| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - JAMES CONSTRUCTION GROUP LLC |
- 2 - GILCHRIST CONSTRUCTION CO. LLC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing and grubbing
|
lump |
lump |
140,000.00 |
140,000.00 |
150,000.00 |
150,000.00 |
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
lump |
80,000.00 |
80,000.00 |
65,000.00 |
65,000.00 |
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
10,351   |
sq m |
10.00 |
103,510.00 |
12.00 |
124,212.00 |
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
6,424   |
sq m |
4.00 |
25,696.00 |
8.25 |
52,998.00 |
|
|
|
|
| 202-02-I |
removal of existing traffic signal equipment
|
lump |
lump |
5,250.00 |
5,250.00 |
6,500.00 |
6,500.00 |
|
|
|
|
| 202-02-01 |
removal of metal commercial building (sta. 14+750 lt.,
10 m x 50 m) |
1   |
ea |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
|
|
|
|
| 203-01 |
general excavation
|
9,926   |
cu m |
9.00 |
89,334.00 |
8.50 |
84,371.00 |
|
|
|
|
| 203-02 |
drainage excavation
|
141   |
cu m |
20.00 |
2,820.00 |
25.00 |
3,525.00 |
|
|
|
|
| 203-03 |
embankment
|
9,675   |
cu m |
20.00 |
193,500.00 |
30.00 |
290,250.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
10   |
ea |
50.00 |
500.00 |
50.00 |
500.00 |
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
6   |
ea |
175.00 |
1,050.00 |
220.00 |
1,320.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
200   |
ln m |
12.00 |
2,400.00 |
15.00 |
3,000.00 |
|
|
|
|
| 302-02-F |
class ii base course (300 mm thick)
|
21,416.0 |
sq m |
30.00 |
642,480.00 |
28.00 |
599,648.00 |
|
|
|
|
| 304-01 |
lime
|
243.90 |
Mg |
195.00 |
47,560.50 |
205.00 |
49,999.50 |
|
|
|
|
| 304-04-D |
lime treatment (type d) (300 mm thick)
|
15,484   |
sq m |
1.50 |
23,226.00 |
2.15 |
33,290.60 |
|
|
|
|
| 401-01 |
aggregate surface course (net section)
|
6.3 |
cu m |
175.00 |
1,102.50 |
200.00 |
1,260.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
500.0 |
cu m |
150.00 |
75,000.00 |
100.00 |
50,000.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
908.8 |
Mg |
180.00 |
163,584.00 |
165.00 |
149,952.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
125.2 |
Mg |
235.00 |
29,422.00 |
245.00 |
30,674.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
400   |
sq m |
5.00 |
2,000.00 |
12.00 |
4,800.00 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 40   |
cu m |
0.25 |
- 10.00 |
1.00 |
- 40.00 |
|
|
|
|
| 510-01-B |
pavement patching (300 mm minimum thickness)
|
62   |
sq m |
200.00 |
12,400.00 |
200.00 |
12,400.00 |
|
|
|
|
| 601-01-K |
portland cement concrete pavement (250 mm thick)
|
15,256.9 |
sq m |
85.00 |
1,296,836.50 |
82.00 |
1,251,065.80 |
|
|
|
|
| 601-02-K |
portland cement concrete pavement (250 mm thick)
(crossovers & turnouts) |
3,530.8 |
sq m |
98.00 |
346,018.40 |
100.00 |
353,080.00 |
|
|
|
|
| 601-04 |
portland cement concrete pavement coring
|
30   |
ea |
100.00 |
3,000.00 |
120.00 |
3,600.00 |
|
|
|
|
| 602-05-K-01 |
full depth patching of jointed concrete pavement
|
178.5 |
sq m |
350.00 |
62,475.00 |
250.00 |
44,625.00 |
|
|
|
|
| 701-03-F |
storm drain pipe (375 mm rcp)
|
831.3 |
ln m |
140.00 |
116,382.00 |
185.00 |
153,790.50 |
|
|
|
|
| 701-03-F-01 |
storm drain pipe (375 mm)(pccsp)(outfall)
|
6.0 |
ln m |
150.00 |
900.00 |
270.00 |
1,620.00 |
|
|
|
|
| 701-03-G |
storm drain pipe (450 mm rcp)
|
192.7 |
ln m |
160.00 |
30,832.00 |
200.00 |
38,540.00 |
|
|
|
|
| 701-03-I |
storm drain pipe (600 mm rcp)
|
394.2 |
ln m |
210.00 |
82,782.00 |
260.00 |
102,492.00 |
|
|
|
|
| 701-03-I-01 |
storm drain pipe (600 mm)(pccsp)(outfall)
|
12.0 |
ln m |
225.00 |
2,700.00 |
385.00 |
4,620.00 |
|
|
|
|
| 701-03-K |
storm drain pipe (750 mm rcp)
|
390.1 |
ln m |
250.00 |
97,525.00 |
300.00 |
117,030.00 |
|
|
|
|
| 701-03-M |
storm drain pipe (900 mm rcp)
|
49.4 |
ln m |
300.00 |
14,820.00 |
525.00 |
25,935.00 |
|
|
|
|
| 701-03-N |
storm drain pipe (1050 mm rcp)
|
33.1 |
ln m |
500.00 |
16,550.00 |
670.00 |
22,177.00 |
|
|
|
|
| 701-03-O |
storm drain pipe (1200 mm rcp)
|
219.0 |
ln m |
665.00 |
145,635.00 |
740.00 |
162,060.00 |
|
|
|
|
| 701-03-P |
storm drain pipe (1350 mm rcp)
|
64.0 |
ln m |
785.00 |
50,240.00 |
865.00 |
55,360.00 |
|
|
|
|
| 701-03-P-01 |
storm drain pipe (1350 mm)(pccsp)(outfall)
|
6.0 |
ln m |
785.00 |
4,710.00 |
850.00 |
5,100.00 |
|
|
|
|
| 701-09-A |
fabricating pipe fitting (375mm x 375mm)
|
1   |
ea |
370.00 |
370.00 |
330.00 |
330.00 |
|
|
|
|
| 701-09-B |
fabricating pipe fitting (375mm x 450mm)
|
3   |
ea |
450.00 |
1,350.00 |
400.00 |
1,200.00 |
|
|
|
|
| 701-09-C |
fabricating pipe fitting (375mm x 600mm)
|
2   |
ea |
530.00 |
1,060.00 |
1,000.00 |
2,000.00 |
|
|
|
|
| 701-09-D |
fabricating pipe fitting (375mm x 750mm)
|
6   |
ea |
1,050.00 |
6,300.00 |
1,800.00 |
10,800.00 |
|
|
|
|
| 702-02-F |
manholes (mh-01)
|
27   |
ea |
2,750.00 |
74,250.00 |
3,700.00 |
99,900.00 |
|
|
|
|
| 702-03-A |
catch basins (cb-01)
|
37   |
ea |
2,000.00 |
74,000.00 |
2,500.00 |
92,500.00 |
|
|
|
|
| 702-03-B |
catch basins (cb-02)
|
6   |
ea |
3,300.00 |
19,800.00 |
4,000.00 |
24,000.00 |
|
|
|
|
| 702-03-C |
catch basins (cb-06)
|
33   |
ea |
4,550.00 |
150,150.00 |
4,100.00 |
135,300.00 |
|
|
|
|
| 702-03-D |
catch basins (cb-07)
|
2   |
ea |
6,000.00 |
12,000.00 |
4,400.00 |
8,800.00 |
|
|
|
|
| 702-03-F |
catch basins (cb-08)
|
10   |
ea |
6,000.00 |
60,000.00 |
7,500.00 |
75,000.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
3   |
ea |
1,500.00 |
4,500.00 |
2,000.00 |
6,000.00 |
|
|
|
|
| 703-03 |
perforated pipe underdrains
|
707   |
ln m |
30.00 |
21,210.00 |
55.00 |
38,885.00 |
|
|
|
|
| 705-06-B |
chain link fence (1500 mm height)
|
127   |
ln m |
95.00 |
12,065.00 |
100.00 |
12,700.00 |
|
|
|
|
| 706-02-C |
concrete drive (150 mm thick)
|
3,831.3 |
sq m |
80.00 |
306,504.00 |
70.00 |
268,191.00 |
|
|
|
|
| 707-01 |
concrete curb
|
2,048.6 |
ln m |
5.00 |
10,243.00 |
15.00 |
30,729.00 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
226.3 |
ln m |
50.00 |
11,315.00 |
48.00 |
10,862.40 |
|
|
|
|
| 708-01 |
right-of-way monument
|
39   |
ea |
180.00 |
7,020.00 |
550.00 |
21,450.00 |
|
|
|
|
| 711-01-D |
riprap (25 kg, 300mm thick)
|
205   |
sq m |
50.00 |
10,250.00 |
75.00 |
15,375.00 |
|
|
|
|
| 711-04 |
geotextile fabric
|
205   |
sq m |
5.00 |
1,025.00 |
3.50 |
717.50 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
lump |
41,500.00 |
41,500.00 |
275,000.00 |
275,000.00 |
|
|
|
|
| 713-04-A-01 |
temporary pavement markings (solid line)(100 mm width)
(type 1 removable) |
1.130 |
km |
15,000.00 |
16,950.00 |
12,000.00 |
13,560.00 |
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
220.0 |
kg |
4.00 |
880.00 |
1.05 |
231.00 |
|
|
|
|
| 717-01 |
seeding
|
220   |
kg |
18.00 |
3,960.00 |
19.00 |
4,180.00 |
|
|
|
|
| 718-01 |
fertilizer
|
4,035   |
kg |
1.00 |
4,035.00 |
1.00 |
4,035.00 |
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
ea |
15,000.00 |
15,000.00 |
40,000.00 |
40,000.00 |
|
|
|
|
| 726-01 |
bedding material
|
1,339.0 |
cu m |
100.00 |
133,900.00 |
110.00 |
147,290.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
lump |
550,000.00 |
550,000.00 |
645,000.00 |
645,000.00 |
|
|
|
|
| 729-01 |
sign (type a)
|
3.36 |
sq m |
150.00 |
504.00 |
325.00 |
1,092.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
6   |
ea |
95.00 |
570.00 |
90.00 |
540.00 |
|
|
|
|
| 729-19-B |
dead end road installation (type b)
|
1   |
ea |
3,000.00 |
3,000.00 |
3,400.00 |
3,400.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
132   |
ea |
10.00 |
1,320.00 |
5.50 |
726.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (200 mm width)
|
703   |
ln m |
3.30 |
2,319.90 |
3.00 |
2,109.00 |
|
|
|
|
| 732-01-D |
plastic pavement striping (300 mm width)
|
266   |
ln m |
5.00 |
1,330.00 |
4.25 |
1,130.50 |
|
|
|
|
| 732-01-E |
plastic pavement striping (600 mm width)
|
384   |
ln m |
10.00 |
3,840.00 |
8.50 |
3,264.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line)(100 mm width)
|
1.364 |
km |
2,990.00 |
4,078.36 |
2,000.00 |
2,728.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(100 mm width)
|
0.206 |
km |
970.00 |
199.82 |
585.00 |
120.51 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
18   |
ea |
200.00 |
3,600.00 |
220.00 |
3,960.00 |
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
2   |
ea |
250.00 |
500.00 |
245.00 |
490.00 |
|
|
|
|
| 732-05 |
removal of existing markings
|
0.220 |
km |
10,000.00 |
2,200.00 |
4,300.00 |
946.00 |
|
|
|
|
| 735-01 |
mailboxes
|
43   |
ea |
10.00 |
430.00 |
1.20 |
51.60 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
43   |
ea |
150.00 |
6,450.00 |
150.00 |
6,450.00 |
|
|
|
|
| 736-01 |
trenching and backfilling
|
11   |
ln m |
21.00 |
231.00 |
26.00 |
286.00 |
|
|
|
|
| 736-04-B |
signal support (7.92m galvanized steel strain pole)
|
4   |
ea |
7,125.00 |
28,500.00 |
8,500.00 |
34,000.00 |
|
|
|
|
| 736-05-B |
signal heads (3-section, 300mm led lens)
|
7   |
ea |
1,270.00 |
8,890.00 |
1,500.00 |
10,500.00 |
|
|
|
|
| 736-05-C |
signal heads (5-section, 300mm led lens)
|
3   |
ea |
2,100.00 |
6,300.00 |
2,500.00 |
7,500.00 |
|
|
|
|
| 736-06 |
signal service
|
1   |
ea |
2,100.00 |
2,100.00 |
2,500.00 |
2,500.00 |
|
|
|
|
| 736-08 |
signal controller (ts-2 type 2, in type 6 cabinet)
|
1   |
ea |
19,250.00 |
19,250.00 |
21,000.00 |
21,000.00 |
|
|
|
|
| 736-10 |
underground junction box
|
6   |
ea |
570.00 |
3,420.00 |
700.00 |
4,200.00 |
|
|
|
|
| 736-11-B |
conduit (25mm dia. sch. 80)
|
7   |
ln m |
8.00 |
56.00 |
10.00 |
70.00 |
|
|
|
|
| 736-11-D |
conduit (75mm dia. sch. 80)
|
4   |
ln m |
16.25 |
65.00 |
20.00 |
80.00 |
|
|
|
|
| 736-12-A |
conductor (3c power)
|
7   |
ln m |
11.00 |
77.00 |
14.00 |
98.00 |
|
|
|
|
| 736-12-B |
conductor (6c signal/#14 awg)
|
63   |
ln m |
6.00 |
378.00 |
8.00 |
504.00 |
|
|
|
|
| 736-12-C |
conductor (10 signal/#14 awg)
|
262   |
ln m |
11.00 |
2,882.00 |
15.00 |
3,930.00 |
|
|
|
|
| 736-12-D |
conductor (video)
|
155   |
ln m |
5.00 |
775.00 |
7.00 |
1,085.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
lump |
100,000.00 |
100,000.00 |
125,000.00 |
125,000.00 |
|
|
|
|
| 742-01 |
sanitary sewer pipe (200mm pvc, astm d3034, sdr 35)
|
801   |
ln m |
135.00 |
108,135.00 |
250.00 |
200,250.00 |
|
|
|
|
| 742-02 |
adjusting sanitary sewer house connections
|
30   |
ea |
815.00 |
24,450.00 |
600.00 |
18,000.00 |
|
|
|
|
| 742-03 |
adjusting sanitary sewer service lines
|
100   |
ln m |
40.00 |
4,000.00 |
200.00 |
20,000.00 |
|
|
|
|
| S-001 |
video detector device and connection
|
4   |
ea |
6,350.00 |
25,400.00 |
7,500.00 |
30,000.00 |
|
|
|
|
| S-002 |
video detection system
|
1   |
ea |
4,280.00 |
4,280.00 |
5,000.00 |
5,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
5,836,398.98 |
|
6,559,801.91 |
|
|
|
|
|