| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GILCHRIST CONSTRUCTION CO. LLC |
- 2 - D & J CONSTRUCTION CO., INC. |
- 3 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
35,000.00 |
35,000.00 |
5,000.00 |
5,000.00 |
2,500.00 |
2,500.00 |
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
5,000.00 |
5,000.00 |
2,000.00 |
2,000.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-D |
removal of concrete walks & drives
|
27   |
SQYD |
15.00 |
405.00 |
25.00 |
675.00 |
21.00 |
567.00 |
|
|
| 202-02-H |
removal of guard rail
|
106   |
LNFT |
16.00 |
1,696.00 |
15.00 |
1,590.00 |
18.00 |
1,908.00 |
|
|
| 202-02-I |
removal of surfacing and stone base
|
5,533   |
SQYD |
4.50 |
24,898.50 |
6.50 |
35,964.50 |
4.00 |
22,132.00 |
|
|
| 203-07 |
borrow (vehicular measurement)
|
5,556   |
CUYD |
11.00 |
61,116.00 |
14.00 |
77,784.00 |
15.00 |
83,340.00 |
|
|
| 203-07-A |
borrow (vehicular meas.)(selected soils)
|
2,027   |
CUYD |
16.00 |
32,432.00 |
11.00 |
22,297.00 |
15.00 |
30,405.00 |
|
|
| 204-06 |
temporary silt fencing
|
4,000   |
LNFT |
2.00 |
8,000.00 |
3.00 |
12,000.00 |
8.00 |
32,000.00 |
|
|
| 302-01 |
class ii base course (stone only)
|
200.0 |
CUYD |
100.00 |
20,000.00 |
50.00 |
10,000.00 |
200.00 |
40,000.00 |
|
|
| 304-05 |
lime treatment (type e)
|
1,566.15 |
TON |
100.00 |
156,615.00 |
268.00 |
419,728.20 |
325.00 |
508,998.75 |
|
|
| 308-01-A |
in-place cement treated base course (12" thick)
|
134,522   |
SQYD |
6.00 |
807,132.00 |
6.80 |
914,749.60 |
9.00 |
1,210,698.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
225   |
CUYD |
90.00 |
20,250.00 |
50.00 |
11,250.00 |
55.00 |
12,375.00 |
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
507.0 |
CUYD |
50.00 |
25,350.00 |
6.00 |
3,042.00 |
7.00 |
3,549.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
25,890.2 |
TON |
92.00 |
2,381,898.40 |
98.00 |
2,537,239.60 |
88.00 |
2,278,337.60 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
1,104.4 |
TON |
170.00 |
187,748.00 |
98.00 |
108,231.20 |
170.00 |
187,748.00 |
|
|
| 507-01-A |
asphaltic material (crs-2p emulsion)
|
41,702   |
GAL |
5.25 |
218,935.50 |
4.05 |
168,893.10 |
5.00 |
208,510.00 |
|
|
| 507-02-C |
aggregate (s3)
|
134,522   |
SQYD |
1.30 |
174,878.60 |
1.00 |
134,522.00 |
1.10 |
147,974.20 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
119,276   |
SQYD |
0.80 |
95,420.80 |
0.95 |
113,312.20 |
1.75 |
208,733.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 4,976   |
CUYD |
1.00 |
- 4,976.00 |
0.10 |
- 497.60 |
0.10 |
- 497.60 |
|
|
| 701-12-I |
corrugated metal pipe (extension)(24")
|
24   |
LNFT |
300.00 |
7,200.00 |
200.00 |
4,800.00 |
155.00 |
3,720.00 |
|
|
| 701-13-I |
corrugated metal pipe arch (extension)(54" equiv.)
|
8   |
LNFT |
470.00 |
3,760.00 |
225.00 |
1,800.00 |
230.00 |
1,840.00 |
|
|
| 701-15 |
concrete collar
|
4   |
EACH |
1,500.00 |
6,000.00 |
1,000.00 |
4,000.00 |
950.00 |
3,800.00 |
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
25.0 |
LNFT |
80.00 |
2,000.00 |
72.00 |
1,800.00 |
75.00 |
1,875.00 |
|
|
| 704-03 |
blocked out guard rail
|
160.5 |
LNFT |
25.00 |
4,012.50 |
23.00 |
3,691.50 |
23.00 |
3,691.50 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
100.0 |
LNFT |
40.00 |
4,000.00 |
35.00 |
3,500.00 |
37.00 |
3,700.00 |
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
4   |
EACH |
2,800.00 |
11,200.00 |
2,500.00 |
10,000.00 |
2,500.00 |
10,000.00 |
|
|
| 706-02-C |
concrete drive (6" thick)
|
14.9 |
SQYD |
200.00 |
2,980.00 |
80.00 |
1,192.00 |
80.00 |
1,192.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
70,000.00 |
70,000.00 |
25,000.00 |
25,000.00 |
35,000.00 |
35,000.00 |
|
|
| 713-02-C |
temporary pavement markings (8" width)
|
225   |
LNFT |
1.00 |
225.00 |
1.50 |
337.50 |
0.34 |
76.50 |
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
777   |
LNFT |
2.00 |
1,554.00 |
2.00 |
1,554.00 |
1.00 |
777.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
25.050 |
MILE |
400.00 |
10,020.00 |
225.00 |
5,636.25 |
150.00 |
3,757.50 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
12.015 |
MILE |
400.00 |
4,806.00 |
200.00 |
2,403.00 |
300.00 |
3,604.50 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
84.420 |
MILE |
400.00 |
33,768.00 |
1.00 |
84.42 |
300.00 |
25,326.00 |
|
|
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
3   |
EACH |
200.00 |
600.00 |
100.00 |
300.00 |
55.00 |
165.00 |
|
|
| 713-05-C |
temporary pavement legends and symbols (only)
|
3   |
EACH |
200.00 |
600.00 |
200.00 |
600.00 |
55.00 |
165.00 |
|
|
| 716-01-A |
mulch (vegetative)
|
32.0 |
TON |
440.00 |
14,080.00 |
400.00 |
12,800.00 |
400.00 |
12,800.00 |
|
|
| 717-01 |
seeding
|
966   |
LB |
8.25 |
7,969.50 |
8.00 |
7,728.00 |
7.50 |
7,245.00 |
|
|
| 718-01 |
fertilizer
|
16,000   |
LB |
0.50 |
8,000.00 |
0.40 |
6,400.00 |
0.40 |
6,400.00 |
|
|
| 726-01 |
bedding material
|
17.6 |
CUYD |
115.00 |
2,024.00 |
100.00 |
1,760.00 |
110.00 |
1,936.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
330,000.00 |
330,000.00 |
105,000.00 |
105,000.00 |
255,000.00 |
255,000.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
6   |
EACH |
75.00 |
450.00 |
100.00 |
600.00 |
70.00 |
420.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
4   |
EACH |
85.00 |
340.00 |
100.00 |
400.00 |
80.00 |
320.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
1,374   |
EACH |
6.50 |
8,931.00 |
6.00 |
8,244.00 |
5.50 |
7,557.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
75   |
LNFT |
1.50 |
112.50 |
6.00 |
450.00 |
1.00 |
75.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
259   |
LNFT |
5.30 |
1,372.70 |
8.00 |
2,072.00 |
3.25 |
841.75 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
11.440 |
MILE |
2,800.00 |
32,032.00 |
2,700.00 |
30,888.00 |
2,750.00 |
31,460.00 |
|
|
| 732-02-B |
plastic pavement striping (solid line) (6" width)
|
16.770 |
MILE |
3,700.00 |
62,049.00 |
3,500.00 |
58,695.00 |
3,750.00 |
62,887.50 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.005 |
MILE |
1,100.00 |
4,405.50 |
1,100.00 |
4,405.50 |
650.00 |
2,603.25 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
1   |
EACH |
235.00 |
235.00 |
500.00 |
500.00 |
275.00 |
275.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
235.00 |
235.00 |
700.00 |
700.00 |
275.00 |
275.00 |
|
|
| 735-01 |
mailboxes
|
11   |
EACH |
10.00 |
110.00 |
25.00 |
275.00 |
1.00 |
11.00 |
|
|
| 735-02 |
mailbox supports (single)
|
7   |
EACH |
200.00 |
1,400.00 |
175.00 |
1,225.00 |
165.00 |
1,155.00 |
|
|
| 735-03 |
mailbox supports (double)
|
2   |
EACH |
220.00 |
440.00 |
200.00 |
400.00 |
185.00 |
370.00 |
|
|
| 736-09 |
loop detector
|
447   |
LNFT |
33.00 |
14,751.00 |
15.00 |
6,705.00 |
13.00 |
5,811.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
25,000.00 |
25,000.00 |
20,000.00 |
20,000.00 |
22,500.00 |
22,500.00 |
|
|
| S-001 |
tree trimming
|
lump |
LUMP |
20,000.00 |
20,000.00 |
44,000.00 |
44,000.00 |
40,000.00 |
40,000.00 |
|
|
| S-002 |
cleaning existing ditches
|
200   |
LNFT |
9.50 |
1,900.00 |
15.00 |
3,000.00 |
10.00 |
2,000.00 |
|
|
| S-003 |
rumble strips (ground-in)
|
16.7 |
MILE |
595.00 |
9,936.50 |
850.00 |
14,195.00 |
900.00 |
15,030.00 |
|
|
| S-004 |
saw cutting concrete drives (6" depth)
|
27   |
LNFT |
30.00 |
810.00 |
9.00 |
243.00 |
9.00 |
243.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
4,961,109.00 |
|
4,975,164.97 |
|
5,560,183.45 |
|
|
|