Letting of 2/25/2009 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 744-10-0021
Parish: CALCASIEU
Routes:
Description: SIDEWALK ON PRATER ROAD
Type Const: grading, sidewalk and related work
Estimated Construction Cost: $220,643.00
 
RankLicenseBidderConstruction Bid
1 43371 RMD HOLDINGS LTD $119,291.43
2 36384 JOHN BAILEY, INC. $186,019.70
 
Item Number Item Description Quantity Unit of Measure - 1 -
RMD HOLDINGS LTD
- 2 -
JOHN BAILEY, INC.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
203-05 excavation and embankment lump      LUMP 4,500.00 4,500.00 28,500.00 28,500.00        
204-06 temporary silt fencing 200      LNFT 10.00 2,000.00 6.00 1,200.00        
702-04-B adjusting catch basins 10      EACH 450.00 4,500.00 1,500.00 15,000.00        
706-01-A concrete walk (4" thick) 1,065.3    SQYD 48.00 51,134.40 65.00 69,244.50        
706-01-C concrete walk (6" thick) 263.6    SQYD 63.00 16,606.80 82.00 21,615.20        
713-01 temporary signs & barricades lump      LUMP 3,000.00 3,000.00 10,000.00 10,000.00        
716-01-B mulch (fiber) 0.6    TON 1,500.00 900.00 1,000.00 600.00        
727-01 mobilization lump      LUMP 20,000.00 20,000.00 25,000.00 25,000.00        
732-01-E plastic pavement striping (24" width) 148      LNFT 50.00 7,400.00 15.00 2,220.00        
739-01 hydro-seeding 0.41   ACRE 3,903.00 1,600.23 4,000.00 1,640.00        
740-01 construction layout lump      LUMP 2,400.00 2,400.00 3,500.00 3,500.00        
S-001 channel drain installation 6      EACH 500.00 3,000.00 500.00 3,000.00        
S-002 channel drain 3      EACH 750.00 2,250.00 1,500.00 4,500.00        
                       
 CONTRACTOR TOTAL       119,291.43   186,019.70        