| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - MADDEN CONTRACTING CO., INC. |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 3 - GILCHRIST CONSTRUCTION CO. LLC |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
1,000.00 |
1,000.00 |
5,500.00 |
5,500.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-H |
removal of guard rail
|
1,208   |
LNFT |
6.00 |
7,248.00 |
6.50 |
7,852.00 |
8.50 |
10,268.00 |
|
|
| 203-07 |
borrow (vehicular measurement)
|
160   |
CUYD |
20.00 |
3,200.00 |
25.00 |
4,000.00 |
12.00 |
1,920.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
400   |
CUYD |
43.00 |
17,200.00 |
45.00 |
18,000.00 |
76.00 |
30,400.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
7,551.6 |
TON |
102.00 |
770,263.20 |
96.50 |
728,729.40 |
115.00 |
868,434.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
619.6 |
TON |
50.00 |
30,980.00 |
167.50 |
103,783.00 |
150.00 |
92,940.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
68,421   |
SQYD |
1.23 |
84,157.83 |
1.50 |
102,631.50 |
0.55 |
37,631.55 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 1,865   |
CUYD |
0.01 |
- 18.65 |
0.10 |
- 186.50 |
0.01 |
- 18.65 |
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
360   |
SQYD |
100.00 |
36,000.00 |
120.00 |
43,200.00 |
112.00 |
40,320.00 |
|
|
| 701-01-I |
cross drain pipe (24" rcp/pcp)
|
64   |
LNFT |
200.00 |
12,800.00 |
265.00 |
16,960.00 |
275.00 |
17,600.00 |
|
|
| 704-01-A |
guard rail (single thrie beam)(3'-1 1/2" post spacing)
|
200.0 |
LNFT |
50.00 |
10,000.00 |
55.00 |
11,000.00 |
55.00 |
11,000.00 |
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
232.0 |
LNFT |
48.75 |
11,310.00 |
50.00 |
11,600.00 |
55.00 |
12,760.00 |
|
|
| 704-03 |
blocked out guard rail
|
100.0 |
LNFT |
20.00 |
2,000.00 |
21.00 |
2,100.00 |
22.00 |
2,200.00 |
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
8   |
EACH |
2,500.00 |
20,000.00 |
2,650.00 |
21,200.00 |
2,500.00 |
20,000.00 |
|
|
| 707-04 |
asphaltic curb
|
80.0 |
LNFT |
10.00 |
800.00 |
35.00 |
2,800.00 |
30.00 |
2,400.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
40,500.00 |
40,500.00 |
13,000.00 |
13,000.00 |
14,000.00 |
14,000.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
9.279 |
MILE |
325.00 |
3,015.68 |
140.00 |
1,299.06 |
150.00 |
1,391.85 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
5.555 |
MILE |
1.00 |
5.56 |
300.00 |
1,666.50 |
300.00 |
1,666.50 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
30.636 |
MILE |
1.00 |
30.64 |
450.00 |
13,786.20 |
425.00 |
13,020.30 |
|
|
| 716-01-A |
mulch (vegetative)
|
4.8 |
TON |
1,000.00 |
4,800.00 |
650.00 |
3,120.00 |
700.00 |
3,360.00 |
|
|
| 717-01 |
seeding
|
72   |
LB |
10.00 |
720.00 |
13.00 |
936.00 |
8.00 |
576.00 |
|
|
| 718-01 |
fertilizer
|
2,411   |
LB |
1.00 |
2,411.00 |
0.55 |
1,326.05 |
0.70 |
1,687.70 |
|
|
| 726-01 |
bedding material
|
14.0 |
CUYD |
80.00 |
1,120.00 |
130.00 |
1,820.00 |
115.00 |
1,610.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
40,500.00 |
40,500.00 |
42,500.00 |
42,500.00 |
45,000.00 |
45,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
10   |
EACH |
75.00 |
750.00 |
80.00 |
800.00 |
85.00 |
850.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
700   |
EACH |
4.50 |
3,150.00 |
5.25 |
3,675.00 |
5.75 |
4,025.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
320   |
LNFT |
1.00 |
320.00 |
1.00 |
320.00 |
1.00 |
320.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
36   |
LNFT |
3.00 |
108.00 |
3.50 |
126.00 |
4.00 |
144.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
15.318 |
MILE |
2,500.00 |
38,295.00 |
2,750.00 |
42,124.50 |
2,950.00 |
45,188.10 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
2.777 |
MILE |
700.00 |
1,943.90 |
750.00 |
2,082.75 |
780.00 |
2,166.06 |
|
|
| 735-01 |
mailboxes
|
15   |
EACH |
1.00 |
15.00 |
1.00 |
15.00 |
2.00 |
30.00 |
|
|
| 735-02 |
mailbox supports (single)
|
11   |
EACH |
125.00 |
1,375.00 |
130.00 |
1,430.00 |
160.00 |
1,760.00 |
|
|
| 735-03 |
mailbox supports (double)
|
2   |
EACH |
175.00 |
350.00 |
180.00 |
360.00 |
250.00 |
500.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
15,000.00 |
15,000.00 |
16,000.00 |
16,000.00 |
11,250.00 |
11,250.00 |
|
|
| S-001 |
roadway reinforcing mesh (complete road system)
|
424   |
SQYD |
7.50 |
3,180.00 |
10.00 |
4,240.00 |
10.00 |
4,240.00 |
|
|
| S-002 |
saw cutting
|
15,900   |
INFT |
0.01 |
159.00 |
0.15 |
2,385.00 |
2.00 |
31,800.00 |
|
|
| S-003 |
cleaning existing ditches
|
40   |
LNFT |
10.00 |
400.00 |
30.00 |
1,200.00 |
38.50 |
1,540.00 |
|
|
| S-004 |
dressing project shoulders
|
lump |
LUMP |
36,000.00 |
36,000.00 |
26,000.00 |
26,000.00 |
25,000.00 |
25,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,201,089.16 |
|
1,259,381.46 |
|
1,363,980.41 |
|
|
|