Letting of 12/10/2008 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 713-17-0041
Parish: E BATON ROUGE
Routes:
Description: OLD BAKER ROAD BRIDGE OVER DRAINAGE BAYOU
Type Const: grading, drainage structures, class ii base course, superpav e asphaltic concrete,
and related work.
Estimated Construction Cost: $270,707.00
 
RankLicenseBidderConstruction Bid
1 25088 RCS CONTRACTORS, INC. $199,404.28
2 27634 PHYLWAY CONSTRUCTION LLC $216,004.00
3 12198 BYRON E. TALBOT CONTRACTOR, INC. $234,554.24
4 02109 CHAMBERS CONSTRUCTION CO., INC. $249,687.00
5 06276 BARRIERE CONSTRUCTION CO., LLC. $277,541.50
6 09090 GUINN BROTHERS, LLC. $280,508.00
7 32044 QUALITY DESIGN & CONSTRUCTION, LLC. $295,609.60
8 02179 BOH BROS. CONSTRUCTION CO., LLC. $338,258.55
 
Item Number Item Description Quantity Unit of Measure - 1 -
RCS CONTRACTORS, INC.
- 2 -
PHYLWAY CONSTRUCTION LLC
- 3 -
BYRON E. TALBOT CONTRACTOR, INC.
- 4 -
CHAMBERS CONSTRUCTION CO., INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 1,000.00 1,000.00 2,000.00 2,000.00 5,500.00 5,500.00 4,230.00 4,230.00
202-02-A-01 removal of bridge(25' wide x 39.4' long) 1      EACH 17,850.00 17,850.00 15,000.00 15,000.00 15,000.00 15,000.00 7,600.00 7,600.00
202-02-G removal of surfacing & stabilized base 162.6    SQYD 5.50 894.30 20.00 3,252.00 11.15 1,812.99 25.10 4,081.26
203-05 excavation and embankment lump      LUMP 11,000.00 11,000.00 28,000.00 28,000.00 10,000.00 10,000.00 20,560.00 20,560.00
204-02 temporary hay or straw bales 3      EACH 22.00 66.00 12.00 36.00 25.00 75.00 140.00 420.00
204-05-A temporary sediment check dams (hay) 4      EACH 220.00 880.00 120.00 480.00 150.00 600.00 346.00 1,384.00
204-06 temporary silt fencing 200      LNFT 3.30 660.00 4.00 800.00 5.00 1,000.00 4.00 800.00
302-01 class ii base course 61.5    CUYD 198.00 12,177.00 150.00 9,225.00 90.00 5,535.00 183.40 11,279.10
401-02 aggregate surface course (adjusted vehicular
measurement)
16      CUYD 198.00 3,168.00 125.00 2,000.00 60.00 960.00 131.00 2,096.00
502-01 superpave asphaltic concrete 48.1    TON 250.00 12,025.00 200.00 9,620.00 500.00 24,050.00 334.00 16,065.40
701-05-I side drain pipe (24") 112      LNFT 35.06 3,926.72 54.00 6,048.00 47.25 5,292.00 90.00 10,080.00
701-05-K side drain pipe (30") 40      LNFT 40.02 1,600.80 80.00 3,200.00 56.00 2,240.00 117.00 4,680.00
705-01 barbed wire fence 80      LNFT 17.49 1,399.20 20.00 1,600.00 17.50 1,400.00 13.00 1,040.00
713-01 temporary signs & barricades lump      LUMP 10,000.00 10,000.00 8,000.00 8,000.00 17,000.00 17,000.00 9,500.00 9,500.00
716-01-A mulch (vegetative) 0.12   TON 5,500.00 660.00 4,000.00 480.00 5,500.00 660.00 4,580.00 549.60
717-01 seeding 3      LB 110.00 330.00 100.00 300.00 110.00 330.00 52.00 156.00
718-01 fertilizer 60      LB 5.50 330.00 4.00 240.00 5.50 330.00 7.10 426.00
726-01 bedding material 55.5    CUYD 65.00 3,607.50 150.00 8,325.00 100.00 5,550.00 71.00 3,940.50
727-01 mobilization lump      LUMP 9,500.00 9,500.00 10,000.00 10,000.00 23,000.00 23,000.00 14,970.00 14,970.00
729-16-B object marker assembly (type 2) 4      EACH 100.00 400.00 75.00 300.00 100.00 400.00 177.00 708.00
731-02 reflectorized raised pavement markers 4      EACH 56.00 224.00 55.00 220.00 5.75 23.00 32.50 130.00
732-02-A plastic pavement striping (solid line) (4" width) 0.077  MILE 31,900.00 2,456.30 30,000.00 2,310.00 2,650.00 204.05 42,200.00 3,249.40
740-01 construction layout lump      LUMP 5,000.00 5,000.00 6,000.00 6,000.00 5,600.00 5,600.00 4,700.00 4,700.00
805-01-B class a concrete (box culvert headwalls) 19.10   CUYD 1,570.00 29,987.00 1,400.00 26,740.00 1,240.00 23,684.00 1,475.00 28,172.50
805-12-I reinforced concrete box culverts (5'x 5') 156.0    LNFT 435.38 67,919.28 440.00 68,640.00 496.50 77,454.00 613.75 95,745.00
806-01 deformed reinforcing steel 1,594      LB 1.47 2,343.18 2.00 3,188.00 4.30 6,854.20 1.96 3,124.24
                       
 CONTRACTOR TOTAL       199,404.28   216,004.00   234,554.24   249,687.00
 
Item Number Item Description Quantity Unit of Measure - 5 -
BARRIERE CONSTRUCTION CO., LLC.
- 6 -
GUINN BROTHERS, LLC.
- 7 -
QUALITY DESIGN & CONSTRUCTION, LLC.
- 8 -
BOH BROS. CONSTRUCTION CO., LLC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 10,250.00 10,250.00 10,000.00 10,000.00 9,400.00 9,400.00 6,000.00 6,000.00
202-02-A-01 removal of bridge(25' wide x 39.4' long) 1      EACH 19,000.00 19,000.00 23,000.00 23,000.00 8,900.00 8,900.00 4,930.00 4,930.00
202-02-G removal of surfacing & stabilized base 162.6    SQYD 19.00 3,089.40 10.00 1,626.00 18.00 2,926.80 20.00 3,252.00
203-05 excavation and embankment lump      LUMP 27,850.00 27,850.00 15,000.00 15,000.00 47,600.00 47,600.00 29,500.00 29,500.00
204-02 temporary hay or straw bales 3      EACH 23.00 69.00 10.00 30.00 14.00 42.00 30.00 90.00
204-05-A temporary sediment check dams (hay) 4      EACH 231.00 924.00 100.00 400.00 220.00 880.00 280.00 1,120.00
204-06 temporary silt fencing 200      LNFT 3.50 700.00 3.00 600.00 2.00 400.00 3.40 680.00
302-01 class ii base course 61.5    CUYD 173.00 10,639.50 100.00 6,150.00 133.00 8,179.50 141.00 8,671.50
401-02 aggregate surface course (adjusted vehicular
measurement)
16      CUYD 100.00 1,600.00 100.00 1,600.00 108.00 1,728.00 141.00 2,256.00
502-01 superpave asphaltic concrete 48.1    TON 350.00 16,835.00 500.00 24,050.00 224.00 10,774.40 225.00 10,822.50
701-05-I side drain pipe (24") 112      LNFT 65.00 7,280.00 112.00 12,544.00 45.00 5,040.00 76.50 8,568.00
701-05-K side drain pipe (30") 40      LNFT 85.00 3,400.00 160.00 6,400.00 59.00 2,360.00 104.90 4,196.00
705-01 barbed wire fence 80      LNFT 18.00 1,440.00 15.00 1,200.00 25.00 2,000.00 17.90 1,432.00
713-01 temporary signs & barricades lump      LUMP 22,000.00 22,000.00 17,500.00 17,500.00 11,100.00 11,100.00 5,600.00 5,600.00
716-01-A mulch (vegetative) 0.12   TON 9,000.00 1,080.00 4,000.00 480.00 8,200.00 984.00 4,700.00 564.00
717-01 seeding 3      LB 116.00 348.00 100.00 300.00 10.50 31.50 28.00 84.00
718-01 fertilizer 60      LB 6.00 360.00 10.00 600.00 3.20 192.00 1.12 67.20
726-01 bedding material 55.5    CUYD 72.00 3,996.00 100.00 5,550.00 140.00 7,770.00 87.10 4,834.05
727-01 mobilization lump      LUMP 28,700.00 28,700.00 31,500.00 31,500.00 29,200.00 29,200.00 48,600.00 48,600.00
729-16-B object marker assembly (type 2) 4      EACH 37.00 148.00 100.00 400.00 95.00 380.00 90.00 360.00
731-02 reflectorized raised pavement markers 4      EACH 59.00 236.00 100.00 400.00 116.00 464.00 56.00 224.00
732-02-A plastic pavement striping (solid line) (4" width) 0.077  MILE 34,000.00 2,618.00 40,000.00 3,080.00 15,000.00 1,155.00 32,500.00 2,502.50
740-01 construction layout lump      LUMP 8,000.00 8,000.00 5,000.00 5,000.00 14,300.00 14,300.00 14,430.00 14,430.00
805-01-B class a concrete (box culvert headwalls) 19.10   CUYD 1,226.00 23,416.60 1,600.00 30,560.00 1,310.00 25,021.00 1,772.00 33,845.20
805-12-I reinforced concrete box culverts (5'x 5') 156.0    LNFT 505.00 78,780.00 478.00 74,568.00 640.00 99,840.00 909.00 141,804.00
806-01 deformed reinforcing steel 1,594      LB 3.00 4,782.00 5.00 7,970.00 3.10 4,941.40 2.40 3,825.60
                       
 CONTRACTOR TOTAL       277,541.50   280,508.00   295,609.60   338,258.55