| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - R. E. HEIDT CONSTRUCTION CO., INC. |
- 2 - PRAIRIE CONTRACTORS INC. |
- 3 - BESSETTE DEVELOPMENT CORP. |
- 4 - GILCHRIST CONSTRUCTION CO. LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
3,510.00 |
3,510.00 |
1,000.00 |
1,000.00 |
500.00 |
500.00 |
8,000.00 |
8,000.00 |
| 202-02-E |
removal of concrete curbs
|
48.0 |
LNFT |
122.00 |
5,856.00 |
25.00 |
1,200.00 |
5.00 |
240.00 |
15.00 |
720.00 |
| 203-05 |
excavation and embankment
|
lump |
LUMP |
6,788.00 |
6,788.00 |
1,500.00 |
1,500.00 |
100.00 |
100.00 |
8,000.00 |
8,000.00 |
| 203-07 |
borrow (vehicular measurement)
|
345   |
CUYD |
17.00 |
5,865.00 |
25.00 |
8,625.00 |
21.00 |
7,245.00 |
24.00 |
8,280.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
4,580   |
CUYD |
64.00 |
293,120.00 |
59.00 |
270,220.00 |
70.00 |
320,600.00 |
60.00 |
274,800.00 |
| 502-01 |
superpave asphaltic concrete
|
15,830.1 |
TON |
87.00 |
1,377,218.70 |
84.00 |
1,329,728.40 |
87.65 |
1,387,508.27 |
82.00 |
1,298,068.20 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
3,330.8 |
TON |
84.00 |
279,787.20 |
114.00 |
379,711.20 |
139.70 |
465,312.76 |
126.00 |
419,680.80 |
| 509-01 |
cold planing asphaltic pavement
|
80,711   |
SQYD |
0.60 |
48,426.60 |
1.77 |
142,858.47 |
1.33 |
107,345.63 |
1.20 |
96,853.20 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 1,953   |
CUYD |
1.00 |
- 1,953.00 |
0.01 |
- 19.53 |
1.00 |
- 1,953.00 |
1.00 |
- 1,953.00 |
| 510-01-B |
pavement patching (12" minimum thickness)
|
768   |
SQYD |
83.00 |
63,744.00 |
102.00 |
78,336.00 |
74.30 |
57,062.40 |
120.00 |
92,160.00 |
| 510-02 |
pavement widening
|
169.3 |
SQYD |
170.00 |
28,781.00 |
111.00 |
18,792.30 |
86.65 |
14,669.85 |
80.00 |
13,544.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
6,405.00 |
6,405.00 |
30,000.00 |
30,000.00 |
6,100.00 |
6,100.00 |
25,000.00 |
25,000.00 |
| 713-02-E |
temporary pavement markings (24" width)
|
180   |
LNFT |
1.00 |
180.00 |
0.01 |
1.80 |
1.00 |
180.00 |
1.50 |
270.00 |
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
15.525 |
MILE |
295.00 |
4,579.88 |
400.00 |
6,210.00 |
323.50 |
5,022.34 |
400.00 |
6,210.00 |
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
15.525 |
MILE |
414.75 |
6,438.99 |
0.01 |
0.16 |
400.00 |
6,210.00 |
450.00 |
6,986.25 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
49.173 |
MILE |
535.50 |
26,332.14 |
0.01 |
0.49 |
600.00 |
29,503.80 |
400.00 |
19,669.20 |
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
2   |
EACH |
105.00 |
210.00 |
0.01 |
0.02 |
125.00 |
250.00 |
150.00 |
300.00 |
| 713-05-B |
temporary pavement legends and symbols (double arrow)
|
2   |
EACH |
131.25 |
262.50 |
0.01 |
0.02 |
135.00 |
270.00 |
150.00 |
300.00 |
| 713-05-D |
temporary pavement legends and symbols (rr crossing)
|
12   |
EACH |
210.00 |
2,520.00 |
0.01 |
0.12 |
200.00 |
2,400.00 |
225.00 |
2,700.00 |
| 713-05-F |
temporary pavement legends and symbols (yield line)
|
15   |
EACH |
105.00 |
1,575.00 |
0.01 |
0.15 |
175.00 |
2,625.00 |
200.00 |
3,000.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
75,000.00 |
75,000.00 |
65,000.00 |
65,000.00 |
39,000.00 |
39,000.00 |
250,000.00 |
250,000.00 |
| 729-16-B |
object marker assembly (type 2)
|
44   |
EACH |
52.50 |
2,310.00 |
60.00 |
2,640.00 |
50.00 |
2,200.00 |
60.00 |
2,640.00 |
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
78.75 |
315.00 |
100.00 |
400.00 |
75.00 |
300.00 |
85.00 |
340.00 |
| 731-02 |
reflectorized raised pavement markers
|
1,045   |
EACH |
5.36 |
5,601.20 |
6.00 |
6,270.00 |
5.25 |
5,486.25 |
5.50 |
5,747.50 |
| 732-01-E |
plastic pavement striping (24" width)
|
222   |
LNFT |
4.10 |
910.20 |
5.00 |
1,110.00 |
4.00 |
888.00 |
4.50 |
999.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
18.280 |
MILE |
2,992.50 |
54,702.90 |
2,300.00 |
42,044.00 |
2,200.00 |
40,216.00 |
2,500.00 |
45,700.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
6.085 |
MILE |
745.50 |
4,536.37 |
900.00 |
5,476.50 |
850.00 |
5,172.25 |
950.00 |
5,780.75 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
12   |
EACH |
204.75 |
2,457.00 |
200.00 |
2,400.00 |
185.00 |
2,220.00 |
200.00 |
2,400.00 |
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
1   |
EACH |
236.25 |
236.25 |
200.00 |
200.00 |
200.00 |
200.00 |
220.00 |
220.00 |
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
4   |
EACH |
430.50 |
1,722.00 |
350.00 |
1,400.00 |
350.00 |
1,400.00 |
380.00 |
1,520.00 |
| 732-04-F |
plastic pavement legends & symbols (yield line)
|
10   |
EACH |
210.00 |
2,100.00 |
250.00 |
2,500.00 |
220.00 |
2,200.00 |
250.00 |
2,500.00 |
| 732-05 |
removal of existing markings
|
1.645 |
MILE |
5,985.00 |
9,845.33 |
5,000.00 |
8,225.00 |
5,000.00 |
8,225.00 |
5,700.00 |
9,376.50 |
| 735-01 |
mailboxes
|
77   |
EACH |
1.05 |
80.85 |
5.00 |
385.00 |
1.00 |
77.00 |
10.00 |
770.00 |
| 735-02 |
mailbox supports (single)
|
61   |
EACH |
105.00 |
6,405.00 |
125.00 |
7,625.00 |
100.00 |
6,100.00 |
115.00 |
7,015.00 |
| 735-03 |
mailbox supports (double)
|
17   |
EACH |
131.25 |
2,231.25 |
150.00 |
2,550.00 |
125.00 |
2,125.00 |
140.00 |
2,380.00 |
| 735-04 |
mailbox supports (multiple)
|
1   |
EACH |
210.00 |
210.00 |
300.00 |
300.00 |
200.00 |
200.00 |
225.00 |
225.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
7,000.00 |
7,000.00 |
100.00 |
100.00 |
4,000.00 |
4,000.00 |
15,000.00 |
15,000.00 |
| S-101 |
video detection camera and traffic signal interface
appurtenances |
4   |
EACH |
5,985.00 |
23,940.00 |
6,000.00 |
24,000.00 |
5,700.00 |
22,800.00 |
12,000.00 |
48,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,359,250.36 |
|
2,440,790.10 |
|
2,554,001.55 |
|
2,683,202.40 |
|