| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - JAMES CONSTRUCTION GROUP LLC |
- 2 - SHAVERS-WHITTLE CONSTRUCTION INC |
- 3 - CYCLE CONSTRUCTION CO. L.L.C. |
- 4 - FLEMING CONSTRUCTION CO., INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
5,275.00 |
5,275.00 |
3,500.00 |
3,500.00 |
1,200.00 |
1,200.00 |
35,000.00 |
35,000.00 |
| 202-02-A-01 |
removal of bridge(sta.100+18.19;27.1'w x 57' l
concrete structure on wooden piling w/sidewalk) |
1   |
EACH |
50,000.00 |
50,000.00 |
45,000.00 |
45,000.00 |
44,000.00 |
44,000.00 |
80,000.00 |
80,000.00 |
| 202-02-C |
removal of portland cement concrete pavement
|
224   |
SQYD |
77.00 |
17,248.00 |
95.00 |
21,280.00 |
15.00 |
3,360.00 |
80.00 |
17,920.00 |
| 203-05 |
excavation and embankment
|
lump |
LUMP |
10,000.00 |
10,000.00 |
38,000.00 |
38,000.00 |
25,000.00 |
25,000.00 |
40,000.00 |
40,000.00 |
| 701-03-J |
storm drain pipe ( 27" cmp)(outfall)
|
22   |
LNFT |
640.00 |
14,080.00 |
185.00 |
4,070.00 |
200.00 |
4,400.00 |
350.00 |
7,700.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
5,000.00 |
5,000.00 |
20,000.00 |
20,000.00 |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
| 716-01-A |
mulch (vegetative)
|
0.4 |
TON |
600.00 |
240.00 |
650.00 |
260.00 |
500.00 |
200.00 |
1,800.00 |
720.00 |
| 717-01 |
seeding
|
6   |
LB |
6.00 |
36.00 |
12.00 |
72.00 |
60.00 |
360.00 |
60.00 |
360.00 |
| 718-01 |
fertilizer
|
200   |
LB |
0.25 |
50.00 |
1.25 |
250.00 |
1.00 |
200.00 |
3.00 |
600.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
80,000.00 |
80,000.00 |
125,000.00 |
125,000.00 |
411,000.00 |
411,000.00 |
350,000.00 |
350,000.00 |
| 729-16-C |
object marker assembly (type 3)
|
8   |
EACH |
600.00 |
4,800.00 |
95.00 |
760.00 |
86.00 |
688.00 |
145.00 |
1,160.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
10,000.00 |
10,000.00 |
8,000.00 |
8,000.00 |
| 803-03 |
steel sheet pile wall
|
6,966   |
SQFT |
65.00 |
452,790.00 |
53.00 |
369,198.00 |
60.00 |
417,960.00 |
70.00 |
487,620.00 |
| 804-01-D |
precast concrete piles (18")
|
2,218   |
LNFT |
75.00 |
166,350.00 |
146.00 |
323,828.00 |
92.00 |
204,056.00 |
185.00 |
410,330.00 |
| 804-12 |
loading permanent piles
|
1   |
EACH |
50,000.00 |
50,000.00 |
2,500.00 |
2,500.00 |
1,800.00 |
1,800.00 |
110,000.00 |
110,000.00 |
| 805-10-A |
bridge superstructure & substructure(minimum 28'clear
roadway @ 90 degree with special end bents,cast-in-place) |
3   |
SPAN |
50,000.00 |
150,000.00 |
107,500.00 |
322,500.00 |
190,000.00 |
570,000.00 |
85,000.00 |
255,000.00 |
| S-001 |
saw cutting concrete pavement (full depth)
|
115   |
lf |
8.80 |
1,012.00 |
18.00 |
2,070.00 |
15.00 |
1,725.00 |
20.00 |
2,300.00 |
| S-101 |
vibration monitoring
|
lump |
LUMP |
5,000.00 |
5,000.00 |
14,000.00 |
14,000.00 |
18,000.00 |
18,000.00 |
8,000.00 |
8,000.00 |
| S-102 |
concrete approach slab(28' clear roadway,with tapered
concrete barrier railing @ 90 degree crossing(west side) |
1   |
EACH |
50,000.00 |
50,000.00 |
60,000.00 |
60,000.00 |
90,000.00 |
90,000.00 |
104,000.00 |
104,000.00 |
| S-103 |
concrete approach slab(28' clear roadway,with tapered
concrete barrier railing @ 90 degree crossing(east side) |
1   |
EACH |
45,000.00 |
45,000.00 |
50,000.00 |
50,000.00 |
85,000.00 |
85,000.00 |
104,000.00 |
104,000.00 |
| |
crossing(east side) |
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,116,881.00 |
|
1,427,288.00 |
|
1,898,949.00 |
|
2,047,710.00 |
|