Bid Tabulations
Letting of
06/23/2010
LA DOTD Headquarters
| Lead Project: 083-04-0021 | |
| Parish: Bossier, Webster | |
| Routes: LA 2 | |
| Description: BODCAU BAYOU BRIDGE ON LA 2 | |
| Type Const: CLEARING & GRUBBING, GRADING, DRAINAGE STRUCTURES, COLD PLANING ASPH. CONC., CLASS II BASE COURSE, LIME TREATMENT, IN-PLACE CEMENT STABALIZED BASE COURSE, SUPERPAVE ASPH. CONC. PAVEMENT, PRECAST PRESTRESSED CONC. GIRDER SPAN BR., & RELATED WORK. | |
| Estimated Construction Cost: $4,445,821.45 | |
| Rank | License | Bidder | Construction Bid |
|---|---|---|---|
| 1 | 34567 | James Construction Group LLC | $4,485,890.60 |
| 2 | 12312 | Gilchrist Construction Co. LLC | $4,499,798.56 |
| 3 | 39462 | JB James Construction LLC | $4,941,202.02 |
| 48925 | David V. Temple | IRREGULAR |
| Line Number |
Item Number | Item Description | Quantity | Unit of Measure |
- 1 - James Construction Group LLC |
- 2 - Gilchrist Construction Co. LLC |
- 3 - JB James Construction LLC |
David V. Temple |
||||
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
|||||
| 0001 | 201-01-00100 | Clearing and Grubbing | 1 | LUMP | 35,000.00 | 35,000.00 | 60,000.00 | 60,000.00 | 500,000.00 | 500,000.00 | 33,500.00 | 33,500.00 |
| 0002 | 202-01-00100 | Removal of Structures and Obstructions | 1 | LUMP | 10,750.00 | 10,750.00 | 10,000.00 | 10,000.00 | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 |
| 0003 | 202-02-04000 | Removal of Bridge Sta. 129+49.96; 412' x 24' Steel Girder Bridge; Str. No. 04600830600001 | 1 | EACH | 50,000.00 | 50,000.00 | 100,000.00 | 100,000.00 | 60,000.00 | 60,000.00 | 200,000.00 | 200,000.00 |
| 0004 | 202-02-38500 | Removal of Surfacing and Stablized Base | 3,624.4 | SQYD | 15.00 | 54,366.00 | 5.90 | 21,383.96 | 4.00 | 14,497.60 | 9.50 | 34,431.80 |
| 0005 | 203-01-00100 | General Excavation | 28,559 | CUYD | 5.00 | 142,795.00 | 3.45 | 98,528.55 | 7.50 | 214,192.50 | 5.00 | 142,795.00 |
| 0006 | 203-03-00100 | Embankment | 60,584 | CUYD | 13.00 | 787,592.00 | 14.00 | 848,176.00 | 16.00 | 969,344.00 | 10.00 | 605,840.00 |
| 0007 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 73 | EACH | 215.00 | 15,695.00 | 250.00 | 18,250.00 | 100.00 | 7,300.00 | 130.00 | 9,490.00 |
| 0008 | 204-05-00200 | Temporary Sediment Check Dams (Stone) | 7 | EACH | 400.00 | 2,800.00 | 500.00 | 3,500.00 | 800.00 | 5,600.00 | 350.00 | 2,450.00 |
| 0009 | 204-06-00100 | Temporary Silt Fencing | 8,884 | LNFT | 3.00 | 26,652.00 | 1.40 | 12,437.60 | 2.00 | 17,768.00 | 2.00 | 17,768.00 |
| 0010 | 204-07-00100 | Temporary Stone Construction Entrance | 2 | EACH | 4,500.00 | 9,000.00 | 3,500.00 | 7,000.00 | 3,000.00 | 6,000.00 | 3,000.00 | 6,000.00 |
| 0011 | 302-02-03020 | Class II Base Course (8" Thick) (Soil Cement) | 6,016.7 | SQYD | 18.00 | 108,300.60 | 13.00 | 78,217.10 | 10.00 | 60,167.00 | 12.00 | 72,200.40 |
| 0012 | 303-01-00150 | In-Place Cement Stabilized Base Course (8 " Thick) | 12,471 | SQYD | 9.50 | 118,474.50 | 10.00 | 124,710.00 | 6.00 | 74,826.00 | 13.00 | 162,123.00 |
| 0013 | 304-05-00100 | Lime Treatment (Type E) | 131.03 | TON | 270.00 | 35,378.10 | 400.00 | 52,412.00 | 350.00 | 45,860.50 | 385.00 | 50,446.55 |
| 0014 | 402-01-00100 | Traffic Maintenance Aggregate (Vehicular Measurement) | 100 | CUYD | 165.00 | 16,500.00 | 60.00 | 6,000.00 | 90.00 | 9,000.00 | 35.00 | 3,500.00 |
| 0015 | 403-01-00100 | Aggregate Roadway Surfacing (Vehicular Measurement) | 264.5 | CUYD | 100.00 | 26,450.00 | 85.00 | 22,482.50 | 90.00 | 23,805.00 | 100.00 | 26,450.00 |
| 0016 | 502-01-00100 | Superpave Asphaltic Concrete | 3,817.6 | TON | 110.00 | 419,936.00 | 115.00 | 439,024.00 | 110.00 | 419,936.00 | 125.00 | 477,200.00 |
| 0017 | 502-01-00200 | Superpave Asphaltic Concrete, Drives, Turnouts and Miscellaneous | 445.8 | TON | 150.00 | 66,870.00 | 160.00 | 71,328.00 | 150.00 | 66,870.00 | 175.00 | 78,015.00 |
| 0018 | 509-01-00100 | Cold Planing Asphaltic Pavement | 6,510 | SQYD | 4.00 | 26,040.00 | 3.00 | 19,530.00 | 3.00 | 19,530.00 | 4.50 | 29,295.00 |
| 0019 | 509-02-00100 | Contractor Retained Reclaimed Asphaltic Pavement | -543 | CUYD | 1.00 | -543.00 | 1.00 | -543.00 | 0.01 | -5.43 | 1.00 | -543.00 |
| 0020 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 54 | LNFT | 105.00 | 5,670.00 | 90.00 | 4,860.00 | 75.00 | 4,050.00 | 58.00 | 3,132.00 |
| 0021 | 701-01-01020 | Cross Drain Pipe (30" RCP/PP) | 572 | LNFT | 140.00 | 80,080.00 | 92.00 | 52,624.00 | 85.00 | 48,620.00 | 85.00 | 48,620.00 |
| 0022 | 704-03-00100 | Blocked Out Guard Rail | 275 | LNFT | 18.00 | 4,950.00 | 20.00 | 5,500.00 | 20.00 | 5,500.00 | 19.80 | 5,445.00 |
| 0023 | 704-08-00200 | Guard Rail Transitions (Double Thrie Beam) | 100 | LNFT | 54.00 | 5,400.00 | 64.00 | 6,400.00 | 60.00 | 6,000.00 | 59.00 | 5,900.00 |
| 0024 | 704-11-00100 | Guard Rail End Treatment (Flared) | 4 | EACH | 1,975.00 | 7,900.00 | 2,300.00 | 9,200.00 | 2,200.00 | 8,800.00 | 2,050.00 | 8,200.00 |
| 0025 | 705-01-00100 | Barbed Wire Fence | 151 | LNFT | 18.00 | 2,718.00 | 12.00 | 1,812.00 | 7.00 | 1,057.00 | 19.80 | 2,989.80 |
| 0026 | 708-01-00100 | Right-of-Way Monument | 30 | EACH | 140.00 | 4,200.00 | 400.00 | 12,000.00 | 120.00 | 3,600.00 | 150.00 | 4,500.00 |
| 0027 | 708-02-00100 | Right-of-Way Monument Witness Post | 30 | EACH | 50.00 | 1,500.00 | 400.00 | 12,000.00 | 120.00 | 3,600.00 | 150.00 | 4,500.00 |
| 0028 | 711-01-02020 | Riprap (10 lb, 12" Thick) | 233 | SQYD | 38.00 | 8,854.00 | 50.00 | 11,650.00 | 60.00 | 13,980.00 | 70.00 | 16,310.00 |
| 0029 | 711-04-00100 | Geotextile Fabric | 1,400 | SQYD | 3.00 | 4,200.00 | 1.50 | 2,100.00 | 2.00 | 2,800.00 | 4.50 | 6,300.00 |
| 0030 | 712-04-00100 | Flexible Revetment | 1,167 | SQYD | 50.00 | 58,350.00 | 50.00 | 58,350.00 | 55.00 | 64,185.00 | 68.00 | 79,356.00 |
| 0031 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 50,000.00 | 50,000.00 | 190,000.00 | 190,000.00 | 50,000.00 | 50,000.00 | 50,000.00 | 50,000.00 |
| 0032 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 2.523 | MILE | 1,000.00 | 2,523.00 | 500.00 | 1,261.50 | 550.00 | 1,387.65 | 1,100.00 | 2,775.30 |
| 0033 | 716-01-00100 | Mulch (Vegetative) | 49.4 | TON | 450.00 | 22,230.00 | 450.00 | 22,230.00 | 450.00 | 22,230.00 | 495.00 | 24,453.00 |
| 0034 | 717-01-00100 | Seeding | 988 | LB | 8.00 | 7,904.00 | 9.40 | 9,287.20 | 10.00 | 9,880.00 | 8.80 | 8,694.40 |
| 0035 | 718-01-00100 | Fertilizer | 24,700 | LB | 0.42 | 10,374.00 | 0.50 | 12,350.00 | 0.30 | 7,410.00 | 0.50 | 12,350.00 |
| 0036 | 720-01-01020 | Erosion Control System (Slope Protection) (Type B) | 6,146 | SQYD | 1.15 | 7,067.90 | 1.35 | 8,297.10 | 1.50 | 9,219.00 | 1.25 | 7,682.50 |
| 0037 | 720-01-02000 | Erosion Control System, Flexible (Channel Liner) (Type C) | 495 | SQYD | 1.60 | 792.00 | 2.35 | 1,163.25 | 2.50 | 1,237.50 | 1.75 | 866.25 |
| 0038 | 720-01-02020 | Erosion Control System, Flexible (Channel Liner) (Type D) | 3,734 | SQYD | 1.75 | 6,534.50 | 3.00 | 11,202.00 | 2.50 | 9,335.00 | 1.90 | 7,094.60 |
| 0039 | 722-01-00100 | Project Site Laboratory | 1 | EACH | 10,000.00 | 10,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 15,000.00 | 25,000.00 | 25,000.00 |
| 0040 | 725-01-00100 | Temporary Detour Roads | 1,609.6 | SQYD | 38.00 | 61,164.80 | 30.00 | 48,288.00 | 32.00 | 51,507.20 | 50.00 | 80,480.00 |
| 0041 | 726-01-00100 | Bedding Material | 100.6 | CUYD | 70.00 | 7,042.00 | 80.00 | 8,048.00 | 85.00 | 8,551.00 | 50.00 | 5,030.00 |
| 0042 | 727-01-00100 | Mobilization | 1 | LUMP | 435,000.00 | 435,000.00 | 400,000.00 | 400,000.00 | 490,000.00 | 490,000.00 | 200,000.00 | 200,000.00 |
| 0043 | 729-16-00300 | Object Marker Assembly (Type 3) | 12 | EACH | 75.00 | 900.00 | 85.00 | 1,020.00 | 110.00 | 1,320.00 | 82.50 | 990.00 |
| 0044 | 731-01-00100 | Nonreflectorized Raised Pavement Markers | 198 | EACH | 10.00 | 1,980.00 | 12.00 | 2,376.00 | 10.00 | 1,980.00 | 16.50 | 3,267.00 |
| 0045 | 731-02-00100 | Reflectorized Raised Pavement Markers | 146 | EACH | 5.25 | 766.50 | 6.20 | 905.20 | 5.50 | 803.00 | 5.50 | 803.00 |
| 0046 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 3.352 | MILE | 2,500.00 | 8,380.00 | 3,000.00 | 10,056.00 | 2,500.00 | 8,380.00 | 2,850.00 | 9,553.20 |
| 0047 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 80,000.00 | 80,000.00 | 60,000.00 | 60,000.00 | 75,000.00 | 75,000.00 |
| 0048 | 804-01-00200 | Precast Concrete Piles (14") | 120 | LNFT | 155.00 | 18,600.00 | 70.00 | 8,400.00 | 100.00 | 12,000.00 | 75.00 | 9,000.00 |
| 0049 | 804-01-00600 | Precast Concrete Piles (24") | 1,560 | LNFT | 165.00 | 257,400.00 | 95.00 | 148,200.00 | 120.00 | 187,200.00 | 150.00 | 234,000.00 |
| 0050 | 804-01-00800 | Precast Concrete Piles (36") | 1,170 | LNFT | 325.00 | 380,250.00 | 225.00 | 263,250.00 | 210.00 | 245,700.00 | 280.00 | 327,600.00 |
| 0051 | 804-12-00100 | Loading Permanent Piles | 1 | EACH | 5,500.00 | 5,500.00 | 500.00 | 500.00 | 1,000.00 | 1,000.00 | 500.00 | 500.00 |
| 0052 | 804-17-00100 | Dynamic Monitoring | 6 | EACH | 2,200.00 | 13,200.00 | 900.00 | 5,400.00 | 1,500.00 | 9,000.00 | 1,500.00 | 9,000.00 |
| 0053 | 805-01-00700 | Class A Concrete (Bents) | 139.65 | CUYD | 750.00 | 104,737.50 | 1,000.00 | 139,650.00 | 950.00 | 132,667.50 | 500.00 | 69,825.00 |
| 0054 | 805-04-00100 | Class AA(M) Concrete | 473.22 | CUYD | 540.00 | 255,538.80 | 700.00 | 331,254.00 | 650.00 | 307,593.00 | 550.00 | 260,271.00 |
| 0055 | 805-08-00400 | Precast-Prestressed Concrete Girder (Type IV) | 1,990 | LNFT | 160.00 | 318,400.00 | 138.00 | 274,620.00 | 150.00 | 298,500.00 | 175.00 | 348,250.00 |
| 0056 | 805-11-00100 | Strip Seal Joints | 120 | LNFT | 185.00 | 22,200.00 | 200.00 | 24,000.00 | 170.00 | 20,400.00 | 150.00 | 18,000.00 |
| 0057 | 806-01-00100 | Deformed Reinforcing Steel | 25,320 | LB | 1.00 | 25,320.00 | 0.88 | 22,281.60 | 0.80 | 20,256.00 | 0.85 | 21,522.00 |
| 0058 | 806-02-00100 | Deformed Reinforcing Steel (Epoxy Coated) | 132,514 | LB | 1.00 | 132,514.00 | 0.90 | 119,262.60 | 1.00 | 132,514.00 | 0.95 | 125,888.30 |
| 0059 | 807-08-00100 | Structural Metalwork | 1 | LUMP | 5,000.00 | 5,000.00 | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 | 5,000.00 | 5,000.00 |
| 0060 | 810-01-00100 | Concrete Railing (Standard Barrier) | 80 | LNFT | 85.00 | 6,800.00 | 85.00 | 6,800.00 | 60.00 | 4,800.00 | 60.00 | 4,800.00 |
| 0061 | 810-01-00200 | Concrete Railing (Slotted Barrier) | 800 | LNFT | 58.00 | 46,400.00 | 85.00 | 68,000.00 | 55.00 | 44,000.00 | 60.00 | 48,000.00 |
| 0062 | 813-01-00100 | Concrete Approach Slabs | 364.44 | SQYD | 205.00 | 74,710.20 | 235.00 | 85,643.40 | 200.00 | 72,888.00 | 250.00 | 91,110.00 |
| 0063 | NS-724-00002 | Rumble Strips (Shoulder Ground-In) | 1.424 | MILE | 550.00 | 783.20 | 5,000.00 | 7,120.00 | 2,500.00 | 3,560.00 | 7,000.00 | 9,968.00 |
| CONTRACTOR TOTAL | 4,485,890.60 | 4,499,798.56 | 4,941,202.02 | IRREGULAR | ||||||||