| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - SPECIALTY CONTRACTORS |
- 2 - F. J. BURNELL, INC. |
- 3 - GILCHRIST CONSTRUCTION CO. LLC |
- 4 - S.F.C. CONTRACT SERVICES, INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
100,000.00 |
100,000.00 |
66,000.00 |
66,000.00 |
80,000.00 |
80,000.00 |
55,000.00 |
55,000.00 |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
6,000.00 |
6,000.00 |
20,000.00 |
20,000.00 |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
| 202-02-D |
removal of concrete walks & drives
|
36   |
SQYD |
10.00 |
360.00 |
15.00 |
540.00 |
15.00 |
540.00 |
22.00 |
792.00 |
| 202-02-G |
removal of surfacing & stabilized base
|
6,037.8 |
SQYD |
2.00 |
12,075.60 |
4.00 |
24,151.20 |
4.50 |
27,170.10 |
7.00 |
42,264.60 |
| 203-01 |
general excavation
|
20,474   |
CUYD |
1.85 |
37,876.90 |
4.00 |
81,896.00 |
5.00 |
102,370.00 |
3.50 |
71,659.00 |
| 203-03 |
embankment
|
42,911   |
CUYD |
6.00 |
257,466.00 |
9.00 |
386,199.00 |
9.50 |
407,654.50 |
8.00 |
343,288.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
45   |
EACH |
100.00 |
4,500.00 |
100.00 |
4,500.00 |
200.00 |
9,000.00 |
186.00 |
8,370.00 |
| 204-06 |
temporary silt fencing
|
2,420   |
LNFT |
2.00 |
4,840.00 |
2.00 |
4,840.00 |
2.00 |
4,840.00 |
3.00 |
7,260.00 |
| 302-02-D |
class ii base course (8 1/2" thick)
|
15,284.8 |
SQYD |
10.19 |
155,752.11 |
10.75 |
164,311.60 |
11.00 |
168,132.80 |
19.00 |
290,411.20 |
| 304-05 |
lime treatment (type e)
|
21.67 |
TON |
369.00 |
7,996.23 |
200.00 |
4,334.00 |
350.00 |
7,584.50 |
460.00 |
9,968.20 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
59   |
CUYD |
80.00 |
4,720.00 |
90.00 |
5,310.00 |
100.00 |
5,900.00 |
109.00 |
6,431.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
500.0 |
CUYD |
30.00 |
15,000.00 |
10.00 |
5,000.00 |
73.00 |
36,500.00 |
85.00 |
42,500.00 |
| 502-01 |
superpave asphaltic concrete
|
3,177.4 |
TON |
115.00 |
365,401.00 |
130.00 |
413,062.00 |
96.00 |
305,030.40 |
116.00 |
368,578.40 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
297.0 |
TON |
165.00 |
49,005.00 |
185.00 |
54,945.00 |
160.00 |
47,520.00 |
165.00 |
49,005.00 |
| 701-01-I |
cross drain pipe (24" rcp/pcp)
|
112   |
LNFT |
58.00 |
6,496.00 |
65.00 |
7,280.00 |
100.00 |
11,200.00 |
100.00 |
11,200.00 |
| 701-01-M |
cross drain pipe (36" rcp/pcp)
|
168   |
LNFT |
106.00 |
17,808.00 |
100.00 |
16,800.00 |
150.00 |
25,200.00 |
143.00 |
24,024.00 |
| 701-05-G |
side drain pipe (18")
|
168   |
LNFT |
36.00 |
6,048.00 |
45.00 |
7,560.00 |
55.00 |
9,240.00 |
60.00 |
10,080.00 |
| 706-02-C |
concrete drive (6" thick)
|
295.1 |
SQYD |
48.00 |
14,164.80 |
67.00 |
19,771.70 |
115.00 |
33,936.50 |
77.00 |
22,722.70 |
| 708-01 |
right-of-way monument
|
24   |
EACH |
100.00 |
2,400.00 |
160.00 |
3,840.00 |
400.00 |
9,600.00 |
180.00 |
4,320.00 |
| 708-02 |
right-of-way monument witness post
|
24   |
EACH |
100.00 |
2,400.00 |
55.00 |
1,320.00 |
400.00 |
9,600.00 |
90.00 |
2,160.00 |
| 711-01-D |
riprap (55 lb, 18" thick)
|
600   |
SQYD |
58.00 |
34,800.00 |
45.00 |
27,000.00 |
62.00 |
37,200.00 |
55.00 |
33,000.00 |
| 711-04 |
geotextile fabric
|
600   |
SQYD |
3.00 |
1,800.00 |
2.00 |
1,200.00 |
2.80 |
1,680.00 |
3.40 |
2,040.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
10,000.00 |
10,000.00 |
17,000.00 |
17,000.00 |
25,000.00 |
25,000.00 |
28,000.00 |
28,000.00 |
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
1.220 |
MILE |
300.00 |
366.00 |
500.00 |
610.00 |
350.00 |
427.00 |
600.00 |
732.00 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
5.464 |
MILE |
700.00 |
3,824.80 |
225.00 |
1,229.40 |
250.00 |
1,366.00 |
1,100.00 |
6,010.40 |
| 716-01-A |
mulch (vegetative)
|
13.0 |
TON |
800.00 |
10,400.00 |
500.00 |
6,500.00 |
450.00 |
5,850.00 |
600.00 |
7,800.00 |
| 717-01 |
seeding
|
1,040   |
LB |
9.00 |
9,360.00 |
8.50 |
8,840.00 |
8.50 |
8,840.00 |
10.00 |
10,400.00 |
| 718-01 |
fertilizer
|
13,000   |
LB |
0.90 |
11,700.00 |
0.50 |
6,500.00 |
0.50 |
6,500.00 |
0.75 |
9,750.00 |
| 720-01-A |
erosion control system, slope protection (type a)
|
9,950   |
SQYD |
2.00 |
19,900.00 |
1.50 |
14,925.00 |
1.50 |
14,925.00 |
1.50 |
14,925.00 |
| 722-01 |
project site laboratory
|
1   |
EACH |
4,000.00 |
4,000.00 |
10,000.00 |
10,000.00 |
8,000.00 |
8,000.00 |
10,000.00 |
10,000.00 |
| 726-01 |
bedding material
|
118.6 |
CUYD |
80.00 |
9,488.00 |
80.00 |
9,488.00 |
115.00 |
13,639.00 |
78.00 |
9,250.80 |
| 727-01 |
mobilization
|
lump |
LUMP |
48,000.00 |
48,000.00 |
80,000.00 |
80,000.00 |
140,000.00 |
140,000.00 |
175,000.00 |
175,000.00 |
| 729-16-B |
object marker assembly (type 2)
|
4   |
EACH |
100.00 |
400.00 |
110.00 |
440.00 |
85.00 |
340.00 |
620.00 |
2,480.00 |
| 729-19-A |
dead end road installations(type a)
|
1   |
EACH |
5,000.00 |
5,000.00 |
2,000.00 |
2,000.00 |
2,500.00 |
2,500.00 |
2,160.00 |
2,160.00 |
| 731-02 |
reflectorized raised pavement markers
|
102   |
EACH |
5.50 |
561.00 |
5.70 |
581.40 |
5.50 |
561.00 |
7.30 |
744.60 |
| 732-01-E |
plastic pavement striping (24" width)
|
32   |
LNFT |
4.00 |
128.00 |
5.00 |
160.00 |
3.80 |
121.60 |
6.00 |
192.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
3.141 |
MILE |
2,750.00 |
8,637.75 |
3,000.00 |
9,423.00 |
3,000.00 |
9,423.00 |
3,250.00 |
10,208.25 |
| 735-01 |
mailboxes
|
1   |
EACH |
50.00 |
50.00 |
1.00 |
1.00 |
11.00 |
11.00 |
108.00 |
108.00 |
| 735-02 |
mailbox supports (single)
|
1   |
EACH |
150.00 |
150.00 |
250.00 |
250.00 |
145.00 |
145.00 |
108.00 |
108.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
5,000.00 |
5,000.00 |
20,000.00 |
20,000.00 |
20,000.00 |
20,000.00 |
25,000.00 |
25,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,253,875.19 |
|
1,507,808.30 |
|
1,602,547.40 |
|
1,727,943.15 |
|