00 |
56,269.47 |
1,370.00 |
36,209.10 |
1,200.00 |
31,716.00 |
| 805-12-M |
reinforced concrete box culverts (6'x 6')
|
200.0 |
LNFT |
440.00 |
88,000.00 |
468.31 |
93,662.00 |
450.00 |
90,000.00 |
600.00 |
120,000.00 |
| 806-01 |
deformed reinforcing steel
|
2,069   |
LB |
1.18 |
2,441.42 |
1.50 |
3,103.50 |
2.15 |
4,448.35 |
2.00 |
4,138.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
230,942.37 |
|
240,569.22 |
|
248,168.74 |
|
280,826.50 |
|
| |
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 9 - RMD HOLDINGS LTD |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 202-02-A-01 |
removal of bridge(sta. 15+00 - 31 ft. x 37.9 ft.)
|
1   |
EACH |
20,000.00 |
20,000.00 |
|
|
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
104.1 |
SQYD |
25.00 |
2,602.50 |
|
|
|
|
|
|
| 203-05 |
excavation and embankment
|
lump |
LUMP |
50,000.00 |
50,000.00 |
|
|
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
2   |
EACH |
5.00 |
10.00 |
|
|
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
4   |
EACH |
5.00 |
20.00 |
|
|
|
|
|
|
| 204-06 |
temporary silt fencing
|
160   |
LNFT |
5.00 |
800.00 |
|
|
|
|
|
|
| 302-01 |
class ii base course
|
52.9 |
CUYD |
175.00 |
9,257.50 |
|
|
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
8   |
CUYD |
130.00 |
1,040.00 |
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
43.5 |
TON |
246.00 |
10,701.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
5,500.00 |
5,500.00 |
|
|
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
0.1 |
TON |
200.00 |
20.00 |
|
|
|
|
|
|
| 717-01 |
seeding
|
1   |
LB |
100.00 |
100.00 |
|
|
|
|
|
|
| 718-01 |
fertilizer
|
20   |
LB |
40.00 |
800.00 |
|
|
|
|
|
|
| 726-01 |
bedding material
|
79.7 |
CUYD |
50.00 |
3,985.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
35,000.00 |
35,000.00 |
|
|
|
|
|
|
| 729-16-B |
object marker assembly (type 2)
|
4   |
EACH |
100.00 |
400.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
26.43 |
CUYD |
600.00 |
15,858.00 |
|
|
|
|
|
|
| 805-12-M |
reinforced concrete box culverts (6'x 6')
|
200.0 |
LNFT |
650.00 |
130,000.00 |
|
|
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
2,069   |
LB |
5.00 |
10,345.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
316,439.00 |
|
|
|
|
|
|
|