Lead Project: 450-06-0063
Parish: ST MARTIN, IBERVILLE, W BATON ROUGE
Routes: I-10
Description: I-10 PAVEMENT MARKING REPLACEMENT
Type Const: pavement marking replacement, reflectorized raised pavement markers, and related
work.
Estimated Construction Cost: $759,958.20
 
RankLicenseBidderConstruction Bid
1 23811 HIGHWAY TECHNOLOGIES INC $524,128.17
2 48416 SOUTHERN SYNERGY LLC $582,802.75
3 06799 PAV'T-MARK. CO, DIV OF GULF IND INC $921,411.56
 
Item Number Item Description Quantity Unit of Measure - 1 -
HIGHWAY TECHNOLOGIES INC
- 2 -
SOUTHERN SYNERGY LLC
- 3 -
PAV'T-MARK. CO, DIV OF GULF IND INC

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
713-01 temporary signs & barricades lump      LUMP 10,000.00 10,000.00 10,000.00 10,000.00 45,000.00 45,000.00    
727-01 mobilization lump      LUMP 40,000.00 40,000.00 10,000.00 10,000.00 90,000.00 90,000.00    
731-02 reflectorized raised pavement markers 44,400      EACH 3.60 159,840.00 4.75 210,900.00 5.20 230,880.00    
732-02-A plastic pavement striping (solid line) (4" width) 144.440  MILE 1,700.00 245,548.00 1,900.00 274,436.00 3,100.00 447,764.00    
732-02-C plastic pavement striping (solid line) (8" width) 2.250  MILE 3,200.00 7,200.00 3,800.00 8,550.00 6,390.00 14,377.50    
732-03-A plastic pavement striping (broken line)(4" width) 72.909  MILE 630.00 45,932.67 750.00 54,681.75 840.00 61,243.56    
732-05 removal of existing markings 2.745  MILE 3,500.00 9,607.50 3,000.00 8,235.00 5,700.00 15,646.50    
S-001 dynamic message sign unit 3      ea 2,000.00 6,000.00 2,000.00 6,000.00 5,500.00 16,500.00    
                       
 CONTRACTOR TOTAL       524,128.17   582,802.75   921,411.56    