Letting of 12/10/2008 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 308-07-0011
Parish: LINCOLN
Routes: LA 545
Description: LA 151 TO LA 146
Type Const: grading, superpave asphaltic concrete pavement and related work.
Estimated Construction Cost: $1,141,597.13
 
RankLicenseBidderConstruction Bid
1 08584 MADDEN CONTRACTING CO., INC. $835,524.53
 
Item Number Item Description Quantity Unit of Measure - 1 -
MADDEN CONTRACTING CO., INC.

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      LUMP 2,500.00 2,500.00            
202-02-D removal of concrete walks & drives 61      SQYD 10.00 610.00            
203-07 borrow (vehicular measurement) 2,500      CUYD 10.00 25,000.00            
203-07-A borrow (vehicular meas.)(selected soils) 1,966      CUYD 10.00 19,660.00            
308-01-A in-place cement treated base course (12" thick) 25,505      SQYD 8.30 211,691.50            
308-02 removal of existing patches 100      SQYD 1.00 100.00            
401-02 aggregate surface course (adjusted vehicular
measurement)
32      CUYD 50.00 1,600.00            
402-01 traffic maintenance aggregate (vehicular measurement) 479.1    CUYD 1.00 479.10            
502-01 superpave asphaltic concrete 2,805.6    TON 108.50 304,407.60            
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
148.1    TON 65.00 9,626.50            
507-01-A asphaltic material (crs-2p emulsion) 7,907      GAL 3.00 23,721.00            
507-02-C aggregate (s3) 25,505      SQYD 3.50 89,267.50            
706-02-C concrete drive (6" thick) 51.3    SQYD 75.00 3,847.50            
713-01 temporary signs & barricades lump      LUMP 40,500.00 40,500.00            
713-03-A temporary pavement markings (broken line)(4" width)(4'
length)
1.790  MILE 400.00 716.00            
713-03-B temporary pavement markings (broken line)(4" width)
(10' length)
3.580  MILE 1.00 3.58            
713-04-A temporary pavement markings (solid line)(4" width) 14.348  MILE 1.00 14.35            
713-06-A temporary reflectorized raised pavement markers (tabs) 474      EACH 1.85 876.90            
716-01-A mulch (vegetative) 7.0    TON 600.00 4,200.00            
717-01 seeding 209      LB 8.00 1,672.00            
718-01 fertilizer 3,480      LB 1.00 3,480.00            
727-01 mobilization lump      LUMP 40,500.00 40,500.00            
729-16-B object marker assembly (type 2) 3      EACH 100.00 300.00            
731-02 reflectorized raised pavement markers 238      EACH 5.00 1,190.00            
732-02-A plastic pavement striping (solid line) (4" width) 7.174  MILE 2,500.00 17,935.00            
732-03-A plastic pavement striping (broken line)(4" width) 0.900  MILE 600.00 540.00            
735-01 mailboxes 6      EACH 1.00 6.00            
735-02 mailbox supports (single) 4      EACH 250.00 1,000.00            
735-03 mailbox supports (double) 1      EACH 250.00 250.00            
740-01 construction layout lump      LUMP 14,500.00 14,500.00            
S-001 tree trimming lump      LUMP 15,000.00 15,000.00            
S-002 saw cutting concrete drives (6"depth) 22      LNFT 15.00 330.00            
                       
 CONTRACTOR TOTAL       835,524.53            