| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - JAMES CONSTRUCTION GROUP LLC |
- 2 - COASTAL BRIDGE CO., L.L.C. |
- 3 - BOH BROS. CONSTRUCTION CO., LLC. |
- 4 - AUSTIN BRIDGE & ROAD, LP |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
350,000.00 |
350,000.00 |
100,000.00 |
100,000.00 |
200,000.00 |
200,000.00 |
2,000,000.00 |
2,000,000.00 |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
80,000.00 |
80,000.00 |
10,000.00 |
10,000.00 |
10,000.00 |
10,000.00 |
100,000.00 |
100,000.00 |
| 202-02-A |
removal of bridges
|
1   |
EACH |
65,000.00 |
65,000.00 |
240,000.00 |
240,000.00 |
70,000.00 |
70,000.00 |
50,000.00 |
50,000.00 |
| 202-02-D |
removal of concrete walks & drives
|
732   |
SQYD |
15.00 |
10,980.00 |
11.50 |
8,418.00 |
11.00 |
8,052.00 |
160.00 |
117,120.00 |
| 202-02-F |
removal of concrete combination curb & gutter
|
2,385.4 |
LNFT |
12.00 |
28,624.80 |
9.50 |
22,661.30 |
8.00 |
19,083.20 |
22.00 |
52,478.80 |
| 202-02-I |
removal of fender system at pontoon bridge
|
1   |
EACH |
50,000.00 |
50,000.00 |
125,000.00 |
125,000.00 |
30,000.00 |
30,000.00 |
45,000.00 |
45,000.00 |
| 202-02-J |
removal of operating house at pontoon bridge
|
1   |
EACH |
30,000.00 |
30,000.00 |
17,000.00 |
17,000.00 |
28,000.00 |
28,000.00 |
15,000.00 |
15,000.00 |
| 202-02-K |
removal of existing roadway structure
|
17,433   |
SQYD |
10.00 |
174,330.00 |
13.00 |
226,629.00 |
11.50 |
200,479.50 |
15.00 |
261,495.00 |
| 202-02-L |
removal of signal equipment & related items
|
lump |
LUMP |
9,000.00 |
9,000.00 |
3,550.00 |
3,550.00 |
5,000.00 |
5,000.00 |
3,100.00 |
3,100.00 |
| 203-01 |
general excavation
|
8,627   |
CUYD |
20.00 |
172,540.00 |
11.50 |
99,210.50 |
11.00 |
94,897.00 |
20.00 |
172,540.00 |
| 203-03 |
embankment
|
2,917   |
CUYD |
40.00 |
116,680.00 |
31.00 |
90,427.00 |
30.00 |
87,510.00 |
20.00 |
58,340.00 |
| 204-02 |
temporary hay or straw bales
|
345   |
EACH |
15.00 |
5,175.00 |
10.00 |
3,450.00 |
12.00 |
4,140.00 |
8.50 |
2,932.50 |
| 204-05-A |
temporary sediment check dams (hay)
|
24   |
EACH |
125.00 |
3,000.00 |
100.00 |
2,400.00 |
140.00 |
3,360.00 |
85.00 |
2,040.00 |
| 204-06 |
temporary silt fencing
|
3,600   |
LNFT |
3.00 |
10,800.00 |
4.00 |
14,400.00 |
5.00 |
18,000.00 |
10.00 |
36,000.00 |
| 301-02-E-01 |
class i base course (10" thick) (crushed stone or
recycled pccp) |
17,067.5 |
SQYD |
55.00 |
938,712.50 |
57.00 |
972,847.50 |
50.00 |
853,375.00 |
40.00 |
682,700.00 |
| 301-04-E-01 |
class i base course for shoulders (10" thick) (crushed
stone or recycled pccp) |
4,986.3 |
SQYD |
55.00 |
274,246.50 |
57.00 |
284,219.10 |
50.00 |
249,315.00 |
50.00 |
249,315.00 |
| 305-01-A-01 |
subgrade layer (6" thick) (crushed stone or recycled
pccp) |
22,053   |
SQYD |
35.00 |
771,855.00 |
35.00 |
771,855.00 |
35.00 |
771,855.00 |
29.00 |
639,537.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
100   |
CUYD |
125.00 |
12,500.00 |
200.00 |
20,000.00 |
130.00 |
13,000.00 |
100.00 |
10,000.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
1,000.0 |
CUYD |
75.00 |
75,000.00 |
80.00 |
80,000.00 |
75.00 |
75,000.00 |
140.00 |
140,000.00 |
| 502-01 |
superpave asphaltic concrete
|
8,098.3 |
TON |
145.00 |
1,174,253.50 |
150.00 |
1,214,745.00 |
110.00 |
890,813.00 |
146.00 |
1,182,351.80 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
388.4 |
TON |
200.00 |
77,680.00 |
200.00 |
77,680.00 |
110.00 |
42,724.00 |
202.00 |
78,456.80 |
| 509-01 |
cold planing asphaltic pavement
|
3,976   |
SQYD |
3.00 |
11,928.00 |
10.00 |
39,760.00 |
5.00 |
19,880.00 |
7.00 |
27,832.00 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 200   |
CUYD |
1.00 |
- 200.00 |
1.00 |
- 200.00 |
20.00 |
- 4,000.00 |
1.00 |
- 200.00 |
| 510-01-B |
pavement patching (12" minimum thickness)
|
321   |
SQYD |
200.00 |
64,200.00 |
200.00 |
64,200.00 |
112.00 |
35,952.00 |
150.00 |
48,150.00 |
| 701-03-F |
storm drain pipe (15" rcp/rpvccp)
|
2,104   |
LNFT |
120.00 |
252,480.00 |
142.00 |
298,768.00 |
130.00 |
273,520.00 |
75.00 |
157,800.00 |
| 701-03-G |
storm drain pipe (18" rcp/rpvccp)
|
1,526   |
LNFT |
125.00 |
190,750.00 |
148.00 |
225,848.00 |
140.00 |
213,640.00 |
85.00 |
129,710.00 |
| 701-03-I |
storm drain pipe (24" rcp/rpvccp)
|
760   |
LNFT |
120.00 |
91,200.00 |
140.00 |
106,400.00 |
130.00 |
98,800.00 |
98.00 |
74,480.00 |
| 701-03-I-01 |
storm drain pipe (24" cap/pccap) (outfall)
|
52   |
LNFT |
90.00 |
4,680.00 |
110.00 |
5,720.00 |
100.00 |
5,200.00 |
130.00 |
6,760.00 |
| 701-03-K |
storm drain pipe (30" rcp/rpvccp)
|
380   |
LNFT |
110.00 |
41,800.00 |
131.00 |
49,780.00 |
125.00 |
47,500.00 |
130.00 |
49,400.00 |
| 701-03-K-01 |
storm drain pipe (30" cap/pccap) (outfall)
|
40   |
LNFT |
110.00 |
4,400.00 |
125.00 |
5,000.00 |
120.00 |
4,800.00 |
140.00 |
5,600.00 |
| 701-03-M-01 |
storm drain pipe (36" cap/pccap) (outfall)
|
64   |
LNFT |
115.00 |
7,360.00 |
135.00 |
8,640.00 |
120.00 |
7,680.00 |
180.00 |
11,520.00 |
| 701-05-G |
side drain pipe (18")
|
48   |
LNFT |
75.00 |
3,600.00 |
90.00 |
4,320.00 |
75.00 |
3,600.00 |
40.00 |
1,920.00 |
| 701-09-A |
fabricating pipe fittings (15" x 15" x 15" t-branch)
|
5   |
EACH |
1,200.00 |
6,000.00 |
1,500.00 |
7,500.00 |
1,200.00 |
6,000.00 |
1,600.00 |
8,000.00 |
| 701-09-B |
fabricating pipe fittings (18" x 18" x 15" t-branch)
|
3   |
EACH |
1,300.00 |
3,900.00 |
1,600.00 |
4,800.00 |
1,300.00 |
3,900.00 |
1,800.00 |
5,400.00 |
| 702-02-B |
manholes (r-cb-11)
|
3   |
EACH |
3,000.00 |
9,000.00 |
3,500.00 |
10,500.00 |
3,000.00 |
9,000.00 |
3,900.00 |
11,700.00 |
| 702-03-A |
catch basins (cb-01)
|
48   |
EACH |
2,500.00 |
120,000.00 |
3,000.00 |
144,000.00 |
2,600.00 |
124,800.00 |
2,200.00 |
105,600.00 |
| 702-03-G |
catch basins (cb-09)
|
1   |
EACH |
4,500.00 |
4,500.00 |
5,000.00 |
5,000.00 |
5,000.00 |
5,000.00 |
7,500.00 |
7,500.00 |
| 704-03 |
blocked out guard rail
|
456.0 |
LNFT |
20.00 |
9,120.00 |
24.00 |
10,944.00 |
26.00 |
11,856.00 |
20.00 |
9,120.00 |
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
60.00 |
6,000.00 |
65.00 |
6,500.00 |
80.00 |
8,000.00 |
60.00 |
6,000.00 |
| 704-11-B |
guard rail end treatment (tangent)
|
4   |
EACH |
2,400.00 |
9,600.00 |
3,000.00 |
12,000.00 |
3,600.00 |
14,400.00 |
2,400.00 |
9,600.00 |
| 706-01-A |
concrete walk (4" thick)
|
30.4 |
SQYD |
70.00 |
2,128.00 |
75.00 |
2,280.00 |
75.00 |
2,280.00 |
40.00 |
1,216.00 |
| 706-02-C |
concrete drive (6" thick)
|
1,600.8 |
SQYD |
80.00 |
128,064.00 |
60.00 |
96,048.00 |
75.00 |
120,060.00 |
58.00 |
92,846.40 |
| 706-03-C |
incidental concrete paving (6" thick)
|
564.0 |
SQYD |
75.00 |
42,300.00 |
60.00 |
33,840.00 |
75.00 |
42,300.00 |
58.00 |
32,712.00 |
| 707-01 |
concrete curb
|
322.5 |
LNFT |
10.00 |
3,225.00 |
35.00 |
11,287.50 |
15.00 |
4,837.50 |
8.00 |
2,580.00 |
| 707-03 |
combination concrete curb & gutter
|
1,373.4 |
LNFT |
45.00 |
61,803.00 |
50.00 |
68,670.00 |
40.00 |
54,936.00 |
19.50 |
26,781.30 |
| 707-03-A |
combination concrete curb & gutter (width varies)
|
118.1 |
LNFT |
45.00 |
5,314.50 |
100.00 |
11,810.00 |
50.00 |
5,905.00 |
25.00 |
2,952.50 |
| 708-01 |
right-of-way monument
|
46   |
EACH |
300.00 |
13,800.00 |
500.00 |
23,000.00 |
600.00 |
27,600.00 |
120.00 |
5,520.00 |
| 711-01-C |
riprap (30 lb., 18" thick)
|
28   |
SQYD |
75.00 |
2,100.00 |
200.00 |
5,600.00 |
70.00 |
1,960.00 |
260.00 |
7,280.00 |
| 711-04 |
geotextile fabric
|
28   |
SQYD |
5.00 |
140.00 |
5.00 |
140.00 |
5.00 |
140.00 |
100.00 |
2,800.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
80,000.00 |
80,000.00 |
150,000.00 |
150,000.00 |
200,000.00 |
200,000.00 |
35,000.00 |
35,000.00 |
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
0.057 |
MILE |
525.00 |
29.93 |
600.00 |
34.20 |
500.00 |
28.50 |
526.32 |
30.00 |
| 713-03-B-01 |
temporary pvmt. markings (broken line)(4" w)(10' l)
(type i removable) |
0.057 |
MILE |
15,800.00 |
900.60 |
4,500.00 |
256.50 |
15,000.00 |
855.00 |
15,789.47 |
900.00 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
4.621 |
MILE |
750.00 |
3,465.75 |
800.00 |
3,696.80 |
800.00 |
3,696.80 |
749.84 |
3,465.01 |
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
39   |
EACH |
75.00 |
2,925.00 |
60.00 |
2,340.00 |
80.00 |
3,120.00 |
75.00 |
2,925.00 |
| 713-05-B |
temporary pavement legends and symbols (double arrow)
|
10   |
EACH |
100.00 |
1,000.00 |
80.00 |
800.00 |
100.00 |
1,000.00 |
100.00 |
1,000.00 |
| 713-05-C |
temporary pavement legends and symbols (only)
|
4   |
EACH |
100.00 |
400.00 |
80.00 |
320.00 |
100.00 |
400.00 |
100.00 |
400.00 |
| 713-06 |
temporary reflectorized raised pavement markers
|
110   |
EACH |
5.00 |
550.00 |
6.00 |
660.00 |
5.00 |
550.00 |
5.00 |
550.00 |
| 713-07-01 |
temporary precast concrete barrier (contractor
furnished0 (type f) |
44   |
EACH |
1,500.00 |
66,000.00 |
1,200.00 |
52,800.00 |
1,200.00 |
52,800.00 |
1,504.34 |
66,190.96 |
| 717-01 |
seeding
|
105   |
LB |
12.00 |
1,260.00 |
15.00 |
1,575.00 |
25.00 |
2,625.00 |
1.14 |
119.70 |
| 718-01 |
fertilizer
|
3,500   |
LB |
0.50 |
1,750.00 |
1.50 |
5,250.00 |
1.00 |
3,500.00 |
0.30 |
1,050.00 |
| 722-01 |
project site laboratory
|
1   |
EACH |
15,000.00 |
15,000.00 |
36,000.00 |
36,000.00 |
10,000.00 |
10,000.00 |
23,587.20 |
23,587.20 |
| 726-01 |
bedding material
|
1,704.0 |
CUYD |
1.00 |
1,704.00 |
1.00 |
1,704.00 |
20.00 |
34,080.00 |
50.00 |
85,200.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
3,000,000.00 |
3,000,000.00 |
3,000,000.00 |
3,000,000.00 |
3,250,000.00 |
3,250,000.00 |
3,500,000.00 |
3,500,000.00 |
| 729-01 |
sign (type a)
|
400.0 |
SQFT |
25.00 |
10,000.00 |
35.00 |
14,000.00 |
25.00 |
10,000.00 |
25.00 |
10,000.00 |
| 729-01-A |
sign (type a) (r10-10) (24"x30")
|
20.0 |
SQFT |
40.00 |
800.00 |
50.00 |
1,000.00 |
40.00 |
800.00 |
40.00 |
800.00 |
| 729-01-B |
sign (type a) (r10-12) (24"x30")
|
20.0 |
SQFT |
40.00 |
800.00 |
50.00 |
1,000.00 |
40.00 |
800.00 |
40.00 |
800.00 |
| 729-01-C |
sign (type a) (r1-2) (36"x36"x36")
|
7.8 |
SQFT |
40.00 |
312.00 |
50.00 |
390.00 |
40.00 |
312.00 |
40.00 |
312.00 |
| 729-02 |
sign (type b)
|
175.0 |
SQFT |
30.00 |
5,250.00 |
40.00 |
7,000.00 |
30.00 |
5,250.00 |
30.00 |
5,250.00 |
| 729-14 |
delineator assembly (ground mounted)
|
16   |
EACH |
75.00 |
1,200.00 |
60.00 |
960.00 |
80.00 |
1,280.00 |
75.00 |
1,200.00 |
| 729-16-C |
object marker assembly (type 3)
|
10   |
EACH |
80.00 |
800.00 |
150.00 |
1,500.00 |
85.00 |
850.00 |
80.00 |
800.00 |
| 729-19-A |
dead end road installations(type a)
|
2   |
EACH |
1,400.00 |
2,800.00 |
2,500.00 |
5,000.00 |
1,500.00 |
3,000.00 |
1,400.00 |
2,800.00 |
| 729-21 |
u-channel post
|
2   |
EACH |
60.00 |
120.00 |
100.00 |
200.00 |
100.00 |
200.00 |
65.00 |
130.00 |
| 730-09 |
electrical system
|
lump |
LUMP |
1,900,000.00 |
1,900,000.00 |
2,000,000.00 |
2,000,000.00 |
1,840,000.00 |
1,840,000.00 |
1,995,000.00 |
1,995,000.00 |
| 731-02 |
reflectorized raised pavement markers
|
2,364   |
EACH |
5.00 |
11,820.00 |
6.00 |
14,184.00 |
6.00 |
14,184.00 |
5.00 |
11,820.00 |
| 732-01-C |
plastic pavement striping (8" width)
|
961   |
LNFT |
1.00 |
961.00 |
1.10 |
1,057.10 |
1.00 |
961.00 |
1.00 |
961.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
1,634   |
LNFT |
3.00 |
4,902.00 |
4.00 |
6,536.00 |
3.00 |
4,902.00 |
3.00 |
4,902.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
4.058 |
MILE |
2,700.00 |
10,956.60 |
3,000.00 |
12,174.00 |
2,800.00 |
11,362.40 |
2,701.33 |
10,962.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.279 |
MILE |
800.00 |
223.20 |
800.00 |
223.20 |
800.00 |
223.20 |
802.87 |
224.00 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
20   |
EACH |
200.00 |
4,000.00 |
250.00 |
5,000.00 |
200.00 |
4,000.00 |
200.00 |
4,000.00 |
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
8   |
EACH |
250.00 |
2,000.00 |
250.00 |
2,000.00 |
250.00 |
2,000.00 |
250.00 |
2,000.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
26   |
EACH |
250.00 |
6,500.00 |
250.00 |
6,500.00 |
250.00 |
6,500.00 |
250.00 |
6,500.00 |
| 732-04-F |
plastic pavement legends & symbols (merge)
|
2   |
EACH |
250.00 |
500.00 |
400.00 |
800.00 |
250.00 |
500.00 |
250.00 |
500.00 |
| 732-05 |
removal of existing markings
|
1.231 |
MILE |
4,000.00 |
4,924.00 |
10,000.00 |
12,310.00 |
5,000.00 |
6,155.00 |
3,996.75 |
4,920.00 |
| 736-01 |
trenching and backfilling
|
1,000   |
LNFT |
7.00 |
7,000.00 |
7.00 |
7,000.00 |
10.00 |
10,000.00 |
5.00 |
5,000.00 |
| 736-03-A |
jacked or bored conduit (1" pec conduit)
|
50   |
LNFT |
20.00 |
1,000.00 |
25.00 |
1,250.00 |
25.00 |
1,250.00 |
20.00 |
1,000.00 |
| 736-03-B |
jacked or bored conduit (2" pec conduit)
|
1,250   |
LNFT |
30.00 |
37,500.00 |
30.00 |
37,500.00 |
30.00 |
37,500.00 |
29.00 |
36,250.00 |
| 736-03-C |
jacked or bored conduit (3" pec conduit)
|
732   |
LNFT |
32.00 |
23,424.00 |
35.00 |
25,620.00 |
20.00 |
14,640.00 |
32.00 |
23,424.00 |
| 736-04-A |
signal support (single, 40 ft. mast arm)
|
1   |
EACH |
12,000.00 |
12,000.00 |
14,000.00 |
14,000.00 |
15,000.00 |
15,000.00 |
11,661.00 |
11,661.00 |
| 736-04-B |
signal support (single, 45 ft. mast arm)
|
1   |
EACH |
12,500.00 |
12,500.00 |
14,000.00 |
14,000.00 |
15,000.00 |
15,000.00 |
12,051.00 |
12,051.00 |
| 736-04-C |
signal support (single, 50 ft. mast arm)
|
6   |
EACH |
13,750.00 |
82,500.00 |
15,000.00 |
90,000.00 |
17,000.00 |
102,000.00 |
13,416.00 |
80,496.00 |
| 736-05-B |
signal heads (3-section, led, r,y,g)
|
14   |
EACH |
975.00 |
13,650.00 |
1,100.00 |
15,400.00 |
1,100.00 |
15,400.00 |
961.00 |
13,454.00 |
| 736-05-C |
signal heads (3-section, led, r,lty,ltg)
|
4   |
EACH |
840.00 |
3,360.00 |
1,000.00 |
4,000.00 |
1,000.00 |
4,000.00 |
823.00 |
3,292.00 |
| 736-05-D |
signal heads (5-section, led, r,lty,ltg,y,g)
|
4   |
EACH |
1,375.00 |
5,500.00 |
1,500.00 |
6,000.00 |
1,500.00 |
6,000.00 |
1,350.00 |
5,400.00 |
| 736-05-E |
signal heads (5-section, led, r,y,g,rty,rtg)
|
2   |
EACH |
1,375.00 |
2,750.00 |
1,500.00 |
3,000.00 |
1,500.00 |
3,000.00 |
1,350.00 |
2,700.00 |
| 736-06-A |
signal service (pedestal mount)
|
1   |
EACH |
1,500.00 |
1,500.00 |
1,750.00 |
1,750.00 |
2,500.00 |
2,500.00 |
1,460.00 |
1,460.00 |
| 736-06-B |
signal service (pole mount)
|
2   |
EACH |
1,100.00 |
2,200.00 |
1,400.00 |
2,800.00 |
2,400.00 |
4,800.00 |
1,100.00 |
2,200.00 |
| 736-08 |
signal controller (nema ts-2, type 2, in ts-1, type
6 controller cabinet w/ fiber and video equipment) |
2   |
EACH |
25,000.00 |
50,000.00 |
28,000.00 |
56,000.00 |
35,000.00 |
70,000.00 |
25,506.00 |
51,012.00 |
| 736-09 |
loop detector
|
280   |
LNFT |
10.00 |
2,800.00 |
15.00 |
4,200.00 |
20.00 |
5,600.00 |
10.00 |
2,800.00 |
| 736-10-A |
underground junction box (type e)
|
5   |
EACH |
400.00 |
2,000.00 |
500.00 |
2,500.00 |
700.00 |
3,500.00 |
403.00 |
2,015.00 |
| 736-10-B |
underground junction box (type f)
|
8   |
EACH |
475.00 |
3,800.00 |
600.00 |
4,800.00 |
900.00 |
7,200.00 |
465.00 |
3,720.00 |
| 736-10-C |
underground junction box (type h)
|
2   |
EACH |
1,000.00 |
2,000.00 |
1,100.00 |
2,200.00 |
1,400.00 |
2,800.00 |
945.00 |
1,890.00 |
| 736-11-A |
conduit (1/2" pec)
|
30   |
LNFT |
4.00 |
120.00 |
5.00 |
150.00 |
5.00 |
150.00 |
4.00 |
120.00 |
| 736-11-B |
conduit (1" pec)
|
575   |
LNFT |
4.00 |
2,300.00 |
5.00 |
2,875.00 |
4.00 |
2,300.00 |
4.00 |
2,300.00 |
| 736-11-C |
conduit (2" pec)
|
205   |
LNFT |
6.00 |
1,230.00 |
7.00 |
1,435.00 |
5.00 |
1,025.00 |
5.50 |
1,127.50 |
| 736-11-D |
conduit (3" pec)
|
110   |
LNFT |
7.00 |
770.00 |
8.00 |
880.00 |
8.00 |
880.00 |
6.60 |
726.00 |
| 736-12-A |
conductor (video detector)
|
1,175   |
LNFT |
2.25 |
2,643.75 |
3.00 |
3,525.00 |
1.00 |
1,175.00 |
2.25 |
2,643.75 |
| 736-12-B |
conductor,2c (loop lead in) (#14 awg, stranded)
|
460   |
LNFT |
2.00 |
920.00 |
2.50 |
1,150.00 |
1.00 |
460.00 |
1.85 |
851.00 |
| 736-12-C |
conductor,2c (bridge preemption) (#14 awg, stranded)
|
850   |
LNFT |
2.00 |
1,700.00 |
2.50 |
2,125.00 |
1.00 |
850.00 |
1.85 |
1,572.50 |
| 736-12-E |
conductor,3c (power)
|
130   |
LNFT |
6.00 |
780.00 |
8.00 |
1,040.00 |
6.00 |
780.00 |
6.00 |
780.00 |
| 736-12-F |
conductor,6c (signal) (#14 awg, stranded)
|
395   |
LNFT |
2.25 |
888.75 |
3.00 |
1,185.00 |
3.00 |
1,185.00 |
2.25 |
888.75 |
| 736-12-G |
conductor,10c (signal) (#14 awg, stranded)
|
2,135   |
LNFT |
3.00 |
6,405.00 |
3.50 |
7,472.50 |
4.00 |
8,540.00 |
3.00 |
6,405.00 |
| 736-12-H |
conductor (fiber optic cable) (6 count, multimode)
|
1,020   |
LNFT |
8.00 |
8,160.00 |
7.00 |
7,140.00 |
9.00 |
9,180.00 |
8.00 |
8,160.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
250,000.00 |
250,000.00 |
225,000.00 |
225,000.00 |
600,000.00 |
600,000.00 |
360,000.00 |
360,000.00 |
| 804-01-A |
precast concrete piles (12")
|
232   |
LNFT |
65.00 |
15,080.00 |
54.00 |
12,528.00 |
48.00 |
11,136.00 |
125.00 |
29,000.00 |
| 804-01-C |
precast concrete piles (16")
|
7,793   |
LNFT |
70.00 |
545,510.00 |
66.00 |
514,338.00 |
70.00 |
545,510.00 |
60.00 |
467,580.00 |
| 804-01-F |
precast concrete piles (24")
|
11,220   |
LNFT |
100.00 |
1,122,000.00 |
105.00 |
1,178,100.00 |
114.00 |
1,279,080.00 |
100.00 |
1,122,000.00 |
| 804-02-B |
treated timber piles (coastal treatment)
|
16,020   |
LNFT |
20.00 |
320,400.00 |
23.50 |
376,470.00 |
22.00 |
352,440.00 |
60.00 |
961,200.00 |
| 804-05-C |
precast concrete test piles (16")
|
1   |
EACH |
75,000.00 |
75,000.00 |
40,000.00 |
40,000.00 |
11,000.00 |
11,000.00 |
40,000.00 |
40,000.00 |
| 804-05-F |
precast concrete test piles (24")
|
1   |
EACH |
75,000.00 |
75,000.00 |
40,000.00 |
40,000.00 |
27,000.00 |
27,000.00 |
45,000.00 |
45,000.00 |
| 804-09 |
loading test piles
|
2   |
EACH |
30,000.00 |
60,000.00 |
10,000.00 |
20,000.00 |
18,500.00 |
37,000.00 |
35,000.00 |
70,000.00 |
| 804-10 |
reloading test piles
|
2   |
EACH |
1,000.00 |
2,000.00 |
1,000.00 |
2,000.00 |
1,000.00 |
2,000.00 |
8,000.00 |
16,000.00 |
| 804-11 |
redriving test piles
|
2   |
EACH |
1,000.00 |
2,000.00 |
1,000.00 |
2,000.00 |
750.00 |
1,500.00 |
6,000.00 |
12,000.00 |
| 804-12 |
loading permanent piles
|
2   |
EACH |
1,000.00 |
2,000.00 |
1,000.00 |
2,000.00 |
10,000.00 |
20,000.00 |
22,000.00 |
44,000.00 |
| 804-17 |
dynamic monitoring
|
6   |
EACH |
2,000.00 |
12,000.00 |
3,000.00 |
18,000.00 |
5,900.00 |
35,400.00 |
2,500.00 |
15,000.00 |
| 805-01-D |
class a concrete (footings)
|
874.84 |
CUYD |
1,000.00 |
874,840.00 |
600.00 |
524,904.00 |
1,500.00 |
1,312,260.00 |
1,800.00 |
1,574,712.00 |
| 805-01-E |
class a concrete (piers)
|
958.80 |
CUYD |
2,000.00 |
1,917,600.00 |
2,600.00 |
2,492,880.00 |
2,300.00 |
2,205,240.00 |
2,200.00 |
2,109,360.00 |
| 805-01-F |
class a concrete (bents)
|
135.40 |
CUYD |
1,500.00 |
203,100.00 |
1,750.00 |
236,950.00 |
2,500.00 |
338,500.00 |
3,600.00 |
487,440.00 |
| 805-01-H |
class a concrete (counterweights)
|
276.00 |
CUYD |
1,500.00 |
414,000.00 |
1,250.00 |
345,000.00 |
2,500.00 |
690,000.00 |
400.00 |
110,400.00 |
| 805-03 |
class aa concrete
|
578.67 |
CUYD |
1,500.00 |
868,005.00 |
900.00 |
520,803.00 |
2,500.00 |
1,446,675.00 |
2,450.00 |
1,417,741.50 |
| 805-04 |
class aa(m) concrete
|
229.08 |
CUYD |
1,500.00 |
343,620.00 |
1,600.00 |
366,528.00 |
2,000.00 |
458,160.00 |
600.00 |
137,448.00 |
| 806-01 |
deformed reinforcing steel
|
750,000   |
LB |
1.10 |
825,000.00 |
0.95 |
712,500.00 |
0.80 |
600,000.00 |
0.90 |
675,000.00 |
| 807-08 |
structural metalwork
|
lump |
LUMP |
4,150,000.00 |
4,150,000.00 |
3,675,000.00 |
3,675,000.00 |
3,900,000.00 |
3,900,000.00 |
4,000,000.00 |
4,000,000.00 |
| 809-01 |
movable bridge machinery
|
lump |
LUMP |
5,150,000.00 |
5,150,000.00 |
6,200,000.00 |
6,200,000.00 |
5,950,000.00 |
5,950,000.00 |
5,100,000.00 |
5,100,000.00 |
| 809-02 |
traffic barriers
|
lump |
LUMP |
515,000.00 |
515,000.00 |
350,000.00 |
350,000.00 |
500,000.00 |
500,000.00 |
550,000.00 |
550,000.00 |
| 809-03 |
operating house
|
lump |
LUMP |
600,000.00 |
600,000.00 |
770,000.00 |
770,000.00 |
425,000.00 |
425,000.00 |
600,000.00 |
600,000.00 |
| 810-01 |
concrete railing (barrier)
|
331.77 |
LNFT |
85.00 |
28,200.45 |
125.00 |
41,471.25 |
90.00 |
29,859.30 |
70.00 |
23,223.90 |
| 810-03 |
pipe railing (operating house not included)
|
999.31 |
LNFT |
220.00 |
219,848.20 |
175.00 |
174,879.25 |
160.00 |
159,889.60 |
175.00 |
174,879.25 |
| 812-01-B |
treated timber (coastal treatment)
|
19.00 |
MFBM |
15,000.00 |
285,000.00 |
11,500.00 |
218,500.00 |
32,500.00 |
617,500.00 |
23,000.00 |
437,000.00 |
| 813-01 |
concrete approach slabs
|
946.40 |
SQYD |
210.00 |
198,744.00 |
250.00 |
236,600.00 |
200.00 |
189,280.00 |
194.97 |
184,519.61 |
| S-001 |
special detail (cb-06) pg-drain01
|
3   |
EACH |
3,500.00 |
10,500.00 |
4,500.00 |
13,500.00 |
6,000.00 |
18,000.00 |
7,500.00 |
22,500.00 |
| S-002 |
adjusting sanitary sewer house connections
|
3   |
EACH |
850.00 |
2,550.00 |
1,000.00 |
3,000.00 |
3,000.00 |
9,000.00 |
7,000.00 |
21,000.00 |
| S-003 |
adjusting sanitary sewer service lines
|
90   |
LNFT |
125.00 |
11,250.00 |
150.00 |
13,500.00 |
300.00 |
27,000.00 |
500.00 |
45,000.00 |
| S-006 |
impact attenuators (construction zone)
|
4   |
EACH |
20,000.00 |
80,000.00 |
15,000.00 |
60,000.00 |
12,500.00 |
50,000.00 |
18,000.00 |
72,000.00 |
| S-007 |
flashing arrow panel
|
2   |
EACH |
30,000.00 |
60,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
20,000.00 |
7,000.00 |
14,000.00 |
| S-008 |
video detector device and connection
|
2   |
EACH |
6,500.00 |
13,000.00 |
8,000.00 |
16,000.00 |
6,500.00 |
13,000.00 |
6,660.00 |
13,320.00 |
| S-009 |
video detection system (intersection)
|
2   |
EACH |
4,500.00 |
9,000.00 |
5,000.00 |
10,000.00 |
4,500.00 |
9,000.00 |
4,195.00 |
8,390.00 |
| S-012 |
saw cutting
|
250   |
LNFT |
35.00 |
8,750.00 |
10.00 |
2,500.00 |
12.00 |
3,000.00 |
30.00 |
7,500.00 |
| S-101 |
dynamic analysis
|
6   |
EACH |
1,500.00 |
9,000.00 |
3,000.00 |
18,000.00 |
1,200.00 |
7,200.00 |
600.00 |
3,600.00 |
| S-102 |
tower stairs, stair platforms & platform supports
|
lump |
LUMP |
200,000.00 |
200,000.00 |
140,000.00 |
140,000.00 |
125,000.00 |
125,000.00 |
165,000.00 |
165,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
30,442,823.03 |
|
30,897,867.70 |
|
32,672,430.00 |
|
33,954,499.73 |
| | NUMBER OF DAYS BID AT $3,000 PER DAY. |
|
|
|
2,925,000.00 |
|
2,925,000.00 |
|
2,925,000.00 |
|
2,925,000.00 |
| | TOTAL BID |
|
|
|
33,367,823.03 |
|
33,822,867.70 |
|
35,597,430.00 |
|
36,879,499.73 |
|