LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT
Bid Tabulations


Lead Project: 089-03-0028
Parish: Bienville
Routes: LA 9
Description: OTTER CREEK AND DRAIN DRAIN BRIDGES
Type Const: GRADING, DRAIN STRUCT, LIME TREAT, CLASS II BC, SUPERPAVE ACP, CONCRETE SLAB SPANS BRIDGES AND RELATED WORK.
Estimated Construction Cost: $3,069,743.83


RankLicenseBidderConstruction Bid
1 34567 James Construction Group LLC $2,381,671.10
2 48925 David V. Temple $2,531,204.63
3 01012 Cecil D. Gassiott, LLC $2,725,170.53
4 39580 Gerace Construction Llc $2,744,775.07
5 12135 Blount Bros. Construction, Inc. $2,885,853.40
6 39462 Jb James Construction Llc $3,074,793.37
7 12312 Gilchrist Construction Co. LLC $3,098,386.16
8 09090 Guinn Brothers, LLC. $3,403,047.95
9 18546 C W & W Contractors, Inc. $3,529,342.80
10 43371 RMD Holdings Ltd $3,986,268.35


Line
Number
Item Number Item Description Quantity Unit of
Measure
- 1 -
James Construction Group LLC
- 2 -
David V. Temple
- 3 -
Cecil D. Gassiott, LLC
- 4 -
Gerace Construction Llc
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 30,000.00 30,000.00 25,000.00 25,000.00 50,000.00 50,000.00 70,000.00 70,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 6,500.00 6,500.00 10,000.00 10,000.00 20,000.00 20,000.00 3,000.00 3,000.00
0003 202-02-04000 Removal of Bridge Sta. 110+10; 28.3 ft x 57 ft Concrete Precast Slab Unit Bridge 1      EACH 10,000.00 10,000.00 25,000.00 25,000.00 12,500.00 12,500.00 15,000.00 15,000.00
0004 202-02-04000 Removal of Bridge Sta. 210+93; 29.0 ft x 37 ft Concrete Deck Girder Bridge 1      EACH 15,000.00 15,000.00 25,000.00 25,000.00 12,500.00 12,500.00 15,000.00 15,000.00
0005 202-02-38500 Removal of Surfacing and Stablized Base 5,571.2    SQYD 2.00 11,142.40 4.50 25,070.40 5.00 27,856.00 2.00 11,142.40
0006 202-03-00010 Relocation of Existing 84" RCP 1      EACH 3,000.00 3,000.00 5,000.00 5,000.00 15,000.00 15,000.00 3,000.00 3,000.00
0007 203-02-00100 Drainage Excavation 1,425      CUYD 4.00 5,700.00 11.50 16,387.50 11.00 15,675.00 8.00 11,400.00
0008 203-05-00100 Excavation and Embankment 1      LUMP 100,000.00 100,000.00 120,644.00 120,644.00 130,000.00 130,000.00 150,000.00 150,000.00
0009 204-05-00100 Temporary Sediment Check Dams (Hay) 13      EACH 140.00 1,820.00 137.50 1,787.50 125.00 1,625.00 175.00 2,275.00
0010 204-05-00200 Temporary Sediment Check Dams (Stone) 13      EACH 380.00 4,940.00 350.00 4,550.00 400.00 5,200.00 550.00 7,150.00
0011 204-06-00100 Temporary Silt Fencing 4,930      LNFT 2.25 11,092.50 2.20 10,846.00 2.00 9,860.00 1.75 8,627.50
0012 204-07-00100 Temporary Stone Construction Entrance 2      EACH 2,500.00 5,000.00 1,500.00 3,000.00 3,000.00 6,000.00 3,000.00 6,000.00
0013 302-02-03120 Class II Base Course (8" Thick) (Stone or Recycled Portland Cement Concrete) 9,155.4    SQYD 24.00 219,729.60 18.19 166,536.73 23.00 210,574.20 22.00 201,418.80
0014 304-05-00100 Lime Treatment (Type E) 64.89   TON 200.00 12,978.00 395.00 25,631.55 250.00 16,222.50 450.00 29,200.50
0015 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 100      CUYD 30.00 3,000.00 50.00 5,000.00 95.00 9,500.00 67.97 6,797.00
0016 502-01-00100 Superpave Asphaltic Concrete 1,991.2    TON 110.00 219,032.00 145.75 290,217.40 150.00 298,680.00 138.81 276,398.47
0017 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 465.7    TON 150.00 69,855.00 170.50 79,401.85 175.00 81,497.50 164.31 76,519.17
0018 701-05-01040 Side Drain Pipe (18" RCP/PP/CMP) 30      LNFT 45.00 1,350.00 40.25 1,207.50 50.00 1,500.00 80.94 2,428.20
0019 704-03-00100 Blocked Out Guard Rail 606.3    LNFT 18.00 10,913.40 19.80 12,004.74 19.00 11,519.70 19.00 11,519.70
0020 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 200      LNFT 55.00 11,000.00 60.50 12,100.00 58.00 11,600.00 60.00 12,000.00
0021 704-11-00100 Guard Rail End Treatment (Flared) 8      EACH 2,000.00 16,000.00 2,200.00 17,600.00 2,100.00 16,800.00 2,200.00 17,600.00
0022 708-01-00100 Right-of-Way Monument 27      EACH 180.00 4,860.00 150.00 4,050.00 450.00 12,150.00 160.00 4,320.00
0023 708-02-00100 Right-of-Way Monument Witness Post 27      EACH 130.00 3,510.00 150.00 4,050.00 100.00 2,700.00 160.00 4,320.00
0024 712-04-00100 Flexible Revetment 3,051      SQYD 58.00 176,958.00 60.00 183,060.00 60.00 183,060.00 40.00 122,040.00
0025 713-01-00100 Temporary Signs and Barricades 1      LUMP 10,000.00 10,000.00 10,000.00 10,000.00 8,000.00 8,000.00 15,000.00 15,000.00
0026 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 1.723  MILE 350.00 603.05 385.00 663.36 1,000.00 1,723.00 375.00 646.13
0027 716-01-00100 Mulch (Vegetative) 20.4    TON 675.00 13,770.00 740.00 15,096.00 700.00 14,280.00 550.00 11,220.00
0028 717-01-00100 Seeding 404      LB 8.50 3,434.00 9.30 3,757.20 9.00 3,636.00 7.50 3,030.00
0029 718-01-00100 Fertilizer 10,100      LB 0.50 5,050.00 0.55 5,555.00 0.50 5,050.00 0.50 5,050.00
0030 720-01-01020 Erosion Control System (Slope Protection) (Type B) 4,407      SQYD 1.20 5,288.40 1.35 5,949.45 1.25 5,508.75 1.40 6,169.80
0031 720-01-02000 Erosion Control System, Flexible (Channel Liner) (Type C) 456      SQYD 1.95 889.20 2.20 1,003.20 2.00 912.00 1.90 866.40
0032 722-01-00100 Project Site Laboratory 2      EACH 7,300.00 14,600.00 7,500.00 15,000.00 8,000.00 16,000.00 10,000.00 20,000.00
0033 725-01-00100 Temporary Detour Roads 6,827.3    SQYD 50.00 341,365.00 72.50 494,979.25 66.00 450,601.80 70.00 477,911.00
0034 725-02-00100 Temporary Detour Bridging 60      LNFT 1,500.00 90,000.00 1,000.00 60,000.00 2,150.00 129,000.00 3,000.00 180,000.00
0035 727-01-00100 Mobilization 1      LUMP 215,000.00 215,000.00 150,000.00 150,000.00 150,000.00 150,000.00 270,000.00 270,000.00
0036 729-16-00300 Object Marker Assembly (Type 3) 8      EACH 75.00 600.00 82.50 660.00 85.00 680.00 80.00 640.00
0037 731-02-00100 Reflectorized Raised Pavement Markers 88      EACH 15.00 1,320.00 16.50 1,452.00 10.00 880.00 16.00 1,408.00
0038 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.75   MILE 3,200.00 5,600.00 3,520.00 6,160.00 3,200.00 5,600.00 3,500.00 6,125.00
0039 740-01-00100 Construction Layout 1      LUMP 45,000.00 45,000.00 20,000.00 20,000.00 25,000.00 25,000.00 20,000.00 20,000.00
0040 804-01-00200 Precast Concrete Piles (14") 820      LNFT 70.00 57,400.00 65.00 53,300.00 68.00 55,760.00 65.00 53,300.00
0041 804-01-00300 Precast Concrete Piles (16") 920      LNFT 70.00 64,400.00 75.00 69,000.00 72.00 66,240.00 67.50 62,100.00
0042 804-05-00200 Precast Concrete Test Piles (14") 1      EACH 20,000.00 20,000.00 1,500.00 1,500.00 25,000.00 25,000.00 6,000.00 6,000.00
0043 804-05-00300 Precast Concrete Test Piles (16") 1      EACH 20,000.00 20,000.00 1,500.00 1,500.00 25,000.00 25,000.00 6,500.00 6,500.00
0044 804-09-00100 Loading Test Piles 2      EACH 12,000.00 24,000.00 1,000.00 2,000.00 5,000.00 10,000.00 10,000.00 20,000.00
0045 804-10-00100 Reloading Test Piles 1      EACH 2,000.00 2,000.00 1,000.00 1,000.00 5,000.00 5,000.00 2,500.00 2,500.00
0046 804-11-00100 Redriving Test Piles 1      EACH 1,000.00 1,000.00 1,500.00 1,500.00 1,500.00 1,500.00 2,500.00 2,500.00
0047 804-12-00100 Loading Permanent Piles 1      EACH 10,000.00 10,000.00 1,000.00 1,000.00 1,500.00 1,500.00 2,000.00 2,000.00
0048 804-17-00100 Dynamic Monitoring 10      EACH 600.00 6,000.00 1,500.00 15,000.00 500.00 5,000.00 1,577.82 15,778.20
0049 805-01-00700 Class A Concrete (Bents) 76.94   CUYD 825.00 63,475.50 650.00 50,011.00 1,100.00 84,634.00 1,100.00 84,634.00
0050 805-03-00100 Class AA Concrete 284.72   CUYD 600.00 170,832.00 700.00 199,304.00 850.00 242,012.00 650.00 185,068.00
0051 806-01-00100 Deformed Reinforcing Steel 66,020      LB 0.85 56,117.00 1.25 82,525.00 0.75 49,515.00 0.85 56,117.00
0052 810-01-00100 Concrete Railing (Standard Barrier) 320      LNFT 85.00 27,200.00 75.00 24,000.00 68.00 21,760.00 110.00 35,200.00
0053 813-01-00100 Concrete Approach Slabs 728.88   SQYD 210.00 153,064.80 220.00 160,353.60 210.00 153,064.80 175.00 127,554.00
0054 NS-724-00002 Rumble Strips (Shoulder Ground-In) 0.752  MILE 374.00 281.25 7,700.00 5,790.40 390.00 293.28 400.00 300.80
                         
    CONTRACTOR TOTAL       2,381,671.10   2,531,204.63   2,725,170.53   2,744,775.07



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 5 -
Blount Bros. Construction, Inc.
- 6 -
Jb James Construction Llc
- 7 -
Gilchrist Construction Co. LLC
- 8 -
Guinn Brothers, LLC.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 15,000.00 15,000.00 250,000.00 250,000.00 30,000.00 30,000.00 75,000.00 75,000.00
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 30,000.00 30,000.00 16,000.00 16,000.00 4,000.00 4,000.00 8,000.00 8,000.00
0003 202-02-04000 Removal of Bridge Sta. 110+10; 28.3 ft x 57 ft Concrete Precast Slab Unit Bridge 1      EACH 30,000.00 30,000.00 18,000.00 18,000.00 20,000.00 20,000.00 12,000.00 12,000.00
0004 202-02-04000 Removal of Bridge Sta. 210+93; 29.0 ft x 37 ft Concrete Deck Girder Bridge 1      EACH 30,000.00 30,000.00 10,000.00 10,000.00 20,000.00 20,000.00 15,000.00 15,000.00
0005 202-02-38500 Removal of Surfacing and Stablized Base 5,571.2    SQYD 4.00 22,284.80 3.60 20,056.32 4.30 23,956.16 5.00 27,856.00
0006 202-03-00010 Relocation of Existing 84" RCP 1      EACH 4,000.00 4,000.00 8,000.00 8,000.00 5,000.00 5,000.00 15,000.00 15,000.00
0007 203-02-00100 Drainage Excavation 1,425      CUYD 12.00 17,100.00 11.00 15,675.00 12.00 17,100.00 10.00 14,250.00
0008 203-05-00100 Excavation and Embankment 1      LUMP 90,000.00 90,000.00 250,000.00 250,000.00 305,000.00 305,000.00 206,000.00 206,000.00
0009 204-05-00100 Temporary Sediment Check Dams (Hay) 13      EACH 150.00 1,950.00 125.00 1,625.00 150.00 1,950.00 100.00 1,300.00
0010 204-05-00200 Temporary Sediment Check Dams (Stone) 13      EACH 500.00 6,500.00 800.00 10,400.00 300.00 3,900.00 850.00 11,050.00
0011 204-06-00100 Temporary Silt Fencing 4,930      LNFT 2.50 12,325.00 2.30 11,339.00 1.90 9,367.00 3.00 14,790.00
0012 204-07-00100 Temporary Stone Construction Entrance 2      EACH 4,300.00 8,600.00 2,500.00 5,000.00 2,500.00 5,000.00 1,500.00 3,000.00
0013 302-02-03120 Class II Base Course (8" Thick) (Stone or Recycled Portland Cement Concrete) 9,155.4    SQYD 21.00 192,263.40 26.00 238,040.40 22.00 201,418.80 19.00 173,952.60
0014 304-05-00100 Lime Treatment (Type E) 64.89   TON 275.00 17,844.75 300.00 19,467.00 100.00 6,489.00 275.00 17,844.75
0015 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 100      CUYD 40.00 4,000.00 75.00 7,500.00 25.00 2,500.00 50.00 5,000.00
0016 502-01-00100 Superpave Asphaltic Concrete 1,991.2    TON 150.00 298,680.00 135.00 268,812.00 105.00 209,076.00 200.00 398,240.00
0017 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 465.7    TON 150.00 69,855.00 160.00 74,512.00 185.00 86,154.50 240.00 111,768.00
0018 701-05-01040 Side Drain Pipe (18" RCP/PP/CMP) 30      LNFT 40.00 1,200.00 50.00 1,500.00 90.00 2,700.00 200.00 6,000.00
0019 704-03-00100 Blocked Out Guard Rail 606.3    LNFT 30.00 18,189.00 18.00 10,913.40 20.00 12,126.00 22.00 13,338.60
0020 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 200      LNFT 85.00 17,000.00 55.00 11,000.00 60.00 12,000.00 65.00 13,000.00
0021 704-11-00100 Guard Rail End Treatment (Flared) 8      EACH 3,000.00 24,000.00 2,000.00 16,000.00 2,200.00 17,600.00 2,500.00 20,000.00
0022 708-01-00100 Right-of-Way Monument 27      EACH 175.00 4,725.00 150.00 4,050.00 240.00 6,480.00 250.00 6,750.00
0023 708-02-00100 Right-of-Way Monument Witness Post 27      EACH 75.00 2,025.00 150.00 4,050.00 240.00 6,480.00 100.00 2,700.00
0024 712-04-00100 Flexible Revetment 3,051      SQYD 55.00 167,805.00 55.00 167,805.00 55.00 167,805.00 80.00 244,080.00
0025 713-01-00100 Temporary Signs and Barricades 1      LUMP 15,000.00 15,000.00 40,000.00 40,000.00 65,000.00 65,000.00 30,000.00 30,000.00
0026 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 1.723  MILE 150.00 258.45 350.00 603.05 600.00 1,033.80 550.00 947.65
0027 716-01-00100 Mulch (Vegetative) 20.4    TON 600.00 12,240.00 700.00 14,280.00 550.00 11,220.00 650.00 13,260.00
0028 717-01-00100 Seeding 404      LB 10.00 4,040.00 8.50 3,434.00 7.50 3,030.00 15.00 6,060.00
0029 718-01-00100 Fertilizer 10,100      LB 1.00 10,100.00 0.50 5,050.00 0.50 5,050.00 1.00 10,100.00
0030 720-01-01020 Erosion Control System (Slope Protection) (Type B) 4,407      SQYD 2.00 8,814.00 1.20 5,288.40 1.30 5,729.10 1.25 5,508.75
0031 720-01-02000 Erosion Control System, Flexible (Channel Liner) (Type C) 456      SQYD 2.25 1,026.00 2.00 912.00 1.85 843.60 2.00 912.00
0032 722-01-00100 Project Site Laboratory 2      EACH 10,000.00 20,000.00 5,000.00 10,000.00 5,000.00 10,000.00 10,000.00 20,000.00
0033 725-01-00100 Temporary Detour Roads 6,827.3    SQYD 80.00 546,184.00 60.00 409,638.00 70.00 477,911.00 100.00 682,730.00
0034 725-02-00100 Temporary Detour Bridging 60      LNFT 4,167.00 250,020.00 600.00 36,000.00 1,200.00 72,000.00 2,500.00 150,000.00
0035 727-01-00100 Mobilization 1      LUMP 80,000.00 80,000.00 310,000.00 310,000.00 300,000.00 300,000.00 225,000.00 225,000.00
0036 729-16-00300 Object Marker Assembly (Type 3) 8      EACH 125.00 1,000.00 75.00 600.00 80.00 640.00 100.00 800.00
0037 731-02-00100 Reflectorized Raised Pavement Markers 88      EACH 10.00 880.00 15.00 1,320.00 5.85 514.80 25.00 2,200.00
0038 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.75   MILE 5,000.00 8,750.00 3,200.00 5,600.00 3,000.00 5,250.00 4,000.00 7,000.00
0039 740-01-00100 Construction Layout 1      LUMP 25,000.00 25,000.00 40,000.00 40,000.00 20,000.00 20,000.00 40,000.00 40,000.00
0040 804-01-00200 Precast Concrete Piles (14") 820      LNFT 130.00 106,600.00 86.00 70,520.00 94.00 77,080.00 65.00 53,300.00
0041 804-01-00300 Precast Concrete Piles (16") 920      LNFT 140.00 128,800.00 90.00 82,800.00 95.00 87,400.00 85.00 78,200.00
0042 804-05-00200 Precast Concrete Test Piles (14") 1      EACH 5,000.00 5,000.00 15,000.00 15,000.00 35,000.00 35,000.00 20,000.00 20,000.00
0043 804-05-00300 Precast Concrete Test Piles (16") 1      EACH 5,000.00 5,000.00 15,000.00 15,000.00 35,000.00 35,000.00 20,000.00 20,000.00
0044 804-09-00100 Loading Test Piles 2      EACH 10,000.00 20,000.00 20,000.00 40,000.00 35,000.00 70,000.00 500.00 1,000.00
0045 804-10-00100 Reloading Test Piles 1      EACH 2,500.00 2,500.00 100.00 100.00 6,500.00 6,500.00 500.00 500.00
0046 804-11-00100 Redriving Test Piles 1      EACH 2,000.00 2,000.00 100.00 100.00 1,000.00 1,000.00 500.00 500.00
0047 804-12-00100 Loading Permanent Piles 1      EACH 2,500.00 2,500.00 100.00 100.00 500.00 500.00 1.00 1.00
0048 804-17-00100 Dynamic Monitoring 10      EACH 1,500.00 15,000.00 1,200.00 12,000.00 435.00 4,350.00 1,500.00 15,000.00
0049 805-01-00700 Class A Concrete (Bents) 76.94   CUYD 600.00 46,164.00 1,300.00 100,022.00 1,200.00 92,328.00 950.00 73,093.00
0050 805-03-00100 Class AA Concrete 284.72   CUYD 700.00 199,304.00 560.00 159,443.20 1,100.00 313,192.00 850.00 242,012.00
0051 806-01-00100 Deformed Reinforcing Steel 66,020      LB 1.50 99,030.00 1.00 66,020.00 0.75 49,515.00 1.00 66,020.00
0052 810-01-00100 Concrete Railing (Standard Barrier) 320      LNFT 100.00 32,000.00 80.00 25,600.00 70.00 22,400.00 100.00 32,000.00
0053 813-01-00100 Concrete Approach Slabs 728.88   SQYD 200.00 145,776.00 220.00 160,353.60 205.00 149,420.40 245.00 178,575.60
0054 NS-724-00002 Rumble Strips (Shoulder Ground-In) 0.752  MILE 10,000.00 7,520.00 7,000.00 5,264.00 500.00 376.00 16,500.00 12,408.00
                         
    CONTRACTOR TOTAL       2,885,853.40   3,074,793.37   3,098,386.16   3,403,047.95



Line
Number
Item Number Item Description Quantity Unit of
Measure
- 9 -
C W & W Contractors, Inc.
- 10 -
RMD Holdings Ltd
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001 201-01-00100 Clearing and Grubbing 1      LUMP 36,000.00 36,000.00 76,470.59 76,470.59
0002 202-01-00100 Removal of Structures and Obstructions 1      LUMP 10,000.00 10,000.00 19,394.60 19,394.60
0003 202-02-04000 Removal of Bridge Sta. 110+10; 28.3 ft x 57 ft Concrete Precast Slab Unit Bridge 1      EACH 6,000.00 6,000.00 29,626.16 29,626.16
0004 202-02-04000 Removal of Bridge Sta. 210+93; 29.0 ft x 37 ft Concrete Deck Girder Bridge 1      EACH 6,000.00 6,000.00 46,588.24 46,588.24
0005 202-02-38500 Removal of Surfacing and Stablized Base 5,571.2    SQYD 5.00 27,856.00 11.20 62,397.44
0006 202-03-00010 Relocation of Existing 84" RCP 1      EACH 5,000.00 5,000.00 70,348.87 70,348.87
0007 203-02-00100 Drainage Excavation 1,425      CUYD 15.00 21,375.00 10.03 14,292.75
0008 203-05-00100 Excavation and Embankment 1      LUMP 260,000.00 260,000.00 204,798.51 204,798.51
0009 204-05-00100 Temporary Sediment Check Dams (Hay) 13      EACH 125.00 1,625.00 147.06 1,911.78
0010 204-05-00200 Temporary Sediment Check Dams (Stone) 13      EACH 250.00 3,250.00 271.93 3,535.09
0011 204-06-00100 Temporary Silt Fencing 4,930      LNFT 3.00 14,790.00 2.34 11,536.20
0012 204-07-00100 Temporary Stone Construction Entrance 2      EACH 7,000.00 14,000.00 4,547.72 9,095.44
0013 302-02-03120 Class II Base Course (8" Thick) (Stone or Recycled Portland Cement Concrete) 9,155.4    SQYD 22.00 201,418.80 38.71 354,405.53
0014 304-05-00100 Lime Treatment (Type E) 64.89   TON 200.00 12,978.00 470.59 30,536.59
0015 402-01-00100 Traffic Maintenance Aggregate (Vehicular Measurement) 100      CUYD 100.00 10,000.00 56.52 5,652.00
0016 502-01-00100 Superpave Asphaltic Concrete 1,991.2    TON 180.00 358,416.00 197.65 393,560.68
0017 502-01-00200 Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous 465.7    TON 280.00 130,396.00 235.29 109,574.55
0018 701-05-01040 Side Drain Pipe (18" RCP/PP/CMP) 30      LNFT 60.00 1,800.00 129.41 3,882.30
0019 704-03-00100 Blocked Out Guard Rail 606.3    LNFT 65.00 39,409.50 24.71 14,981.67
0020 704-08-00200 Guard Rail Transitions (Double Thrie Beam) 200      LNFT 100.00 20,000.00 88.24 17,648.00
0021 704-11-00100 Guard Rail End Treatment (Flared) 8      EACH 2,500.00 20,000.00 2,941.18 23,529.44
0022 708-01-00100 Right-of-Way Monument 27      EACH 300.00 8,100.00 247.06 6,670.62
0023 708-02-00100 Right-of-Way Monument Witness Post 27      EACH 300.00 8,100.00 247.06 6,670.62
0024 712-04-00100 Flexible Revetment 3,051      SQYD 85.00 259,335.00 70.59 215,370.09
0025 713-01-00100 Temporary Signs and Barricades 1      LUMP 25,000.00 25,000.00 112,812.55 112,812.55
0026 713-04-01000 Temporary Pavement Markings (Solid Line) (4" Width) 1.723  MILE 2,000.00 3,446.00 411.76 709.46
0027 716-01-00100 Mulch (Vegetative) 20.4    TON 1,000.00 20,400.00 794.12 16,200.05
0028 717-01-00100 Seeding 404      LB 30.00 12,120.00 10.00 4,040.00
0029 718-01-00100 Fertilizer 10,100      LB 2.00 20,200.00 0.59 5,959.00
0030 720-01-01020 Erosion Control System (Slope Protection) (Type B) 4,407      SQYD 4.00 17,628.00 3.72 16,394.04
0031 720-01-02000 Erosion Control System, Flexible (Channel Liner) (Type C) 456      SQYD 10.00 4,560.00 13.82 6,301.92
0032 722-01-00100 Project Site Laboratory 2      EACH 15,000.00 30,000.00 32,058.82 64,117.64
0033 725-01-00100 Temporary Detour Roads 6,827.3    SQYD 85.00 580,320.50 44.67 304,975.49
0034 725-02-00100 Temporary Detour Bridging 60      LNFT 1,500.00 90,000.00 2,932.81 175,968.60
0035 727-01-00100 Mobilization 1      LUMP 400,000.00 400,000.00 351,712.88 351,712.88
0036 729-16-00300 Object Marker Assembly (Type 3) 8      EACH 100.00 800.00 88.24 705.92
0037 731-02-00100 Reflectorized Raised Pavement Markers 88      EACH 100.00 8,800.00 17.65 1,553.20
0038 732-02-02000 Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) 1.75   MILE 6,000.00 10,500.00 3,764.71 6,588.24
0039 740-01-00100 Construction Layout 1      LUMP 30,000.00 30,000.00 21,176.47 21,176.47
0040 804-01-00200 Precast Concrete Piles (14") 820      LNFT 85.00 69,700.00 108.59 89,043.80
0041 804-01-00300 Precast Concrete Piles (16") 920      LNFT 110.00 101,200.00 134.91 124,117.20
0042 804-05-00200 Precast Concrete Test Piles (14") 1      EACH 1.00 1.00 57,777.65 57,777.65
0043 804-05-00300 Precast Concrete Test Piles (16") 1      EACH 1.00 1.00 60,270.59 60,270.59
0044 804-09-00100 Loading Test Piles 2      EACH 1.00 2.00 29,396.47 58,792.94
0045 804-10-00100 Reloading Test Piles 1      EACH 1.00 1.00 30,568.24 30,568.24
0046 804-11-00100 Redriving Test Piles 1      EACH 1.00 1.00 29,411.76 29,411.76
0047 804-12-00100 Loading Permanent Piles 1      EACH 1.00 1.00 29,411.76 29,411.76
0048 804-17-00100 Dynamic Monitoring 10      EACH 300.00 3,000.00 4,705.88 47,058.80
0049 805-01-00700 Class A Concrete (Bents) 76.94   CUYD 1,000.00 76,940.00 1,322.57 101,758.54
0050 805-03-00100 Class AA Concrete 284.72   CUYD 800.00 227,776.00 736.34 209,650.72
0051 806-01-00100 Deformed Reinforcing Steel 66,020      LB 2.00 132,040.00 1.50 99,030.00
0052 810-01-00100 Concrete Railing (Standard Barrier) 320      LNFT 100.00 32,000.00 158.89 50,844.80
0053 813-01-00100 Concrete Approach Slabs 728.88   SQYD 200.00 145,776.00 234.12 170,645.39
0054 NS-724-00002 Rumble Strips (Shoulder Ground-In) 0.752  MILE 15,000.00 11,280.00 8,235.29 6,192.94
                 
    CONTRACTOR TOTAL       3,529,342.80   3,986,268.35