| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC. |
- 2 - BOH BROS. CONSTRUCTION CO., LLC. |
- 3 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
10,000.00 |
10,000.00 |
1,000.00 |
1,000.00 |
20,000.00 |
20,000.00 |
|
|
| 202-02-H |
removal of guard rail
|
4,999   |
LNFT |
10.00 |
49,990.00 |
5.00 |
24,995.00 |
20.00 |
99,980.00 |
|
|
| 203-01 |
general excavation
|
3,872   |
CUYD |
1.00 |
3,872.00 |
12.00 |
46,464.00 |
18.00 |
69,696.00 |
|
|
| 203-07 |
borrow (vehicular meas.)
|
24,600   |
CUYD |
20.00 |
492,000.00 |
15.00 |
369,000.00 |
18.00 |
442,800.00 |
|
|
| 203-07-B |
borrow (vehicular meas.)(plastic soils)
|
2,400   |
CUYD |
20.00 |
48,000.00 |
20.00 |
48,000.00 |
18.00 |
43,200.00 |
|
|
| 204-02 |
temporary hay or straw bales
|
20   |
EACH |
100.00 |
2,000.00 |
15.00 |
300.00 |
50.00 |
1,000.00 |
|
|
| 204-06 |
temporary silt fencing
|
15,000   |
LNFT |
1.50 |
22,500.00 |
1.50 |
22,500.00 |
5.00 |
75,000.00 |
|
|
| 302-02-G |
class ii base course (16" thick)
|
8,710.2 |
SQYD |
35.00 |
304,857.00 |
80.00 |
696,816.00 |
44.00 |
383,248.80 |
|
|
| 502-01 |
superpave asphaltic concrete
|
58,927.1 |
TON |
80.00 |
4,714,168.00 |
88.00 |
5,185,584.80 |
77.50 |
4,566,850.25 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
1,900.0 |
TON |
80.00 |
152,000.00 |
130.00 |
247,000.00 |
150.00 |
285,000.00 |
|
|
| 508-01 |
asphalt concrete (sma) wearing course
|
40,356.9 |
TON |
90.00 |
3,632,121.00 |
115.00 |
4,641,043.50 |
125.00 |
5,044,612.50 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
327,439   |
SQYD |
3.00 |
982,317.00 |
2.00 |
654,878.00 |
2.00 |
654,878.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 13,643   |
CUYD |
20.00 |
- 272,860.00 |
15.00 |
- 204,645.00 |
0.10 |
- 1,364.30 |
|
|
| 510-01-D |
pavement patching (18" minimum thickness)
|
300   |
SQYD |
150.00 |
45,000.00 |
185.00 |
55,500.00 |
150.00 |
45,000.00 |
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
702   |
LNFT |
2.00 |
1,404.00 |
11.00 |
7,722.00 |
1.00 |
702.00 |
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
848   |
LNFT |
2.00 |
1,696.00 |
10.00 |
8,480.00 |
1.00 |
848.00 |
|
|
| 602-03 |
cleaning and sealing cracks
|
1,000   |
LNFT |
3.00 |
3,000.00 |
8.00 |
8,000.00 |
1.00 |
1,000.00 |
|
|
| 701-10-G |
reinforced concrete pipe (extension)(18")
|
12   |
LNFT |
300.00 |
3,600.00 |
110.00 |
1,320.00 |
425.00 |
5,100.00 |
|
|
| 701-15 |
concrete collar
|
17   |
EACH |
1,000.00 |
17,000.00 |
450.00 |
7,650.00 |
725.00 |
12,325.00 |
|
|
| 702-07-A |
cross drain safety end (type 1)
|
1   |
EACH |
750.00 |
750.00 |
4,500.00 |
4,500.00 |
6,000.00 |
6,000.00 |
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
125.0 |
LNFT |
45.00 |
5,625.00 |
45.00 |
5,625.00 |
52.00 |
6,500.00 |
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
287.5 |
LNFT |
41.00 |
11,787.50 |
40.00 |
11,500.00 |
30.00 |
8,625.00 |
|
|
| 704-01-C |
guard rail (double thrie beam)(3'-1 1/2" post spacing)
|
287.5 |
LNFT |
61.00 |
17,537.50 |
60.00 |
17,250.00 |
52.00 |
14,950.00 |
|
|
| 704-03 |
blocked out guard rail
|
3,325.0 |
LNFT |
18.00 |
59,850.00 |
18.00 |
59,850.00 |
19.00 |
63,175.00 |
|
|
| 704-06 |
guard rail anchor sections (trailing end)
|
25.0 |
LNFT |
78.00 |
1,950.00 |
75.00 |
1,875.00 |
78.00 |
1,950.00 |
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
37.5 |
LNFT |
91.00 |
3,412.50 |
90.00 |
3,375.00 |
95.00 |
3,562.50 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
350.0 |
LNFT |
61.00 |
21,350.00 |
60.00 |
21,000.00 |
55.00 |
19,250.00 |
|
|
| 704-10 |
guard rail anchor block
|
14   |
EACH |
1,900.00 |
26,600.00 |
1,825.00 |
25,550.00 |
1,400.00 |
19,600.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
24   |
EACH |
2,400.00 |
57,600.00 |
2,300.00 |
55,200.00 |
2,000.00 |
48,000.00 |
|
|
| 706-03-A |
incidental concrete paving (4" thick)
|
1,175.3 |
SQYD |
45.00 |
52,888.50 |
60.00 |
70,518.00 |
50.00 |
58,765.00 |
|
|
| 707-04 |
asphaltic curb
|
100.0 |
LNFT |
50.00 |
5,000.00 |
30.00 |
3,000.00 |
60.00 |
6,000.00 |
|
|
| 710-01 |
flowable fill
|
50   |
CUYD |
90.00 |
4,500.00 |
300.00 |
15,000.00 |
155.00 |
7,750.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
497,550.00 |
497,550.00 |
100,000.00 |
100,000.00 |
900,000.00 |
900,000.00 |
|
|
| 713-02-C |
temporary pavement markings (8" width)
|
8,427   |
LNFT |
0.01 |
84.27 |
0.17 |
1,432.59 |
0.42 |
3,539.34 |
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
3,198   |
LNFT |
0.01 |
31.98 |
0.55 |
1,758.90 |
1.50 |
4,797.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
62.013 |
MILE |
10.00 |
620.13 |
10.00 |
620.13 |
1.00 |
62.01 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
62.130 |
MILE |
100.00 |
6,213.00 |
20.00 |
1,242.60 |
1.00 |
62.13 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
148.470 |
MILE |
100.00 |
14,847.00 |
25.00 |
3,711.75 |
1.00 |
148.47 |
|
|
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
12   |
EACH |
80.00 |
960.00 |
10.00 |
120.00 |
52.00 |
624.00 |
|
|
| 713-05-C |
temporary pavement legends and symbols (only)
|
12   |
EACH |
80.00 |
960.00 |
10.00 |
120.00 |
52.00 |
624.00 |
|
|
| 716-01-A |
mulch (vegetative)
|
10.0 |
TON |
800.00 |
8,000.00 |
700.00 |
7,000.00 |
710.00 |
7,100.00 |
|
|
| 721-01 |
mowing
|
2,320.0 |
ACRE |
20.00 |
46,400.00 |
40.00 |
92,800.00 |
35.00 |
81,200.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
725,000.00 |
725,000.00 |
1,135,000.00 |
1,135,000.00 |
1,489,000.00 |
1,489,000.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
94   |
EACH |
90.00 |
8,460.00 |
65.00 |
6,110.00 |
65.00 |
6,110.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
34   |
EACH |
110.00 |
3,740.00 |
80.00 |
2,720.00 |
77.00 |
2,618.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
4,100   |
EACH |
5.25 |
21,525.00 |
5.50 |
22,550.00 |
5.50 |
22,550.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
2,809   |
LNFT |
1.00 |
2,809.00 |
1.00 |
2,809.00 |
1.15 |
3,230.35 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
1,066   |
LNFT |
4.50 |
4,797.00 |
4.50 |
4,797.00 |
4.00 |
4,264.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
49.490 |
MILE |
3,000.00 |
148,470.00 |
2,400.00 |
118,776.00 |
3,000.00 |
148,470.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
20.671 |
MILE |
1,000.00 |
20,671.00 |
800.00 |
16,536.80 |
800.00 |
16,536.80 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
4   |
EACH |
500.00 |
2,000.00 |
200.00 |
800.00 |
210.00 |
840.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
4   |
EACH |
500.00 |
2,000.00 |
200.00 |
800.00 |
220.00 |
880.00 |
|
|
| 732-05 |
removal of existing markings
|
3.000 |
MILE |
500.00 |
1,500.00 |
5,000.00 |
15,000.00 |
5,750.00 |
17,250.00 |
|
|
| 739-01 |
hydro-seeding
|
30.00 |
ACRE |
1,000.00 |
30,000.00 |
1,000.00 |
30,000.00 |
1,000.00 |
30,000.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
196,483.12 |
196,483.12 |
25,000.00 |
25,000.00 |
50,000.00 |
50,000.00 |
|
|
| S-001 |
rumble strips (ground-in)
|
40.5 |
MILE |
900.00 |
36,450.00 |
900.00 |
36,450.00 |
330.00 |
13,365.00 |
|
|
| S-002 |
concrete apron
|
37   |
EACH |
1,000.00 |
37,000.00 |
1,400.00 |
51,800.00 |
900.00 |
33,300.00 |
|
|
| S-003 |
exposing existing r.c. pipe
|
153   |
LNFT |
100.00 |
15,300.00 |
50.00 |
7,650.00 |
26.00 |
3,978.00 |
|
|
| S-004 |
dynamic message sign unit
|
6   |
EACH |
10,000.00 |
60,000.00 |
13,000.00 |
78,000.00 |
12,500.00 |
75,000.00 |
|
|
| S-005 |
remove and relocate sign posts and footings
|
5   |
EACH |
3,100.00 |
15,500.00 |
3,100.00 |
15,500.00 |
2,200.00 |
11,000.00 |
|
|
| S-006 |
cleaning existing ditches
|
6,350   |
LNFT |
1.75 |
11,112.50 |
3.50 |
22,225.00 |
4.50 |
28,575.00 |
|
|
| S-007 |
video detector device and connection
|
1   |
EACH |
8,000.00 |
8,000.00 |
7,000.00 |
7,000.00 |
7,000.00 |
7,000.00 |
|
|
| S-008 |
video detection system (intersection)
|
1   |
EACH |
5,000.00 |
5,000.00 |
9,500.00 |
9,500.00 |
4,500.00 |
4,500.00 |
|
|
| S-009 |
raising and/or undersealing concrete pavement slabs
|
10,000   |
LBS |
4.00 |
40,000.00 |
6.00 |
60,000.00 |
4.50 |
45,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
12,453,000.00 |
|
13,993,681.07 |
|
15,025,627.85 |
|
|
| | NUMBER OF DAYS BID AT $5,000 PER DAY. |
|
|
|
800,000.00 |
|
1,250,000.00 |
|
1,500,000.00 |
|
|
| | TOTAL BID |
|
|
|
13,253,000.00 |
|
15,243,681.07 |
|
16,525,627.85 |
|
|
|