| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - FORBY CONTRACTING, INC. |
- 2 - D & J CONSTRUCTION CO., INC. |
- 3 - INTERSTATE IMPROVEMENT, INC. |
- 4 - W. E. BLAIN & SONS, INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-G |
removal of surfacing & stabilized base
|
4,437.6 |
SQYD |
7.00 |
31,063.20 |
7.00 |
31,063.20 |
7.00 |
31,063.20 |
11.50 |
51,032.40 |
| 302-01 |
class ii base course
|
115.6 |
CUYD |
80.00 |
9,248.00 |
80.00 |
9,248.00 |
40.00 |
4,624.00 |
100.00 |
11,560.00 |
| 502-01 |
superpave asphaltic concrete
|
1,464.4 |
TON |
125.00 |
183,050.00 |
125.00 |
183,050.00 |
125.00 |
183,050.00 |
132.00 |
193,300.80 |
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
26,564   |
LNFT |
1.25 |
33,205.00 |
1.75 |
46,487.00 |
1.50 |
39,846.00 |
1.55 |
41,174.20 |
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
27,844   |
LNFT |
1.50 |
41,766.00 |
2.00 |
55,688.00 |
1.75 |
48,727.00 |
1.88 |
52,346.72 |
| 602-03 |
cleaning and sealing cracks
|
4,000   |
LNFT |
2.50 |
10,000.00 |
3.00 |
12,000.00 |
2.50 |
10,000.00 |
3.10 |
12,400.00 |
| 602-05-I-01 |
full depth patching of jointed conc pvmt (9" thick)
(16.0 sq yds & under) |
731.6 |
SQYD |
160.00 |
117,056.00 |
200.00 |
146,320.00 |
225.00 |
164,610.00 |
200.00 |
146,320.00 |
| 602-05-I-02 |
full depth patching of jointed conc pvmt (9" thick)
(16.1 - 48.0 sq yds) |
457.3 |
SQYD |
150.00 |
68,595.00 |
195.00 |
89,173.50 |
200.00 |
91,460.00 |
187.00 |
85,515.10 |
| 602-05-I-03 |
full depth patching of jointed conc pvmt (9" thick)
(48.1 sq yds & over) |
544.7 |
SQYD |
120.00 |
65,364.00 |
165.00 |
89,875.50 |
200.00 |
108,940.00 |
150.00 |
81,705.00 |
| 602-10 |
longitudinal shoulder joints
|
31,098   |
LNFT |
1.25 |
38,872.50 |
2.50 |
77,745.00 |
1.25 |
38,872.50 |
1.55 |
48,201.90 |
| 707-01 |
concrete curb
|
110.0 |
LNFT |
18.00 |
1,980.00 |
50.00 |
5,500.00 |
30.00 |
3,300.00 |
22.00 |
2,420.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
25,000.00 |
25,000.00 |
50,000.00 |
50,000.00 |
25,000.00 |
25,000.00 |
150,000.00 |
150,000.00 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
0.748 |
MILE |
800.00 |
598.40 |
500.00 |
374.00 |
500.00 |
374.00 |
800.00 |
598.40 |
| 727-01 |
mobilization
|
lump |
LUMP |
50,000.00 |
50,000.00 |
70,000.00 |
70,000.00 |
135,000.00 |
135,000.00 |
158,000.00 |
158,000.00 |
| 731-02 |
reflectorized raised pavement markers
|
721   |
EACH |
4.50 |
3,244.50 |
6.00 |
4,326.00 |
6.00 |
4,326.00 |
4.50 |
3,244.50 |
| 732-01-C |
plastic pavement striping (8" width)
|
800   |
LNFT |
1.00 |
800.00 |
4.00 |
3,200.00 |
4.00 |
3,200.00 |
1.00 |
800.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
8.778 |
MILE |
2,500.00 |
21,945.00 |
3,000.00 |
26,334.00 |
2,600.00 |
22,822.80 |
2,500.00 |
21,945.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.389 |
MILE |
600.00 |
2,633.40 |
1,200.00 |
5,266.80 |
1,100.00 |
4,827.90 |
600.00 |
2,633.40 |
| 732-05 |
removal of existing markings
|
4.389 |
MILE |
4,000.00 |
17,556.00 |
3,300.00 |
14,483.70 |
3,200.00 |
14,044.80 |
4,000.00 |
17,556.00 |
| 735-01 |
mailboxes
|
4   |
EACH |
50.00 |
200.00 |
25.00 |
100.00 |
500.00 |
2,000.00 |
118.00 |
472.00 |
| 735-02 |
mailbox supports (single)
|
4   |
EACH |
50.00 |
200.00 |
125.00 |
500.00 |
200.00 |
800.00 |
132.00 |
528.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
2,500.00 |
2,500.00 |
6,000.00 |
6,000.00 |
5,000.00 |
5,000.00 |
25,000.00 |
25,000.00 |
| S-001 |
routing, cleaning and sealing random cracks
|
200   |
LNFT |
3.50 |
700.00 |
12.00 |
2,400.00 |
2.00 |
400.00 |
4.35 |
870.00 |
| S-002 |
rumble strips (ground-in)
|
0.9 |
MILE |
5,500.00 |
4,950.00 |
10,000.00 |
9,000.00 |
5,444.44 |
4,900.00 |
3,000.00 |
2,700.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
730,527.00 |
|
938,134.70 |
|
947,188.20 |
|
1,110,323.42 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - JEFF MERCER LLC |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-G |
removal of surfacing & stabilized base
|
4,437.6 |
SQYD |
8.00 |
35,500.80 |
|
|
|
|
|
|
| 302-01 |
class ii base course
|
115.6 |
CUYD |
300.00 |
34,680.00 |
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
1,464.4 |
TON |
185.00 |
270,914.00 |
|
|
|
|
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
26,564   |
LNFT |
2.50 |
66,410.00 |
|
|
|
|
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
27,844   |
LNFT |
2.50 |
69,610.00 |
|
|
|
|
|
|
| 602-03 |
cleaning and sealing cracks
|
4,000   |
LNFT |
2.50 |
10,000.00 |
|
|
|
|
|
|
| 602-05-I-01 |
full depth patching of jointed conc pvmt (9" thick)
(16.0 sq yds & under) |
731.6 |
SQYD |
195.00 |
142,662.00 |
|
|
|
|
|
|
| 602-05-I-02 |
full depth patching of jointed conc pvmt (9" thick)
(16.1 - 48.0 sq yds) |
457.3 |
SQYD |
185.00 |
84,600.50 |
|
|
|
|
|
|
| 602-05-I-03 |
full depth patching of jointed conc pvmt (9" thick)
(48.1 sq yds & over) |
544.7 |
SQYD |
165.00 |
89,875.50 |
|
|
|
|
|
|
| 602-10 |
longitudinal shoulder joints
|
31,098   |
LNFT |
2.65 |
82,409.70 |
|
|
|
|
|
|
| 707-01 |
concrete curb
|
110.0 |
LNFT |
80.00 |
8,800.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
50,000.00 |
50,000.00 |
|
|
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
0.748 |
MILE |
3,370.00 |
2,520.76 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
145,000.00 |
145,000.00 |
|
|
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
721   |
EACH |
6.00 |
4,326.00 |
|
|
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
800   |
LNFT |
1.50 |
1,200.00 |
|
|
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
8.778 |
MILE |
3,200.00 |
28,089.60 |
|
|
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
4.389 |
MILE |
1,000.00 |
4,389.00 |
|
|
|
|
|
|
| 732-05 |
removal of existing markings
|
4.389 |
MILE |
3,800.00 |
16,678.20 |
|
|
|
|
|
|
| 735-01 |
mailboxes
|
4   |
EACH |
50.00 |
200.00 |
|
|
|
|
|
|
| 735-02 |
mailbox supports (single)
|
4   |
EACH |
250.00 |
1,000.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
20,000.00 |
20,000.00 |
|
|
|
|
|
|
| S-001 |
routing, cleaning and sealing random cracks
|
200   |
LNFT |
25.00 |
5,000.00 |
|
|
|
|
|
|
| S-002 |
rumble strips (ground-in)
|
0.9 |
MILE |
52,800.00 |
47,520.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,221,386.06 |
|
|
|
|
|
|
|