| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC |
- 2 - BOH BROS. CONSTRUCTION CO., LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
2,079   |
SQYD |
22.00 |
45,738.00 |
6.00 |
12,474.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
3,000   |
LNFT |
1.00 |
3,000.00 |
2.00 |
6,000.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
300.0 |
CUYD |
35.00 |
10,500.00 |
85.00 |
25,500.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
8,925.8 |
TON |
110.00 |
981,838.00 |
95.00 |
847,951.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
614.7 |
TON |
125.00 |
76,837.50 |
250.00 |
153,675.00 |
|
|
|
|
| 509-01-B |
cold planing asphaltic pavement (2" avg. depth)
|
59,258   |
SQYD |
1.00 |
59,258.00 |
3.00 |
177,774.00 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
4,760   |
SQYD |
100.00 |
476,000.00 |
50.00 |
238,000.00 |
|
|
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
2,000   |
LNFT |
5.00 |
10,000.00 |
1.75 |
3,500.00 |
|
|
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
22,354   |
LNFT |
1.50 |
33,531.00 |
1.75 |
39,119.50 |
|
|
|
|
| 602-03 |
cleaning and sealing cracks
|
1,000   |
LNFT |
4.00 |
4,000.00 |
4.00 |
4,000.00 |
|
|
|
|
| 602-05-H-01 |
full depth patching of jointed conc pvmt (8 1/2" thick)
(16.0 sq yds and un der) |
120.9 |
SQYD |
185.00 |
22,366.50 |
350.00 |
42,315.00 |
|
|
|
|
| 602-05-H-02 |
full depth patching of jointed conc pvmt (8 1/2" thick)
(16.1 sq yds to 48 .0 sq yds) |
1,673.8 |
SQYD |
125.00 |
209,225.00 |
220.00 |
368,236.00 |
|
|
|
|
| 602-05-H-03 |
full depth patching of jointed conc pvmt (8 1/2" thick)
(48.1 sq yds and ov er) |
3,705.1 |
SQYD |
120.00 |
444,612.00 |
208.00 |
770,660.80 |
|
|
|
|
| 701-03-E |
storm drain pipe (12" rpcvp)
|
16   |
LNFT |
150.00 |
2,400.00 |
90.00 |
1,440.00 |
|
|
|
|
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
187   |
LNFT |
120.00 |
22,440.00 |
95.00 |
17,765.00 |
|
|
|
|
| 706-01-A |
concrete walk (4" thick)
|
1,200.0 |
SQYD |
90.00 |
108,000.00 |
80.00 |
96,000.00 |
|
|
|
|
| 707-04 |
asphaltic curb
|
3,094.0 |
LNFT |
20.00 |
61,880.00 |
17.00 |
52,598.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
450,000.00 |
450,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
3.557 |
MILE |
100.00 |
355.70 |
325.00 |
1,156.03 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
3.557 |
MILE |
100.00 |
355.70 |
725.00 |
2,578.83 |
|
|
|
|
| 713-05-E |
temporary pavement legends and symbols (school
crossing) |
3   |
EACH |
50.00 |
150.00 |
80.00 |
240.00 |
|
|
|
|
| 723-01 |
granular material (net section)
|
1,200   |
CUYD |
25.00 |
30,000.00 |
32.00 |
38,400.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
450,000.00 |
450,000.00 |
525,000.00 |
525,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
690   |
EACH |
7.00 |
4,830.00 |
5.00 |
3,450.00 |
|
|
|
|
| 732-01-B |
plastic pavement striping (6" width)
|
6,432   |
LNFT |
0.75 |
4,824.00 |
1.00 |
6,432.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
669   |
LNFT |
1.25 |
836.25 |
1.00 |
669.00 |
|
|
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
866   |
LNFT |
2.75 |
2,381.50 |
2.00 |
1,732.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
211   |
LNFT |
5.00 |
1,055.00 |
3.75 |
791.25 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
4.233 |
MILE |
2,500.00 |
10,582.50 |
2,904.00 |
12,292.63 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.894 |
MILE |
900.00 |
4,404.60 |
760.00 |
3,719.44 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
7   |
EACH |
250.00 |
1,750.00 |
195.00 |
1,365.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
7   |
EACH |
250.00 |
1,750.00 |
210.00 |
1,470.00 |
|
|
|
|
| 732-04-E |
plastic pavement legends & symbols (school crossing)
|
3   |
EACH |
450.00 |
1,350.00 |
450.00 |
1,350.00 |
|
|
|
|
| 736-09 |
loop detector
|
667   |
LNFT |
17.00 |
11,339.00 |
15.00 |
10,005.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
150,000.00 |
150,000.00 |
225,000.00 |
225,000.00 |
|
|
|
|
| S-001 |
concrete walks (6" thick) (handicapped ramp - type a)
|
48   |
EACH |
1,500.00 |
72,000.00 |
1,500.00 |
72,000.00 |
|
|
|
|
| S-002 |
concrete walks (6" thick) (handicapped ramp - type b)
|
84   |
EACH |
1,700.00 |
142,800.00 |
1,700.00 |
142,800.00 |
|
|
|
|
| S-004 |
reconstruction of concrete curb and gutter bottom (8"
barrier curb) |
947   |
LNFT |
63.00 |
59,661.00 |
60.00 |
56,820.00 |
|
|
|
|
| S-005 |
reconstruction of concrete curb and gutter (mountable
curb) |
1,075   |
LNFT |
60.00 |
64,500.00 |
60.00 |
64,500.00 |
|
|
|
|
| S-006 |
drilled doweled 8" barrier concrete curb
|
50   |
LNFT |
32.00 |
1,600.00 |
72.00 |
3,600.00 |
|
|
|
|
| S-006A |
drilled doweled 8" mountable concrete curb
|
93   |
LNFT |
32.00 |
2,976.00 |
72.00 |
6,696.00 |
|
|
|
|
| S-007 |
doweled 8" barrier concrete curb
|
267   |
LNFT |
22.00 |
5,874.00 |
27.00 |
7,209.00 |
|
|
|
|
| S-007A |
doweled mountable concrete curb
|
1,361   |
LNFT |
22.00 |
29,942.00 |
10.00 |
13,610.00 |
|
|
|
|
| S-009 |
concrete pavement repair (18.1 sq yds to 48.0 sq yds)
|
241.0 |
SQYD |
140.00 |
33,740.00 |
418.00 |
100,738.00 |
|
|
|
|
| S-010 |
concrete pavement repair (48.1 sq yds and over)
|
2,953.8 |
SQYD |
130.00 |
383,994.00 |
320.00 |
945,216.00 |
|
|
|
|
| S-016A |
catch basin adjustment type a
|
3   |
EACH |
1,500.00 |
4,500.00 |
500.00 |
1,500.00 |
|
|
|
|
| S-017 |
manhole adjustment
|
51   |
EACH |
1,000.00 |
51,000.00 |
900.00 |
45,900.00 |
|
|
|
|
| S-020 |
rehablitate existing catch basins
|
1   |
EACH |
2,500.00 |
2,500.00 |
1,000.00 |
1,000.00 |
|
|
|
|
| S-023 |
catch basin frame and cover
|
3   |
EACH |
850.00 |
2,550.00 |
1,250.00 |
3,750.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
4,555,227.25 |
|
5,257,998.48 |
|
|
|
|
|