Letting of 3/18/2009 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 001-08-0036
Parish: LINCOLN
Routes: US 167
Description: RUSTON DOWNTOWN DISTRICT REVITALIZATION
Type Const: concrete sidewalks, decorative street lighting, new water main installation and
related work.
Estimated Construction Cost: $1,204,262.60
 
RankLicenseBidderConstruction Bid
1 18546 C W & W CONTRACTORS, INC. $1,359,084.00
2 30774 PROGRESSIVE CONSTRUCTION CO., LLC. $1,422,470.65
3 43371 RMD HOLDINGS LTD $1,474,010.85
4 15099 AMETHYST CONSTRUCTION, INC. $1,490,173.00
 
Item Number Item Description Quantity Unit of Measure - 1 -
C W & W CONTRACTORS, INC.
- 2 -
PROGRESSIVE CONSTRUCTION CO., LLC.
- 3 -
RMD HOLDINGS LTD
- 4 -
AMETHYST CONSTRUCTION, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      LUMP 30,000.00 30,000.00 230,000.00 230,000.00 180,000.00 180,000.00 70,000.00 70,000.00
202-02-D removal of concrete walks & drives 1,760      SQYD 5.00 8,800.00 11.00 19,360.00 15.00 26,400.00 18.00 31,680.00
202-02-E removal of concrete curbs 1,544.0    LNFT 5.00 7,720.00 11.00 16,984.00 6.00 9,264.00 5.00 7,720.00
202-02-G removal of surfacing & stabilized base 1,920.0    SQYD 5.00 9,600.00 6.60 12,672.00 5.25 10,080.00 26.00 49,920.00
202-03 relocation of signs and posts 2      EACH 1,000.00 2,000.00 350.00 700.00 200.00 400.00 300.00 600.00
203-01 general excavation 250      CUYD 15.00 3,750.00 6.00 1,500.00 12.00 3,000.00 16.00 4,000.00
203-07-A borrow (vehicular meas.)(selected soils) 500      CUYD 20.00 10,000.00 20.00 10,000.00 12.00 6,000.00 25.00 12,500.00
302-02-A class ii base course (4" thick) 2,329.0    SQYD 11.00 25,619.00 15.25 35,517.25 24.00 55,896.00 20.00 46,580.00
302-02-C class ii base course (8" thick) 1,360.0    SQYD 22.00 29,920.00 35.70 48,552.00 27.00 36,720.00 32.00 43,520.00
306-02 scarifying and compacting roadbed (9" thick) 1,360      SQYD 3.00 4,080.00 7.50 10,200.00 21.00 28,560.00 11.00 14,960.00
502-03 superpave asphaltic concrete (3 1/2" thick) 1,360      SQYD 40.00 54,400.00 60.50 82,280.00 75.00 102,000.00 84.00 114,240.00
701-03-E-01 storm drain pipe (12" pvcp) 310      LNFT 35.00 10,850.00 55.00 17,050.00 75.00 23,250.00 75.00 23,250.00
702-01 junction boxes 15      EACH 4,500.00 67,500.00 3,850.00 57,750.00 750.00 11,250.00 4,300.00 64,500.00
702-03-G catch basins (cb-09) 10      EACH 5,000.00 50,000.00 3,850.00 38,500.00 2,400.00 24,000.00 4,500.00 45,000.00
706-01-A concrete walk (4" thick) 2,010.0    SQYD 65.00 130,650.00 71.50 143,715.00 48.00 96,480.00 60.00 120,600.00
706-04 handicapped curb ramps 17.0    EACH 1,500.00 25,500.00 1,100.00 18,700.00 600.00 10,200.00 1,600.00 27,200.00
707-03 combination concrete curb & gutter 1,910.0    LNFT 30.00 57,300.00 22.00 42,020.00 25.00 47,750.00 28.00 53,480.00
713-01 temporary signs & barricades lump      LUMP 25,000.00 25,000.00 25,000.00 25,000.00 45,000.00 45,000.00 100,000.00 100,000.00
727-01 mobilization lump      LUMP 110,000.00 110,000.00 70,000.00 70,000.00 250,350.00 250,350.00 50,000.00 50,000.00
729-01 sign (type a) 6.0    SQFT 100.00 600.00 75.00 450.00 25.00 150.00 22.00 132.00
729-08-A mounting (2 1/2" post) 4      EACH 1,000.00 4,000.00 700.00 2,800.00 150.00 600.00 750.00 3,000.00
730-05 light pole (14'-0" mount vernon w/ fluted shaft) 18      EACH 3,500.00 63,000.00 2,475.00 44,550.00 2,250.00 40,500.00 3,400.00 61,200.00
730-07 luminaire (holophane gv175mh00xx8rn)(175 watt clear mh
with lunar optics)
18      EACH 1,500.00 27,000.00 1,600.00 28,800.00 1,455.00 26,190.00 2,100.00 37,800.00
732-04-F plastic pavement legends & symbols (handicap) 4      EACH 2,000.00 8,000.00 1,650.00 6,600.00 1,500.00 6,000.00 1,550.00 6,200.00
732-05 removal of existing markings 0.363  MILE 12,500.00 4,537.50 11,000.00 3,993.00 10,000.00 3,630.00 10,000.00 3,630.00
737-03-A painted traffic striping (solid line)(4" width) 1,650      LNFT 1.25 2,062.50 1.10 1,815.00 1.00 1,650.00 1.75 2,887.50
737-03-D painted traffic striping (solid line)(12" width) 1,350      LNFT 2.00 2,700.00 1.65 2,227.50 1.50 2,025.00 1.75 2,362.50
740-01 construction layout lump      LUMP 25,000.00 25,000.00 5,000.00 5,000.00 42,000.00 42,000.00 9,600.00 9,600.00
S-001 saw cutting asphaltic concrete pavement per 1" depth 2,010      LNFT 2.00 4,020.00 5.00 10,050.00 2.10 4,221.00 5.00 10,050.00
S-002 brick pavers 2,870      SQFT 15.00 43,050.00 17.00 48,790.00 9.60 27,552.00 7.50 21,525.00
S-003 irrigation system lump      LUMP 50,000.00 50,000.00 20,000.00 20,000.00 36,000.00 36,000.00 20,000.00 20,000.00
S-004 handrail 1      EACH 4,500.00 4,500.00 1,700.00 1,700.00 600.00 600.00 1,500.00 1,500.00
S-005-A trash receptacles 12      EACH 1,800.00 21,600.00 950.00 11,400.00 697.00 8,364.00 1,500.00 18,000.00
S-005-B benches 12      EACH 3,500.00 42,000.00 1,300.00 15,600.00 897.00 10,764.00 3,000.00 36,000.00
S-005-C planters 46      EACH 1,600.00 73,600.00 800.00 36,800.00 648.00 29,808.00 1,200.00 55,200.00
S-006 hanging baskets 46      EACH 100.00 4,600.00 150.00 6,900.00 21.00 966.00 620.00 28,520.00
S-007 roof drain downspouts 10      EACH 500.00 5,000.00 1,320.00 13,200.00 100.00 1,000.00 1,800.00 18,000.00
S-008 sidewalk drain cover 2      EACH 500.00 1,000.00 1,320.00 2,640.00 250.00 500.00 750.00 1,500.00
S-009 adjusting metal lid lump      LUMP 2,000.00 2,000.00 1,320.00 1,320.00 100.00 100.00 1,200.00 1,200.00
S-010 adjusting monitoring well 1      EACH 3,000.00 3,000.00 1,100.00 1,100.00 100.00 100.00 800.00 800.00
S-011 relocation of street signs with new posts 10      EACH 1,500.00 15,000.00 450.00 4,500.00 150.00 1,500.00 200.00 2,000.00
S-012-A conduit (1 1/4" sch 40 pvc, no conductors, include
pull tape full length)
1,181      LNFT 11.00 12,991.00 8.90 10,510.90 8.05 9,507.05 10.00 11,810.00
S-012-B conduit (2 1/2" sch 40 pvc, no conductors, include
pull tape full length)
1,798      LNFT 13.00 23,374.00 9.00 16,182.00 8.10 14,563.80 12.00 21,576.00
S-012-C conduit (1 1/2" hdpe by horizontal directional
drilling)
110      LNFT 51.00 5,610.00 24.20 2,662.00 22.00 2,420.00 27.00 2,970.00
S-012-D conduit (2 1/2" hdpe by horizontal directional
drilling)
600      LNFT 52.00 31,200.00 27.50 16,500.00 25.00 15,000.00 30.00 18,000.00
S-013-A 8" c-900 pvc water main 880      LNFT 75.00 66,000.00 50.00 44,000.00 75.00 66,000.00 45.00 39,600.00
S-013-B 12" c-900 pvc water main 60      LNFT 125.00 7,500.00 130.00 7,800.00 130.00 7,800.00 55.00 3,300.00
S-013-C iron fittings 3,000      LB 8.00 24,000.00 10.00 30,000.00 10.00 30,000.00 10.00 30,000.00
S-013-D 6" gate valve with valve box 4      EACH 1,000.00 4,000.00 1,660.00 6,640.00 1,600.00 6,400.00 1,400.00 5,600.00
S-013-E 8" gate valve with valve box 5      EACH 1,500.00 7,500.00 2,080.00 10,400.00 2,000.00 10,000.00 1,600.00 8,000.00
S-013-F 12" gate valve with valve box 2      EACH 2,750.00 5,500.00 3,050.00 6,100.00 3,000.00 6,000.00 3,400.00 6,800.00
S-013-G fire hydrant 4      EACH 4,500.00 18,000.00 5,350.00 21,400.00 3,700.00 14,800.00 4,200.00 16,800.00
S-013-H connect new water main to existing water main 6      EACH 2,500.00 15,000.00 2,900.00 17,400.00 2,800.00 16,800.00 2,000.00 12,000.00
S-013-I 3/4" water service assembly 9      EACH 1,000.00 9,000.00 1,200.00 10,800.00 1,700.00 15,300.00 2,000.00 18,000.00
S-013-J 3/4" water service line 90      LNFT 20.00 1,800.00 15.00 1,350.00 20.00 1,800.00 15.00 1,350.00
S-013-K 3/4" water service line by jack & bore 100      LNFT 30.00 3,000.00 25.00 2,500.00 30.00 3,000.00 80.00 8,000.00
S-013-L 2" water service assembly 1      EACH 3,500.00 3,500.00 3,300.00 3,300.00 3,200.00 3,200.00 2,800.00 2,800.00
S-013-M 2" water service line 10      LNFT 100.00 1,000.00 75.00 750.00 75.00 750.00 20.00 200.00
S-013-N 1" water service assembly 1      LNFT 2,000.00 2,000.00 1,500.00 1,500.00 2,000.00 2,000.00 1,200.00 1,200.00
S-013-O 1" water service line 10      EACH 80.00 800.00 50.00 500.00 50.00 500.00 20.00 200.00
S-014-A 4" pe water main 30      LNFT 50.00 1,500.00 90.00 2,700.00 90.00 2,700.00 35.00 1,050.00
S-014-B 4" pe water main by horizontal directional drilling 26      LNFT 100.00 2,600.00 115.00 2,990.00 75.00 1,950.00 160.00 4,160.00
S-014-C 8" pe water main by horizontal directional drilling 40      LNFT 200.00 8,000.00 150.00 6,000.00 80.00 3,200.00 210.00 8,400.00
S-014-D 12" pe water main by horizontal directional drilling 25      LNFT 350.00 8,750.00 295.00 7,375.00 160.00 4,000.00 240.00 6,000.00
S-015 adjusting water valves, gas valves, meter boxes and
sewer cleanouts
5      EACH 500.00 2,500.00 825.00 4,125.00 300.00 1,500.00 500.00 2,500.00
S-016 abandoning existing water mains lump      LUMP 5,000.00 5,000.00 8,250.00 8,250.00 12,000.00 12,000.00 9,000.00 9,000.00
S-017 temporary business entrances lump      LUMP 20,000.00 20,000.00 30,000.00 30,000.00 12,000.00 12,000.00 30,000.00 30,000.00
                       
 CONTRACTOR TOTAL       1,359,084.00   1,422,470.65   1,474,010.85   1,490,173.00