Bid Tabulations
Letting of
08/31/2011
LA DOTD Headquarters
| Lead Project: 085-03-0015 | |
| Parish: Bossier | |
| Routes: LA 160 | |
| Description: La 160: LA 3 to Rocky Mount | |
| Type Const: Cold Planning Asphaltic Pavement, Asphaltic Surface Treatment, Superpave Asphaltic Concrete Pavement, Culverts, Revetment, Guardrail, Pavement Markings, Erosion Control and Related Work | |
| Estimated Construction Cost: $1,931,144.10 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 17464 | Benton & Brown, LLC. | $1,868,820.45 |
| 2 | 36374 | Best-Yet Builders, Llc | $1,879,538.97 |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - Benton & Brown, LLC. |
- 2 - Best-Yet Builders, Llc |
||
| Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 202-02-14500 | Removal of Guard Rail | 998 | LNFT | 4.00 | 3,992.00 | 4.00 | 3,992.00 |
| 0002 | 202-02-32100 | Removal of Pipe (Cross Drain) Stations: 25+33, 25+45, 33+27, 43+18, 52+26, 69+30, 87+29, 87+39, 170+19, 211+13, 220+94, 220+96, 237+19, 271+84, 278+50, 278+61, 316+93. | 809 | LNFT | 10.00 | 8,090.00 | 25.00 | 20,225.00 |
| 0003 | 203-07-00100 | Borrow (Vehicular Measurement) | 3,000 | CUYD | 17.00 | 51,000.00 | 15.00 | 45,000.00 |
| 0004 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 150 | CUYD | 70.00 | 10,500.00 | 45.00 | 6,750.00 |
| 0005 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 48 | CUYD | 50.00 | 2,400.00 | 100.00 | 4,800.00 |
| 0006 | 502-01-00100 | Superpave Asphaltic Concrete | 9,426.5 | TON | 95.00 | 895,517.50 | 97.15 | 915,784.48 |
| 0007 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 720 | TON | 100.00 | 72,000.00 | 100.00 | 72,000.00 |
| 0008 | 507-01-00100 | Asphaltic Material (CRS-2P Emulsion) | 32,704 | GAL | 3.70 | 121,004.80 | 4.00 | 130,816.00 |
| 0009 | 507-02-00200 | Aggregate (S2) | 79,767 | SQYD | 1.00 | 79,767.00 | 1.10 | 87,743.70 |
| 0010 | 509-01-00100 | Cold Planing Asphaltic Pavement | 2,242 | SQYD | 2.00 | 4,484.00 | 3.00 | 6,726.00 |
| 0011 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -63 | CUYD | 0.10 | -6.30 | 0.10 | -6.30 |
| 0012 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 1,500 | SQYD | 40.00 | 60,000.00 | 38.80 | 58,200.00 |
| 0013 | 701-01-01000 | Cross Drain Pipe (24" RCP/PP) | 422 | LNFT | 105.00 | 44,310.00 | 68.15 | 28,759.30 |
| 0014 | 701-01-01020 | Cross Drain Pipe (30" RCP/PP) | 96 | LNFT | 125.00 | 12,000.00 | 96.35 | 9,249.60 |
| 0015 | 701-01-01040 | Cross Drain Pipe (36" RCP/PP) | 166 | LNFT | 165.00 | 27,390.00 | 132.60 | 22,011.60 |
| 0016 | 701-01-01180 | Cross Drain Pipe (96" RCP) | 120 | LNFT | 750.00 | 90,000.00 | 827.40 | 99,288.00 |
| 0017 | 701-02-01160 | Cross Drain Pipe Arch (84" Equiv. RCPA) | 66 | LNFT | 900.00 | 59,400.00 | 1,027.50 | 67,815.00 |
| 0018 | 701-08-00100 | Relaying Pipe | 92 | LNFT | 110.00 | 10,120.00 | 50.00 | 4,600.00 |
| 0019 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 8 | LNFT | 125.00 | 1,000.00 | 75.00 | 600.00 |
| 0020 | 701-15-00100 | Concrete Collar | 10 | EACH | 900.00 | 9,000.00 | 1,000.00 | 10,000.00 |
| 0021 | 704-01-01000 | Guard Rail (Single Thrie Beam) (3'-1 1/2" post spacing) | 200 | LNFT | 40.00 | 8,000.00 | 40.00 | 8,000.00 |
| 0022 | 704-01-01020 | Guard Rail (Single Thrie Beam) (6'-3" post spacing) | 384 | LNFT | 60.00 | 23,040.00 | 60.00 | 23,040.00 |
| 0023 | 704-03-00100 | Blocked Out Guard Rail | 168 | LNFT | 27.00 | 4,536.00 | 27.00 | 4,536.00 |
| 0024 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 2,500.00 | 10,000.00 | 2,500.00 | 10,000.00 |
| 0025 | 712-04-00100 | Flexible Revetment | 320 | SQYD | 60.00 | 19,200.00 | 75.00 | 24,000.00 |
| 0026 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 35,000.00 | 35,000.00 | 12,500.00 | 12,500.00 |
| 0027 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 50 | LNFT | 2.00 | 100.00 | 2.00 | 100.00 |
| 0028 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 12.438 | MILE | 350.00 | 4,353.30 | 800.00 | 9,950.40 |
| 0029 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 5.944 | MILE | 250.00 | 1,486.00 | 250.00 | 1,486.00 |
| 0030 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 40.67 | MILE | 350.00 | 14,234.50 | 83.35 | 3,389.84 |
| 0031 | 713-05-00400 | Temporary Pavement Legends & Symbols (RR Crossing) | 2 | EACH | 100.00 | 200.00 | 100.00 | 200.00 |
| 0032 | 726-01-00100 | Bedding Material | 175 | CUYD | 55.00 | 9,625.00 | 75.00 | 13,125.00 |
| 0033 | 727-01-00100 | Mobilization | 1 | LUMP | 50,000.00 | 50,000.00 | 25,000.00 | 25,000.00 |
| 0034 | 729-16-00200 | Object Marker Assembly (Type 2) | 22 | EACH | 60.00 | 1,320.00 | 60.00 | 1,320.00 |
| 0035 | 729-16-00300 | Object Marker Assembly (Type 3) | 8 | EACH | 100.00 | 800.00 | 100.00 | 800.00 |
| 0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 821 | EACH | 4.50 | 3,694.50 | 4.00 | 3,284.00 |
| 0037 | 732-01-01080 | Plastic Pavement Striping (24" Width) (Thermoplastic 90 mil) | 50 | LNFT | 5.00 | 250.00 | 5.00 | 250.00 |
| 0038 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 20.336 | MILE | 2,900.00 | 58,974.40 | 2,600.00 | 52,873.60 |
| 0039 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.973 | MILE | 750.00 | 2,229.75 | 750.00 | 2,229.75 |
| 0040 | 732-04-18000 | Plastic Pavement Legends and Symbols (RR Crossing) | 2 | EACH | 500.00 | 1,000.00 | 300.00 | 600.00 |
| 0041 | 735-01-00100 | Mailboxes | 48 | EACH | 1.00 | 48.00 | 50.00 | 2,400.00 |
| 0042 | 735-02-00100 | Mailbox Supports (Single) | 48 | EACH | 120.00 | 5,760.00 | 75.00 | 3,600.00 |
| 0043 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 7,500.00 | 7,500.00 |
| 0044 | NS-500-00280 | Surface Preparation | 1 | LUMP | 43,000.00 | 43,000.00 | 75,000.00 | 75,000.00 |
| CONTRACTOR TOTAL | 1,868,820.45 | 1,879,538.97 | ||||||