| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - F.G. SULLIVAN, JR. CONTRACTOR LLC |
- 2 - H & S CONSTRUCTION CO., INC. |
- 3 - GILCHRIST CONSTRUCTION CO. LLC |
- 4 - M. MATT DURAND, LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks & drives
|
360   |
SQYD |
20.00 |
7,200.00 |
22.00 |
7,920.00 |
20.00 |
7,200.00 |
8.00 |
2,880.00 |
| 202-02-I |
removal of cross drains
|
448   |
LNFT |
5.00 |
2,240.00 |
20.00 |
8,960.00 |
25.00 |
11,200.00 |
24.00 |
10,752.00 |
| 203-07 |
borrow (vehicular measurement)
|
250   |
CUYD |
15.00 |
3,750.00 |
22.00 |
5,500.00 |
25.00 |
6,250.00 |
18.00 |
4,500.00 |
| 203-07-A |
borrow (vehicular meas.)(selected soils)
|
300   |
CUYD |
15.00 |
4,500.00 |
22.00 |
6,600.00 |
25.00 |
7,500.00 |
18.00 |
5,400.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
40   |
EACH |
75.00 |
3,000.00 |
190.00 |
7,600.00 |
270.00 |
10,800.00 |
150.00 |
6,000.00 |
| 303-01-B |
in-place cement stabilized base course (8 1/2" thick)
|
43,808   |
SQYD |
9.00 |
394,272.00 |
9.05 |
396,462.40 |
9.75 |
427,128.00 |
9.80 |
429,318.40 |
| 303-02 |
removal of existing patches
|
200   |
SQYD |
5.00 |
1,000.00 |
16.55 |
3,310.00 |
5.00 |
1,000.00 |
10.00 |
2,000.00 |
| 304-05 |
lime treatment (type e)
|
200.00 |
TON |
200.00 |
40,000.00 |
469.00 |
93,800.00 |
400.00 |
80,000.00 |
391.50 |
78,300.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
200   |
CUYD |
30.00 |
6,000.00 |
80.00 |
16,000.00 |
78.00 |
15,600.00 |
61.50 |
12,300.00 |
| 502-01 |
superpave asphaltic concrete
|
8,859.2 |
TON |
87.00 |
770,750.40 |
105.00 |
930,216.00 |
108.00 |
956,793.60 |
119.00 |
1,054,244.80 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
1,300.0 |
TON |
150.00 |
195,000.00 |
135.00 |
175,500.00 |
160.00 |
208,000.00 |
130.00 |
169,000.00 |
| 509-01 |
cold planing asphaltic pavement
|
39,281   |
SQYD |
4.00 |
157,124.00 |
2.75 |
108,022.75 |
1.00 |
39,281.00 |
2.00 |
78,562.00 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 3,273   |
CUYD |
0.01 |
- 32.73 |
0.01 |
- 32.73 |
1.00 |
- 3,273.00 |
2.00 |
- 6,546.00 |
| 701-01-I |
cross drain pipe (24" rcp/pcp)
|
128   |
LNFT |
140.00 |
17,920.00 |
140.00 |
17,920.00 |
170.00 |
21,760.00 |
75.50 |
9,664.00 |
| 701-01-M |
cross drain pipe (36" rcp/pcp)
|
64   |
LNFT |
170.00 |
10,880.00 |
160.00 |
10,240.00 |
195.00 |
12,480.00 |
154.00 |
9,856.00 |
| 701-01-N |
cross drain pipe (42" rcp/pcp)
|
48   |
LNFT |
190.00 |
9,120.00 |
220.00 |
10,560.00 |
250.00 |
12,000.00 |
180.00 |
8,640.00 |
| 701-02-D |
cross drain pipe arch (24" equiv. rcpa)
|
40   |
LNFT |
150.00 |
6,000.00 |
150.00 |
6,000.00 |
155.00 |
6,200.00 |
155.00 |
6,200.00 |
| 701-02-E |
cross drain pipe arch (30" equiv. rcpa)
|
112   |
LNFT |
160.00 |
17,920.00 |
145.00 |
16,240.00 |
175.00 |
19,600.00 |
96.00 |
10,752.00 |
| 701-02-G |
cross drain pipe arch (42" equiv. rcpa)
|
56   |
LNFT |
200.00 |
11,200.00 |
220.00 |
12,320.00 |
250.00 |
14,000.00 |
185.00 |
10,360.00 |
| 701-08 |
relaying pipe
|
8   |
LNFT |
150.00 |
1,200.00 |
106.00 |
848.00 |
53.00 |
424.00 |
220.00 |
1,760.00 |
| 701-15 |
concrete collar
|
4   |
EACH |
1,200.00 |
4,800.00 |
980.00 |
3,920.00 |
1,000.00 |
4,000.00 |
2,000.00 |
8,000.00 |
| 706-02-C |
concrete drive (6" thick)
|
20.0 |
SQYD |
90.00 |
1,800.00 |
111.00 |
2,220.00 |
160.00 |
3,200.00 |
220.00 |
4,400.00 |
| 706-03-C |
incidental concrete paving (6" thick)
|
30.3 |
SQYD |
90.00 |
2,727.00 |
88.00 |
2,666.40 |
160.00 |
4,848.00 |
162.00 |
4,908.60 |
| 707-01 |
concrete curb
|
72.4 |
LNFT |
20.00 |
1,448.00 |
32.00 |
2,316.80 |
50.00 |
3,620.00 |
33.00 |
2,389.20 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
119,000.00 |
119,000.00 |
38,000.00 |
38,000.00 |
20,000.00 |
20,000.00 |
150,000.00 |
150,000.00 |
| 713-02-C |
temporary pavement markings (8" width)
|
200   |
LNFT |
0.25 |
50.00 |
0.39 |
78.00 |
2.00 |
400.00 |
0.40 |
80.00 |
| 713-02-E |
temporary pavement markings (24" width)
|
38   |
LNFT |
0.50 |
19.00 |
0.99 |
37.62 |
2.00 |
76.00 |
1.00 |
38.00 |
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
7.869 |
MILE |
600.00 |
4,721.40 |
385.00 |
3,029.57 |
450.00 |
3,541.05 |
1,900.00 |
14,951.10 |
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
2.403 |
MILE |
250.00 |
600.75 |
414.00 |
994.84 |
525.00 |
1,261.58 |
450.00 |
1,081.35 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
6.879 |
MILE |
250.00 |
1,719.75 |
546.00 |
3,755.93 |
790.00 |
5,434.41 |
600.00 |
4,127.40 |
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
2   |
EACH |
50.00 |
100.00 |
56.00 |
112.00 |
130.00 |
260.00 |
60.00 |
120.00 |
| 713-05-C |
temporary pavement legends and symbols (only)
|
2   |
EACH |
50.00 |
100.00 |
56.00 |
112.00 |
130.00 |
260.00 |
60.00 |
120.00 |
| 722-02 |
project site laboratory (equipped)
|
1   |
EACH |
10,000.00 |
10,000.00 |
7,000.00 |
7,000.00 |
9,500.00 |
9,500.00 |
18,000.00 |
18,000.00 |
| 726-01 |
bedding material
|
100   |
CUYD |
0.00 |
0.00 |
85.00 |
8,500.00 |
115.00 |
11,500.00 |
99.48 |
9,948.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
130,000.00 |
130,000.00 |
95,000.00 |
95,000.00 |
200,000.00 |
200,000.00 |
75,000.00 |
75,000.00 |
| 729-16-B |
object marker assembly (type 2)
|
44   |
EACH |
60.00 |
2,640.00 |
69.00 |
3,036.00 |
60.00 |
2,640.00 |
120.00 |
5,280.00 |
| 731-02 |
reflectorized raised pavement markers
|
625   |
EACH |
6.00 |
3,750.00 |
6.00 |
3,750.00 |
6.50 |
4,062.50 |
6.00 |
3,750.00 |
| 732-01-C |
plastic pavement striping (8" width)
|
200   |
LNFT |
1.25 |
250.00 |
1.05 |
210.00 |
1.30 |
260.00 |
1.10 |
220.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
38   |
LNFT |
5.00 |
190.00 |
4.15 |
157.70 |
5.25 |
199.50 |
4.51 |
171.38 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
6.879 |
MILE |
3,000.00 |
20,637.00 |
3,200.00 |
22,012.80 |
2,900.00 |
19,949.10 |
3,400.00 |
23,388.60 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
2.403 |
MILE |
1,000.00 |
2,403.00 |
828.00 |
1,989.68 |
1,000.00 |
2,403.00 |
900.00 |
2,162.70 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
225.00 |
450.00 |
216.00 |
432.00 |
240.00 |
480.00 |
234.00 |
468.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
2   |
EACH |
225.00 |
450.00 |
260.00 |
520.00 |
240.00 |
480.00 |
400.00 |
800.00 |
| 735-01 |
mailboxes
|
71   |
EACH |
5.00 |
355.00 |
1.10 |
78.10 |
10.00 |
710.00 |
6.00 |
426.00 |
| 735-02 |
mailbox supports (single)
|
34   |
EACH |
125.00 |
4,250.00 |
133.00 |
4,522.00 |
100.00 |
3,400.00 |
120.00 |
4,080.00 |
| 735-03 |
mailbox supports (double)
|
9   |
EACH |
175.00 |
1,575.00 |
188.00 |
1,692.00 |
140.00 |
1,260.00 |
250.00 |
2,250.00 |
| 735-04 |
mailbox supports (multiple)
|
6   |
EACH |
250.00 |
1,500.00 |
355.00 |
2,130.00 |
225.00 |
1,350.00 |
500.00 |
3,000.00 |
| 739-01 |
hydro-seeding
|
0.75 |
ACRE |
2,500.00 |
1,875.00 |
2,900.00 |
2,175.00 |
3,000.00 |
2,250.00 |
2,400.00 |
1,800.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
35,700.00 |
35,700.00 |
6,000.00 |
6,000.00 |
11,000.00 |
11,000.00 |
75,000.00 |
75,000.00 |
| S-001 |
cement treatment (12" thick)
|
10,000.0 |
SQYD |
7.50 |
75,000.00 |
7.17 |
71,700.00 |
7.50 |
75,000.00 |
9.00 |
90,000.00 |
| S-002 |
full depth sawcutting of existing portland cement
concrete drives |
12,500   |
INFT |
1.10 |
13,750.00 |
1.10 |
13,750.00 |
2.00 |
25,000.00 |
1.50 |
18,750.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,100,904.57 |
|
2,135,884.86 |
|
2,272,288.74 |
|
2,428,653.53 |
|