| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - T. L. WALLACE CONSTRUCTION, INC. |
- 2 - P.R. PARKER COMPANY INC |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 507-01-A |
asphaltic material (crs-2p emulsion)
|
54,454   |
GAL |
3.75 |
204,202.50 |
3.90 |
212,370.60 |
|
|
|
|
| 507-02-B |
aggregate (s2)
|
80,079   |
SQYD |
1.00 |
80,079.00 |
1.27 |
101,700.33 |
|
|
|
|
| 507-02-C |
aggregate (s3)
|
80,079   |
SQYD |
1.10 |
88,086.90 |
1.10 |
88,086.90 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
615   |
SQYD |
130.00 |
79,950.00 |
112.00 |
68,880.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
3,995.00 |
3,995.00 |
20,000.00 |
20,000.00 |
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
12   |
LNFT |
0.90 |
10.80 |
0.90 |
10.80 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
2.582 |
MILE |
300.00 |
774.60 |
300.00 |
774.60 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
12.379 |
MILE |
600.00 |
7,427.40 |
600.00 |
7,427.40 |
|
|
|
|
| 713-05-D |
temporary pavement legends and symbols (rr crossing)
|
1   |
EACH |
400.00 |
400.00 |
400.00 |
400.00 |
|
|
|
|
| 713-06-A |
temporary reflectorized raised pavement markers (tabs)
|
3,070   |
EACH |
1.00 |
3,070.00 |
2.00 |
6,140.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
17,500.00 |
17,500.00 |
59,000.00 |
59,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
1,375   |
EACH |
4.50 |
6,187.50 |
4.50 |
6,187.50 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
1,200   |
LNFT |
1.00 |
1,200.00 |
1.00 |
1,200.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
1,950   |
LNFT |
3.00 |
5,850.00 |
3.00 |
5,850.00 |
|
|
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
1   |
EACH |
400.00 |
400.00 |
400.00 |
400.00 |
|
|
|
|
| 732-05 |
removal of existing markings
|
0.100 |
MILE |
10,000.00 |
1,000.00 |
10,000.00 |
1,000.00 |
|
|
|
|
| 737-01-A |
painted traffic striping (solid line)(4" width)
|
12.379 |
MILE |
600.00 |
7,427.40 |
600.00 |
7,427.40 |
|
|
|
|
| 737-02-A |
painted traffic striping (broken line)(4" width)
|
2.582 |
MILE |
300.00 |
774.60 |
300.00 |
774.60 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
6,000.00 |
6,000.00 |
1,000.00 |
1,000.00 |
|
|
|
|
| S-001 |
saw cutting asphaltic concrete pavement
|
19,500   |
INFT |
0.25 |
4,875.00 |
0.10 |
1,950.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
519,210.70 |
|
590,580.13 |
|
|
|
|
|