| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - LOUISIANA BRIDGE, INC. |
- 2 - C W & W CONTRACTORS, INC. |
- 3 - BLOUNT BROS. CONSTRUCTION, INC. |
- 4 - JAMES CONSTRUCTION GROUP LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
3,600.00 |
3,600.00 |
15,000.00 |
15,000.00 |
40,000.00 |
40,000.00 |
55,000.00 |
55,000.00 |
| 202-02-A-01 |
removal of bridges (sta 100+00; 55'x20' timber bridge)
|
1   |
EACH |
3,300.00 |
3,300.00 |
7,500.00 |
7,500.00 |
20,000.00 |
20,000.00 |
8,000.00 |
8,000.00 |
| 202-02-I |
removal of pipes (sta 15+26; 3-72" cmp)
|
lump |
LUMP |
4,000.00 |
4,000.00 |
7,500.00 |
7,500.00 |
20,000.00 |
20,000.00 |
10,000.00 |
10,000.00 |
| 203-05 |
excavation and embankment
|
lump |
LUMP |
159,000.00 |
159,000.00 |
100,000.00 |
100,000.00 |
80,000.00 |
80,000.00 |
89,000.00 |
89,000.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
8   |
EACH |
60.00 |
480.00 |
250.00 |
2,000.00 |
115.00 |
920.00 |
165.00 |
1,320.00 |
| 204-06 |
temporary silt fencing
|
1,800   |
LNFT |
3.00 |
5,400.00 |
3.00 |
5,400.00 |
3.00 |
5,400.00 |
3.00 |
5,400.00 |
| 302-01-A |
class ii base course (stone)
|
615.1 |
CUYD |
80.00 |
49,208.00 |
100.00 |
61,510.00 |
90.00 |
55,359.00 |
125.00 |
76,887.50 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
72   |
CUYD |
106.00 |
7,632.00 |
100.00 |
7,200.00 |
45.00 |
3,240.00 |
75.00 |
5,400.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
100.0 |
CUYD |
104.00 |
10,400.00 |
100.00 |
10,000.00 |
40.00 |
4,000.00 |
50.00 |
5,000.00 |
| 502-01 |
superpave asphaltic concrete
|
480.6 |
TON |
227.00 |
109,096.20 |
150.00 |
72,090.00 |
120.00 |
57,672.00 |
160.00 |
76,896.00 |
| 701-05-G |
side drain pipe (18")
|
30   |
LNFT |
109.00 |
3,270.00 |
50.00 |
1,500.00 |
40.00 |
1,200.00 |
75.00 |
2,250.00 |
| 704-08-B |
guard rail transitions (double thrie beam)
|
200.0 |
LNFT |
65.00 |
13,000.00 |
73.00 |
14,600.00 |
65.00 |
13,000.00 |
57.00 |
11,400.00 |
| 704-09 |
guard rail anchor sections (turndown)
|
200.0 |
LNFT |
40.00 |
8,000.00 |
45.00 |
9,000.00 |
40.00 |
8,000.00 |
35.00 |
7,000.00 |
| 705-02 |
combination mesh & barbed wire fence
|
400   |
LNFT |
10.00 |
4,000.00 |
20.00 |
8,000.00 |
10.00 |
4,000.00 |
6.00 |
2,400.00 |
| 707-04 |
asphaltic curb
|
40.0 |
LNFT |
26.00 |
1,040.00 |
30.00 |
1,200.00 |
30.00 |
1,200.00 |
30.00 |
1,200.00 |
| 711-01-D |
riprap (55 lb,18" thick )
|
550   |
SQYD |
85.00 |
46,750.00 |
85.00 |
46,750.00 |
65.00 |
35,750.00 |
65.00 |
35,750.00 |
| 711-04 |
geotextile fabric
|
550   |
SQYD |
4.00 |
2,200.00 |
3.00 |
1,650.00 |
3.00 |
1,650.00 |
4.00 |
2,200.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
9,000.00 |
9,000.00 |
15,000.00 |
15,000.00 |
20,000.00 |
20,000.00 |
20,000.00 |
20,000.00 |
| 713-02-A-01 |
temporary pavement markings (4" width)(type
1 removable) |
4,408   |
LNFT |
3.00 |
13,224.00 |
4.00 |
17,632.00 |
3.00 |
13,224.00 |
2.25 |
9,918.00 |
| 713-02-E |
temporary pavement markings (24" width)(type
1 removable) |
20   |
LNFT |
16.00 |
320.00 |
23.00 |
460.00 |
20.00 |
400.00 |
14.00 |
280.00 |
| 713-07 |
temporary precast concrete barrier (contractor
furnished) |
52   |
EACH |
725.00 |
37,700.00 |
1,000.00 |
52,000.00 |
800.00 |
41,600.00 |
1,000.00 |
52,000.00 |
| 716-01-A |
mulch (vegetative)
|
1.4 |
TON |
1,542.00 |
2,158.80 |
2,500.00 |
3,500.00 |
550.00 |
770.00 |
650.00 |
910.00 |
| 717-01 |
seeding
|
21   |
LB |
7.00 |
147.00 |
50.00 |
1,050.00 |
10.00 |
210.00 |
7.00 |
147.00 |
| 718-01 |
fertilizer
|
700   |
LB |
2.00 |
1,400.00 |
2.00 |
1,400.00 |
1.00 |
700.00 |
0.35 |
245.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
55,000.00 |
55,000.00 |
75,000.00 |
75,000.00 |
40,000.00 |
40,000.00 |
110,000.00 |
110,000.00 |
| 729-16-C |
object marker assembly (type 3)
|
16   |
EACH |
85.00 |
1,360.00 |
95.00 |
1,520.00 |
150.00 |
2,400.00 |
75.00 |
1,200.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
15,200.00 |
15,200.00 |
15,000.00 |
15,000.00 |
30,000.00 |
30,000.00 |
20,000.00 |
20,000.00 |
| 803-05 |
temporary sheeting
|
lump |
LUMP |
15,000.00 |
15,000.00 |
50,000.00 |
50,000.00 |
60,000.00 |
60,000.00 |
35,000.00 |
35,000.00 |
| 804-01-B |
precast concrete piles (14")
|
1,935   |
LNFT |
56.00 |
108,360.00 |
100.00 |
193,500.00 |
60.00 |
116,100.00 |
90.00 |
174,150.00 |
| 804-12 |
loading permanent piles
|
2   |
EACH |
1.00 |
2.00 |
1.00 |
2.00 |
5,000.00 |
10,000.00 |
2,500.00 |
5,000.00 |
| 805-10-A |
bridge superstructure & substructure (28' rdw; 90 deg
xing)(c.i.p.) |
12   |
SPAN |
31,000.00 |
372,000.00 |
30,000.00 |
360,000.00 |
42,000.00 |
504,000.00 |
38,000.00 |
456,000.00 |
| S-001 |
temporary traffic signal (solar operated)
|
2   |
EACH |
41,000.00 |
82,000.00 |
60,000.00 |
120,000.00 |
45,000.00 |
90,000.00 |
2,500.00 |
5,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,143,248.00 |
|
1,276,964.00 |
|
1,280,795.00 |
|
1,284,953.50 |
|