| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - GILCHRIST CONSTRUCTION CO. LLC |
- 3 - H & S CONSTRUCTION CO., INC. |
- 4 - PRAIRIE CONTRACTORS INC. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-E |
removal of concrete curbs
|
4,775.0 |
LNFT |
2.50 |
11,937.50 |
15.00 |
71,625.00 |
7.00 |
33,425.00 |
4.00 |
19,100.00 |
| 203-01 |
general excavation
|
50   |
CUYD |
16.00 |
800.00 |
14.00 |
700.00 |
30.00 |
1,500.00 |
25.00 |
1,250.00 |
| 203-07 |
borrow (vehicular measurement)
|
202   |
CUYD |
23.00 |
4,646.00 |
20.00 |
4,040.00 |
25.00 |
5,050.00 |
25.00 |
5,050.00 |
| 502-01 |
superpave asphaltic concrete
|
5,740.1 |
TON |
100.00 |
574,010.00 |
128.00 |
734,732.80 |
120.00 |
688,812.00 |
135.00 |
774,913.50 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
509.4 |
TON |
150.00 |
76,410.00 |
245.00 |
124,803.00 |
155.00 |
78,957.00 |
200.00 |
101,880.00 |
| 509-01 |
cold planing asphaltic pavement
|
31,881   |
SQYD |
2.00 |
63,762.00 |
0.50 |
15,940.50 |
5.00 |
159,405.00 |
4.25 |
135,494.25 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 1,904   |
CUYD |
0.10 |
- 190.40 |
0.01 |
- 19.04 |
0.01 |
- 19.04 |
0.01 |
- 19.04 |
| 510-01-B |
pavement patching (12" minimum thickness)
|
250   |
SQYD |
125.00 |
31,250.00 |
200.00 |
50,000.00 |
190.00 |
47,500.00 |
140.00 |
35,000.00 |
| 510-03 |
pavement joint repair
|
50.0 |
TON |
250.00 |
12,500.00 |
250.00 |
12,500.00 |
300.00 |
15,000.00 |
200.00 |
10,000.00 |
| 602-05-G-01 |
full depth patching of jointed conc pvmt (8" thick)
(16.0 sq yds & under) |
50.0 |
SQYD |
310.00 |
15,500.00 |
300.00 |
15,000.00 |
356.00 |
17,800.00 |
300.00 |
15,000.00 |
| 702-04-A |
adjusting manholes
|
16   |
EACH |
2,100.00 |
33,600.00 |
1,300.00 |
20,800.00 |
239.00 |
3,824.00 |
1,000.00 |
16,000.00 |
| 702-04-B |
adjusting catch basins
|
3   |
EACH |
3,100.00 |
9,300.00 |
2,500.00 |
7,500.00 |
3,555.00 |
10,665.00 |
4,000.00 |
12,000.00 |
| 706-03-A |
incidental concrete paving (4" thick)
|
35.7 |
SQYD |
80.00 |
2,856.00 |
100.00 |
3,570.00 |
172.00 |
6,140.40 |
125.00 |
4,462.50 |
| 707-01 |
concrete curb
|
4,775.0 |
LNFT |
16.00 |
76,400.00 |
27.50 |
131,312.50 |
18.00 |
85,950.00 |
16.50 |
78,787.50 |
| 710-01 |
flowable fill
|
50   |
CUYD |
105.00 |
5,250.00 |
150.00 |
7,500.00 |
118.50 |
5,925.00 |
150.00 |
7,500.00 |
| 711-04 |
geotextile fabric
|
20   |
SQYD |
21.00 |
420.00 |
3.78 |
75.60 |
24.00 |
480.00 |
30.00 |
600.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
40,000.00 |
40,000.00 |
18,000.00 |
18,000.00 |
42,000.00 |
42,000.00 |
75,000.00 |
75,000.00 |
| 713-02-C |
temporary pavement markings (8" width)
|
3,960   |
LNFT |
0.32 |
1,267.20 |
0.50 |
1,980.00 |
0.36 |
1,425.60 |
0.01 |
39.60 |
| 713-02-E |
temporary pavement markings (24" width)
|
939   |
LNFT |
1.00 |
939.00 |
1.00 |
939.00 |
1.07 |
1,004.73 |
0.01 |
9.39 |
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
4.050 |
MILE |
150.00 |
607.50 |
250.00 |
1,012.50 |
414.97 |
1,680.63 |
400.00 |
1,620.00 |
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
3.239 |
MILE |
300.00 |
971.70 |
300.00 |
971.70 |
350.00 |
1,133.65 |
0.01 |
0.03 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
6.424 |
MILE |
425.00 |
2,730.20 |
400.00 |
2,569.60 |
468.00 |
3,006.43 |
0.01 |
0.06 |
| 727-01 |
mobilization
|
lump |
LUMP |
73,500.00 |
73,500.00 |
45,000.00 |
45,000.00 |
65,000.00 |
65,000.00 |
75,000.00 |
75,000.00 |
| 731-02 |
reflectorized raised pavement markers
|
272   |
EACH |
5.50 |
1,496.00 |
5.00 |
1,360.00 |
6.05 |
1,645.60 |
5.50 |
1,496.00 |
| 732-01-C |
plastic pavement striping (8" width)
|
1,320   |
LNFT |
1.00 |
1,320.00 |
1.00 |
1,320.00 |
1.07 |
1,412.40 |
1.00 |
1,320.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
313   |
LNFT |
3.25 |
1,017.25 |
3.00 |
939.00 |
3.50 |
1,095.50 |
3.00 |
939.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.342 |
MILE |
2,750.00 |
6,440.50 |
3,000.00 |
7,026.00 |
3,094.51 |
7,247.34 |
3,000.00 |
7,026.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.079 |
MILE |
750.00 |
809.25 |
800.00 |
863.20 |
841.80 |
908.30 |
710.00 |
766.09 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
4   |
EACH |
190.00 |
760.00 |
200.00 |
800.00 |
207.49 |
829.96 |
200.00 |
800.00 |
| 732-04-E |
plastic pavement legends & symbols (school crossing)
|
2   |
EACH |
500.00 |
1,000.00 |
500.00 |
1,000.00 |
533.54 |
1,067.08 |
500.00 |
1,000.00 |
| 739-01 |
hydro-seeding
|
0.50 |
ACRE |
3,200.00 |
1,600.00 |
1,500.00 |
750.00 |
3,200.00 |
1,600.00 |
5,000.00 |
2,500.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
7,200.00 |
7,200.00 |
10,000.00 |
10,000.00 |
6,500.00 |
6,500.00 |
100.00 |
100.00 |
| 741-11 |
adjusting water valve and meter box
|
7   |
EACH |
800.00 |
5,600.00 |
600.00 |
4,200.00 |
900.00 |
6,300.00 |
1,000.00 |
7,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,065,709.70 |
|
1,298,811.36 |
|
1,304,271.58 |
|
1,391,634.88 |
|