Letting of 2/25/2009 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 362-01-0009
Parish: NATCHITOCHES
Routes: LA 491
Description: RAT BOIS BAYOU & BAYOU NID AIGLE
Type Const: grading, drainage structures, class ii base course, super pave asphaltic concrete
pavement, lime treatment, precast prestressed concrete girder spans bridge, and related work.
Estimated Construction Cost: $2,438,286.08
 
RankLicenseBidderConstruction Bid
1 12312 GILCHRIST CONSTRUCTION CO. LLC $2,727,820.55
2 34567 JAMES CONSTRUCTION GROUP LLC $2,839,280.79
3 14422 T. L. WALLACE CONSTRUCTION, INC. $3,163,540.25
4 18546 C W & W CONTRACTORS, INC. $3,294,560.80
 
Item Number Item Description Quantity Unit of Measure - 1 -
GILCHRIST CONSTRUCTION CO. LLC
- 2 -
JAMES CONSTRUCTION GROUP LLC
- 3 -
T. L. WALLACE CONSTRUCTION, INC.
- 4 -
C W & W CONTRACTORS, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 50,000.00 50,000.00 70,000.00 70,000.00 100,000.00 100,000.00 30,000.00 30,000.00
202-01 removal of structures & obstructions lump      LUMP 25,000.00 25,000.00 10,000.00 10,000.00 6,000.00 6,000.00 20,000.00 20,000.00
202-02-A-01 removal of bridge (str. no. 08353620102501 ; sta.
23+82.31 ; 135' x 18' treated timber trestle
bridge)
1      EACH 25,000.00 25,000.00 10,000.00 10,000.00 12,500.00 12,500.00 15,000.00 15,000.00
202-02-A-02 removal of bridge (str. no. 08353620105301 ; sta.
61+62.02 ; 154' x 18' treated timber trestle
bridge)
1      EACH 25,000.00 25,000.00 12,000.00 12,000.00 14,500.00 14,500.00 20,000.00 20,000.00
202-02-H removal of guard rail 448      LNFT 12.00 5,376.00 3.00 1,344.00 5.00 2,240.00 15.00 6,720.00
203-02 drainage excavation 1,999      CUYD 20.00 39,980.00 14.00 27,986.00 12.50 24,987.50 30.00 59,970.00
203-05 excavation & embankment lump      LUMP 90,000.00 90,000.00 55,000.00 55,000.00 50,000.00 50,000.00 100,000.00 100,000.00
204-05-A temporary sediment check dams (hay) 16      EACH 250.00 4,000.00 145.00 2,320.00 64.00 1,024.00 250.00 4,000.00
204-06 temporary silt fencing 550      LNFT 2.50 1,375.00 4.00 2,200.00 3.00 1,650.00 3.00 1,650.00
302-02-D-01 class ii base course (8 1/2" thick) 4,214.3    SQYD 26.00 109,571.80 28.00 118,000.40 28.00 118,000.40 25.00 105,357.50
304-05 lime treatment (type e) 48.73   TON 250.00 12,182.50 285.00 13,888.05 375.00 18,273.75 250.00 12,182.50
401-02 aggregate surface course (adjusted vehicular
measurement)
74      CUYD 125.00 9,250.00 115.00 8,510.00 94.00 6,956.00 100.00 7,400.00
402-01 traffic maintenance aggregate (vehicular measurement) 500.0    CUYD 30.00 15,000.00 100.00 50,000.00 43.75 21,875.00 100.00 50,000.00
403-01 aggregate roadway surfacing (vehicular measurement) 90.0    CUYD 100.00 9,000.00 108.00 9,720.00 125.00 11,250.00 100.00 9,000.00
502-01 superpave asphaltic concrete 622.5    TON 150.00 93,375.00 150.00 93,375.00 250.00 155,625.00 200.00 124,500.00
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
228.5    TON 250.00 57,125.00 175.00 39,987.50 312.50 71,406.25 200.00 45,700.00
701-05-G side drain pipe (18") 376      LNFT 115.00 43,240.00 45.00 16,920.00 53.75 20,210.00 60.00 22,560.00
701-05-I side drain pipe (24") 112      LNFT 185.00 20,720.00 55.00 6,160.00 65.00 7,280.00 70.00 7,840.00
701-05-I-01 side drain pipe (24")(erosion) 168      LNFT 200.00 33,600.00 50.00 8,400.00 50.00 8,400.00 70.00 11,760.00
704-03 blocked out guard rail 225.0    LNFT 20.00 4,500.00 25.00 5,625.00 31.25 7,031.25 25.00 5,625.00
704-08-B guard rail transitions (double thrie beam) 200.0    LNFT 58.00 11,600.00 65.00 13,000.00 77.50 15,500.00 70.00 14,000.00
704-11-A guard rail end treatment (flared) 6      EACH 2,200.00 13,200.00 2,650.00 15,900.00 3,000.00 18,000.00 2,700.00 16,200.00
705-01 barbed wire fence 1,615      LNFT 7.00 11,305.00 6.50 10,497.50 8.00 12,920.00 20.00 32,300.00
705-02 combination mesh & barbed wire fence 220      LNFT 8.00 1,760.00 7.50 1,650.00 9.50 2,090.00 25.00 5,500.00
705-04 single swinging driveway gates 4      EACH 550.00 2,200.00 500.00 2,000.00 625.00 2,500.00 2,000.00 8,000.00
705-05 double swinging driveway gates 1      DBGT 800.00 800.00 800.00 800.00 1,000.00 1,000.00 2,500.00 2,500.00
708-01 right-of-way monument 16      EACH 425.00 6,800.00 140.00 2,240.00 175.00 2,800.00 300.00 4,800.00
708-02 right-of-way monument witness post 16      EACH 425.00 6,800.00 50.00 800.00 62.50 1,000.00 300.00 4,800.00
711-01-C riprap (30 lb, 14" thick) 56      SQYD 250.00 14,000.00 50.00 2,800.00 141.25 7,910.00 100.00 5,600.00
711-04 geotextile fabric 56      SQYD 17.00 952.00 12.00 672.00 7.00 392.00 3.00 168.00
712-04 flexible revetment 950      SQYD 52.00 49,400.00 54.00 51,300.00 140.00 133,000.00 90.00 85,500.00
713-01 temporary signs & barricades lump      LUMP 20,000.00 20,000.00 20,000.00 20,000.00 12,000.00 12,000.00 40,000.00 40,000.00
713-04-A temporary pavement markings (solid line)(4" width) 3.279  MILE 750.00 2,459.25 725.00 2,377.28 750.00 2,459.25 1,000.00 3,279.00
716-01-A mulch (vegetative) 7.50   TON 550.00 4,125.00 595.00 4,462.50 750.00 5,625.00 1,500.00 11,250.00
717-01 seeding 450      LB 8.50 3,825.00 7.00 3,150.00 8.75 3,937.50 15.00 6,750.00
718-01 fertilizer 5,000      LB 0.65 3,250.00 0.60 3,000.00 0.72 3,600.00 1.00 5,000.00
720-01-A erosion control system, slope protection (type a) 2,600      SQYD 1.75 4,550.00 1.30 3,380.00 1.62 4,212.00 1.65 4,290.00
722-01 project site laboratory 1      EACH 40,000.00 40,000.00 10,000.00 10,000.00 7,500.00 7,500.00 20,000.00 20,000.00
725-01 temporary detour roads 2,274.2    SQYD 75.00 170,565.00 100.00 227,420.00 52.00 118,258.40 77.00 175,113.40
725-02 temporary detour bridging 160.00   LNFT 1,200.00 192,000.00 1,500.00 240,000.00 2,500.00 400,000.00 1,600.00 256,000.00
725-03 low profile runaround 1      EACH 180,000.00 180,000.00 245,000.00 245,000.00 150,000.00 150,000.00 115,000.00 115,000.00
727-01 mobilization lump      LUMP 250,000.00 250,000.00 285,000.00 285,000.00 320,000.00 320,000.00 225,000.00 225,000.00
729-16-C object marker assembly (type 3) 8      EACH 80.00 640.00 75.00 600.00 140.00 1,120.00 95.00 760.00
731-02 reflectorized raised pavement markers 32      EACH 5.25 168.00 5.10 163.20 6.30 201.60 10.00 320.00
732-02-A plastic pavement striping (solid line) (4" width) 0.964  MILE 3,000.00 2,892.00 2,904.00 2,799.46 7,500.00 7,230.00 7,600.00 7,326.40
735-01 mailboxes 3      EACH 50.00 150.00 10.00 30.00 31.25 93.75 200.00 600.00
735-02 mailbox supports (single) 3      EACH 150.00 450.00 150.00 450.00 200.00 600.00 200.00 600.00
740-01 construction layout lump      LUMP 35,000.00 35,000.00 40,000.00 40,000.00 37,000.00 37,000.00 65,000.00 65,000.00
804-01-B precast concrete piles (14") 2,160      LNFT 46.00 99,360.00 65.00 140,400.00 45.50 98,280.00 80.00 172,800.00
804-01-F precast concrete piles (24") 690      LNFT 120.00 82,800.00 170.00 117,300.00 115.73 79,853.70 220.00 151,800.00
804-12 loading permanent piles 2      EACH 7,500.00 15,000.00 5,000.00 10,000.00 21,000.00 42,000.00 1.00 2.00
805-01-F class a concrete (bents) 124.29   CUYD 1,000.00 124,290.00 890.00 110,618.10 800.00 99,432.00 1,200.00 149,148.00
805-03 class aa concrete 217.20   CUYD 700.00 152,040.00 850.00 184,620.00 700.00 152,040.00 1,000.00 217,200.00
805-04 class aa(m) concrete 129.48   CUYD 1,100.00 142,428.00 1,075.00 139,191.00 750.00 97,110.00 1,000.00 129,480.00
805-08-H precast-prestressed concrete girders (type quad beam) 948.0    LNFT 75.00 71,100.00 90.00 85,320.00 68.00 64,464.00 125.00 118,500.00
805-11 strip seal joints 74.28   LNFT 225.00 16,713.00 180.00 13,370.40 185.00 13,741.80 300.00 22,284.00
806-01 deformed reinforcing steel 95,174      LB 1.30 123,726.20 0.90 85,656.60 1.15 109,450.10 3.00 285,522.00
807-08 structural metalwork lump      LUMP 11,000.00 11,000.00 12,000.00 12,000.00 11,000.00 11,000.00 55,000.00 55,000.00
810-01 concrete railing (type) 640.00   LNFT 65.00 41,600.00 70.00 44,800.00 75.00 48,000.00 100.00 64,000.00
813-01 concrete approach slabs 550.68   SQYD 260.00 143,176.80 260.00 143,176.80 750.00 413,010.00 225.00 123,903.00
S-101 special anchor section 2      EACH 1,200.00 2,400.00 950.00 1,900.00 2,500.00 5,000.00 15,000.00 30,000.00
                       
 CONTRACTOR TOTAL       2,727,820.55   2,839,280.79   3,163,540.25   3,294,560.80