| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - D & J CONSTRUCTION CO., INC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
4,000.00 |
4,000.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
63   |
SQYD |
21.00 |
1,323.00 |
22.00 |
1,386.00 |
|
|
|
|
| 203-07 |
borrow (vehicular measurement)
|
1,419   |
CUYD |
26.00 |
36,894.00 |
20.00 |
28,380.00 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
773   |
CUYD |
27.00 |
20,871.00 |
30.00 |
23,190.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
10,064.9 |
TON |
110.00 |
1,107,139.00 |
112.00 |
1,127,268.80 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
204.3 |
TON |
280.00 |
57,204.00 |
162.00 |
33,096.60 |
|
|
|
|
| 507-01-A |
asphaltic material (crs-2p emulsion)
|
35,554   |
GAL |
5.00 |
177,770.00 |
4.25 |
151,104.50 |
|
|
|
|
| 507-02-B |
aggregate (s2)
|
52,285   |
SQYD |
1.00 |
52,285.00 |
1.15 |
60,127.75 |
|
|
|
|
| 507-02-C |
aggregate (s3)
|
52,285   |
SQYD |
0.80 |
41,828.00 |
0.75 |
39,213.75 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
52,285   |
SQYD |
2.00 |
104,570.00 |
2.50 |
130,712.50 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 2,179   |
CUYD |
0.10 |
- 217.90 |
0.10 |
- 217.90 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
2,903   |
SQYD |
100.00 |
290,300.00 |
130.00 |
377,390.00 |
|
|
|
|
| 510-03 |
pavement joint repair
|
175.8 |
TON |
225.00 |
39,555.00 |
200.00 |
35,160.00 |
|
|
|
|
| 706-02-C |
concrete drive (6" thick)
|
63.2 |
SQYD |
75.00 |
4,740.00 |
75.00 |
4,740.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
30,000.00 |
30,000.00 |
125,000.00 |
125,000.00 |
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
11.139 |
MILE |
180.00 |
2,005.02 |
250.00 |
2,784.75 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
11.139 |
MILE |
300.00 |
3,341.70 |
200.00 |
2,227.80 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
22.278 |
MILE |
300.00 |
6,683.40 |
1.00 |
22.28 |
|
|
|
|
| 713-06-A |
temporary reflectorized raised pavement markers (tabs)
|
981   |
EACH |
2.00 |
1,962.00 |
2.00 |
1,962.00 |
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
8.1 |
TON |
400.00 |
3,240.00 |
500.00 |
4,050.00 |
|
|
|
|
| 717-01 |
seeding
|
162   |
LB |
8.00 |
1,296.00 |
8.00 |
1,296.00 |
|
|
|
|
| 718-01 |
fertilizer
|
5,401   |
LB |
0.50 |
2,700.50 |
0.50 |
2,700.50 |
|
|
|
|
| 726-01 |
bedding material
|
12.4 |
CUYD |
100.00 |
1,240.00 |
100.00 |
1,240.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
175,000.00 |
175,000.00 |
175,000.00 |
175,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
490   |
EACH |
5.00 |
2,450.00 |
8.00 |
3,920.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
7.667 |
MILE |
2,600.00 |
19,934.20 |
3,000.00 |
23,001.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
3.713 |
MILE |
650.00 |
2,413.45 |
1,800.00 |
6,683.40 |
|
|
|
|
| 735-01 |
mailboxes
|
6   |
EACH |
1.00 |
6.00 |
25.00 |
150.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
2   |
EACH |
550.00 |
1,100.00 |
500.00 |
1,000.00 |
|
|
|
|
| 735-03 |
mailbox supports (double)
|
2   |
EACH |
550.00 |
1,100.00 |
500.00 |
1,000.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
20,000.00 |
20,000.00 |
11,000.00 |
11,000.00 |
|
|
|
|
| 805-12-A |
reinforced concrete box culverts (4'x 3')
|
15.0 |
LNFT |
550.00 |
8,250.00 |
600.00 |
9,000.00 |
|
|
|
|
| S-001 |
tree trimming
|
lump |
LUMP |
15,000.00 |
15,000.00 |
15,000.00 |
15,000.00 |
|
|
|
|
| S-002 |
cleaning existing ditches
|
300   |
LNFT |
12.00 |
3,600.00 |
15.00 |
4,500.00 |
|
|
|
|
| S-003 |
saw cutting concrete drives (6"depth)
|
60   |
LNFT |
9.00 |
540.00 |
10.00 |
600.00 |
|
|
|
|
| S-004 |
saw cutting asphalt concrete patches
|
124,146   |
LNFT |
0.12 |
14,897.52 |
0.01 |
1,241.46 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,255,020.89 |
|
2,409,931.19 |
|
|
|
|
|