Letting of 12/10/2008 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 008-09-0057
Parish: RAPIDES
Routes: US 71
Description: US 71 TURN LANE EXTENSION
Type Const: grading, class ii base course, superpave asphaltic concrete pavement, and related
work.
Estimated Construction Cost: $198,580.71
 
RankLicenseBidderConstruction Bid
1 12312 GILCHRIST CONSTRUCTION CO. LLC $156,066.95
2 35849 T.L. CONSTRUCTION INC $168,771.80
3 46404 TARVER LAND DEVELOPMENT LLC $170,767.40
4 49239 W L BASS CONSTRUCTION INC. $189,316.48
5 30774 PROGRESSIVE CONSTRUCTION CO., INC. $193,410.95
6 32044 QUALITY DESIGN & CONSTRUCTION, LLC. $247,158.60
 
Item Number Item Description Quantity Unit of Measure - 1 -
GILCHRIST CONSTRUCTION CO. LLC
- 2 -
T.L. CONSTRUCTION INC
- 3 -
TARVER LAND DEVELOPMENT LLC
- 4 -
W L BASS CONSTRUCTION INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-I removal of asphaltic pavement 766.8    SQYD 11.00 8,434.80 11.00 8,434.80 6.50 4,984.20 19.00 14,569.20
203-05 excavation and embankment lump      LUMP 6,000.00 6,000.00 25,000.00 25,000.00 10,000.00 10,000.00 19,000.00 19,000.00
204-02 temporary hay or straw bales 16      EACH 30.00 480.00 20.00 320.00 20.00 320.00 1.00 16.00
204-06 temporary silt fencing 880      LNFT 1.60 1,408.00 2.75 2,420.00 4.00 3,520.00 1.00 880.00
302-02-F-01 class ii base course (12" thick)(crushed stone only) 1,297.4    SQYD 30.00 38,922.00 37.00 48,003.80 30.00 38,922.00 37.00 48,003.80
502-01 superpave asphaltic concrete 420.2    TON 135.00 56,727.00 120.00 50,424.00 150.00 63,030.00 140.00 58,828.00
713-01 temporary signs & barricades lump      LUMP 10,000.00 10,000.00 6,000.00 6,000.00 4,000.00 4,000.00 2,150.00 2,150.00
713-02-A temporary pavement markings (4" width) 1,257      LNFT 1.00 1,257.00 1.00 1,257.00 0.20 251.40 0.12 150.84
713-02-E temporary pavement markings (24" width) 12      LNFT 1.00 12.00 1.00 12.00 1.00 12.00 0.72 8.64
727-01 mobilization lump      LUMP 16,000.00 16,000.00 7,500.00 7,500.00 17,000.00 17,000.00 15,000.00 15,000.00
731-02 reflectorized raised pavement markers 61      EACH 5.50 335.50 10.00 610.00 7.00 427.00 5.00 305.00
732-01-A plastic pavement striping (4" width) 865      LNFT 2.35 2,032.75 4.00 3,460.00 5.00 4,325.00 3.00 2,595.00
732-01-C plastic pavement striping (8" width) 528      LNFT 2.95 1,557.60 7.50 3,960.00 7.00 3,696.00 6.00 3,168.00
732-01-E plastic pavement striping (24" width) 12      LNFT 3.50 42.00 15.00 180.00 15.00 180.00 12.00 144.00
732-04-A plastic pavement legends & symbols (arrow) 2      EACH 295.00 590.00 350.00 700.00 500.00 1,000.00 500.00 1,000.00
732-04-C plastic pavement legends & symbols (only) 2      EACH 295.00 590.00 400.00 800.00 500.00 1,000.00 600.00 1,200.00
736-09 loop detector 157      LNFT 26.00 4,082.00 17.00 2,669.00 25.00 3,925.00 21.00 3,297.00
739-01 hydro-seeding 0.49   ACRE 1,300.00 637.00 3,500.00 1,715.00 5,000.00 2,450.00 3,000.00 1,470.00
740-01 construction layout lump      LUMP 3,500.00 3,500.00 3,000.00 3,000.00 2,500.00 2,500.00 6,000.00 6,000.00
S-001 saw cutting asphaltic concrete pavement 11,531      INFT 0.30 3,459.30 0.20 2,306.20 0.80 9,224.80 1.00 11,531.00
                       
 CONTRACTOR TOTAL       156,066.95   168,771.80   170,767.40   189,316.48
 
Item Number Item Description Quantity Unit of Measure - 5 -
PROGRESSIVE CONSTRUCTION CO., INC.
- 6 -
QUALITY DESIGN & CONSTRUCTION, LLC.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-I removal of asphaltic pavement 766.8    SQYD 9.00 6,901.20 10.00 7,668.00        
203-05 excavation and embankment lump      LUMP 13,500.00 13,500.00 52,800.00 52,800.00        
204-02 temporary hay or straw bales 16      EACH 25.00 400.00 14.00 224.00        
204-06 temporary silt fencing 880      LNFT 4.00 3,520.00 2.00 1,760.00        
302-02-F-01 class ii base course (12" thick)(crushed stone only) 1,297.4    SQYD 41.00 53,193.40 39.00 50,598.60        
502-01 superpave asphaltic concrete 420.2    TON 148.50 62,399.70 138.00 57,987.60        
713-01 temporary signs & barricades lump      LUMP 7,500.00 7,500.00 22,100.00 22,100.00        
713-02-A temporary pavement markings (4" width) 1,257      LNFT 2.50 3,142.50 0.80 1,005.60        
713-02-E temporary pavement markings (24" width) 12      LNFT 1.00 12.00 4.20 50.40        
727-01 mobilization lump      LUMP 8,000.00 8,000.00 20,200.00 20,200.00        
731-02 reflectorized raised pavement markers 61      EACH 6.00 366.00 6.60 402.60        
732-01-A plastic pavement striping (4" width) 865      LNFT 3.50 3,027.50 0.70 605.50        
732-01-C plastic pavement striping (8" width) 528      LNFT 7.00 3,696.00 0.70 369.60        
732-01-E plastic pavement striping (24" width) 12      LNFT 15.25 183.00 4.10 49.20        
732-04-A plastic pavement legends & symbols (arrow) 2      EACH 300.00 600.00 115.50 231.00        
732-04-C plastic pavement legends & symbols (only) 2      EACH 3.50 7.00 157.50 315.00        
736-09 loop detector 157      LNFT 60.70 9,529.90 14.30 2,245.10        
739-01 hydro-seeding 0.49   ACRE 3,100.00 1,519.00 4,700.00 2,303.00        
740-01 construction layout lump      LUMP 1,500.00 1,500.00 10,100.00 10,100.00        
S-001 saw cutting asphaltic concrete pavement 11,531      INFT 1.25 14,413.75 1.40 16,143.40        
                       
 CONTRACTOR TOTAL       193,410.95   247,158.60        