| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - D & J CONSTRUCTION CO., INC. |
- 3 - KIEWIT LOUISIANA CO |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
244   |
LNFT |
14.00 |
3,416.00 |
12.00 |
2,928.00 |
10.00 |
2,440.00 |
|
|
| 203-07 |
borrow (vehicular measurement)
|
500   |
CUYD |
24.00 |
12,000.00 |
30.00 |
15,000.00 |
50.00 |
25,000.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
2,925   |
CUYD |
27.00 |
78,975.00 |
15.00 |
43,875.00 |
90.00 |
263,250.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
18,872.2 |
TON |
100.00 |
1,887,220.00 |
112.00 |
2,113,686.40 |
125.00 |
2,359,025.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
866.5 |
TON |
165.00 |
142,972.50 |
112.00 |
97,048.00 |
150.39 |
130,312.94 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
98,818   |
SQYD |
1.10 |
108,699.80 |
1.00 |
98,818.00 |
4.00 |
395,272.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 4,124   |
CUYD |
0.10 |
- 412.40 |
0.10 |
- 412.40 |
0.01 |
- 41.24 |
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
1,782   |
SQYD |
98.00 |
174,636.00 |
110.00 |
196,020.00 |
150.00 |
267,300.00 |
|
|
| 704-03 |
blocked out guard rail
|
100.1 |
LNFT |
23.00 |
2,302.30 |
22.00 |
2,202.20 |
20.00 |
2,002.00 |
|
|
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
25.0 |
LNFT |
50.00 |
1,250.00 |
48.00 |
1,200.00 |
31.00 |
775.00 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
50.0 |
LNFT |
64.00 |
3,200.00 |
62.00 |
3,100.00 |
40.00 |
2,000.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
2   |
EACH |
2,600.00 |
5,200.00 |
2,500.00 |
5,000.00 |
1,600.00 |
3,200.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
12,000.00 |
12,000.00 |
11,000.00 |
11,000.00 |
84,000.00 |
84,000.00 |
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
562   |
LNFT |
0.65 |
365.30 |
3.00 |
1,686.00 |
4.25 |
2,388.50 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
13.890 |
MILE |
145.00 |
2,014.05 |
250.00 |
3,472.50 |
564.00 |
7,833.96 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
13.288 |
MILE |
260.00 |
3,454.88 |
200.00 |
2,657.60 |
268.00 |
3,561.18 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
30.238 |
MILE |
423.00 |
12,790.67 |
1.00 |
30.24 |
429.00 |
12,972.10 |
|
|
| 716-01-A |
mulch (vegetative)
|
27.0 |
TON |
365.00 |
9,855.00 |
350.00 |
9,450.00 |
650.00 |
17,550.00 |
|
|
| 717-01 |
seeding
|
603   |
LB |
7.45 |
4,492.35 |
7.00 |
4,221.00 |
7.50 |
4,522.50 |
|
|
| 718-01 |
fertilizer
|
13,390   |
LB |
0.55 |
7,364.50 |
0.50 |
6,695.00 |
0.35 |
4,686.50 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
112,000.00 |
112,000.00 |
52,000.00 |
52,000.00 |
400,000.00 |
400,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
2   |
EACH |
85.00 |
170.00 |
80.00 |
160.00 |
75.00 |
150.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
1,258   |
EACH |
5.00 |
6,290.00 |
6.00 |
7,548.00 |
6.00 |
7,548.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
281   |
LNFT |
3.25 |
913.25 |
9.00 |
2,529.00 |
15.00 |
4,215.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
15.119 |
MILE |
2,400.00 |
36,285.60 |
2,100.00 |
31,749.90 |
2,500.00 |
37,797.50 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
6.644 |
MILE |
650.00 |
4,318.60 |
1,100.00 |
7,308.40 |
900.00 |
5,979.60 |
|
|
| 735-01 |
mailboxes
|
16   |
EACH |
1.00 |
16.00 |
1.00 |
16.00 |
105.00 |
1,680.00 |
|
|
| 735-02 |
mailbox supports (single)
|
10   |
EACH |
155.00 |
1,550.00 |
155.00 |
1,550.00 |
150.00 |
1,500.00 |
|
|
| 735-03 |
mailbox supports (double)
|
1   |
EACH |
185.00 |
185.00 |
200.00 |
200.00 |
250.00 |
250.00 |
|
|
| 735-04 |
mailbox supports (multiple)
|
1   |
EACH |
345.00 |
345.00 |
350.00 |
350.00 |
390.00 |
390.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
14,000.00 |
14,000.00 |
16,000.00 |
16,000.00 |
44,000.00 |
44,000.00 |
|
|
| S-001 |
saw cutting asphaltic concrete patches (12" deep)
|
5,080   |
LNFT |
1.75 |
8,890.00 |
2.40 |
12,192.00 |
5.00 |
25,400.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,656,759.40 |
|
2,749,280.84 |
|
4,116,960.54 |
|
|
|