Letting of 11/12/2008 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 713-08-0109
Parish: BOSSIER
Routes:
Description: CROUCH ROAD BRIDGE OVER WHITE OAK BRANCH
Type Const: grading, class ii base course, superpave asphaltic concrete pavement, precast prestressed
concrete girder spans bridge, and related work.
Estimated Construction Cost: $441,992.00
 
RankLicenseBidderConstruction Bid
1 18546 C W & W CONTRACTORS, INC. $391,728.00
2 28218 F. J. BURNELL, INC. $402,840.50
3 49864 TERRAL CONSTRUCTION L.L.C.� $428,074.00
4 12135 BLOUNT BROS. CONSTRUCTION, INC. $507,508.00
5 09090 GUINN BROTHERS, LLC. $602,626.60
 
Item Number Item Description Quantity Unit of Measure - 1 -
C W & W CONTRACTORS, INC.
- 2 -
F. J. BURNELL, INC.
- 3 -
TERRAL CONSTRUCTION L.L.C.�
- 4 -
BLOUNT BROS. CONSTRUCTION, INC.
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing and grubbing lump      LUMP 5,000.00 5,000.00 10,000.00 10,000.00 5,000.00 5,000.00 30,000.00 30,000.00
202-02-A-01 removal of bridge (sta. 15+25 - 26.1 ft. x 45.5 ft.
timber bridge)
1      EACH 5,000.00 5,000.00 10,000.00 10,000.00 5,300.00 5,300.00 30,000.00 30,000.00
203-05 excavation and embankment lump      LUMP 25,000.00 25,000.00 20,000.00 20,000.00 25,000.00 25,000.00 30,000.00 30,000.00
204-02 temporary hay or straw bales 11      EACH 10.00 110.00 10.00 110.00 12.00 132.00 20.00 220.00
204-03 temporary slope drains 180      LNFT 15.00 2,700.00 5.00 900.00 2.00 360.00 20.00 3,600.00
204-05-A temporary sediment check dams (hay) 5      EACH 125.00 625.00 125.00 625.00 120.00 600.00 400.00 2,000.00
204-06 temporary silt fencing 1,060      LNFT 3.00 3,180.00 2.00 2,120.00 2.40 2,544.00 3.00 3,180.00
302-01 class ii base course 249.8    CUYD 100.00 24,980.00 70.00 17,486.00 125.00 31,225.00 90.00 22,482.00
401-02 aggregate surface course (adjusted vehicular
measurement)
2      CUYD 100.00 200.00 500.00 1,000.00 180.00 360.00 100.00 200.00
502-01 superpave asphaltic concrete 196.3    TON 175.00 34,352.50 220.00 43,186.00 300.00 58,890.00 160.00 31,408.00
704-03 blocked out guard rail 50.0    LNFT 30.00 1,500.00 28.00 1,400.00 25.00 1,250.00 30.00 1,500.00
704-08-B guard rail transitions (double thrie beam) 100.0    LNFT 75.00 7,500.00 72.00 7,200.00 84.00 8,400.00 75.00 7,500.00
704-11-A guard rail end treatment (flared) 4      EACH 2,900.00 11,600.00 2,300.00 9,200.00 3,300.00 13,200.00 2,500.00 10,000.00
705-01 barbed wire fence 293      LNFT 8.50 2,490.50 5.50 1,611.50 12.00 3,516.00 6.00 1,758.00
712-02 sacked concrete revetment 372      SQYD 85.00 31,620.00 60.00 22,320.00 87.00 32,364.00 90.00 33,480.00
713-01 temporary signs and barricades lump      LUMP 10,000.00 10,000.00 8,000.00 8,000.00 9,600.00 9,600.00 15,000.00 15,000.00
716-01-A mulch (vegetative) 0.6    TON 2,400.00 1,440.00 1,000.00 600.00 2,000.00 1,200.00 1,000.00 600.00
717-01 seeding 13      LB 13.00 169.00 30.00 390.00 1.00 13.00 20.00 260.00
718-01 fertilizer 280      LB 1.00 280.00 2.00 560.00 2.00 560.00 1.00 280.00
727-01 moblization lump      LUMP 35,000.00 35,000.00 18,000.00 18,000.00 40,000.00 40,000.00 50,000.00 50,000.00
729-16-C object marker assembly (type 3) 4      EACH 95.00 380.00 110.00 440.00 100.00 400.00 200.00 800.00
740-01 construction layout lump      LUMP 5,000.00 5,000.00 7,500.00 7,500.00 3,000.00 3,000.00 20,000.00 20,000.00
804-01-B precast concrete piles (14") 736      LNFT 100.00 73,600.00 147.00 108,192.00 60.00 44,160.00 90.00 66,240.00
804-12 loading permanent piles 1      EACH 1.00 1.00 1,000.00 1,000.00 1,000.00 1,000.00 5,000.00 5,000.00
805-10-A bridge superstructure and substructure (28ft. clr.
rdwy.; 60deg crossing) (precast only)
3      SPAN 30,000.00 90,000.00 32,000.00 96,000.00 40,000.00 120,000.00 42,000.00 126,000.00
S-101 concrete approach slabs (28ft. clr. rdwy.; 60deg
crossing)
2      EACH 10,000.00 20,000.00 7,500.00 15,000.00 10,000.00 20,000.00 8,000.00 16,000.00
                       
 CONTRACTOR TOTAL       391,728.00   402,840.50   428,074.00   507,508.00
 
Item Number Item Description Quantity Unit of Measure - 5 -
GUINN BROTHERS, LLC.

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing and grubbing lump      LUMP 30,000.00 30,000.00            
202-02-A-01 removal of bridge (sta. 15+25 - 26.1 ft. x 45.5 ft.
timber bridge)
1      EACH 10,000.00 10,000.00            
203-05 excavation and embankment lump      LUMP 30,000.00 30,000.00            
204-02 temporary hay or straw bales 11      EACH 10.00 110.00            
204-03 temporary slope drains 180      LNFT 10.00 1,800.00            
204-05-A temporary sediment check dams (hay) 5      EACH 100.00 500.00            
204-06 temporary silt fencing 1,060      LNFT 5.00 5,300.00            
302-01 class ii base course 249.8    CUYD 105.00 26,229.00            
401-02 aggregate surface course (adjusted vehicular
measurement)
2      CUYD 100.00 200.00            
502-01 superpave asphaltic concrete 196.3    TON 602.00 118,172.60            
704-03 blocked out guard rail 50.0    LNFT 40.00 2,000.00            
704-08-B guard rail transitions (double thrie beam) 100.0    LNFT 80.00 8,000.00            
704-11-A guard rail end treatment (flared) 4      EACH 3,800.00 15,200.00            
705-01 barbed wire fence 293      LNFT 8.00 2,344.00            
712-02 sacked concrete revetment 372      SQYD 125.00 46,500.00            
713-01 temporary signs and barricades lump      LUMP 15,000.00 15,000.00            
716-01-A mulch (vegetative) 0.6    TON 2,800.00 1,680.00            
717-01 seeding 13      LB 30.00 390.00            
718-01 fertilizer 280      LB 1.00 280.00            
727-01 moblization lump      LUMP 55,000.00 55,000.00            
729-16-C object marker assembly (type 3) 4      EACH 100.00 400.00            
740-01 construction layout lump      LUMP 17,000.00 17,000.00            
804-01-B precast concrete piles (14") 736      LNFT 70.00 51,520.00            
804-12 loading permanent piles 1      EACH 1.00 1.00            
805-10-A bridge superstructure and substructure (28ft. clr.
rdwy.; 60deg crossing) (precast only)
3      SPAN 45,000.00 135,000.00            
S-101 concrete approach slabs (28ft. clr. rdwy.; 60deg
crossing)
2      EACH 15,000.00 30,000.00            
                       
 CONTRACTOR TOTAL       602,626.60            