| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - BARRIERE CONSTRUCTION CO., LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-B |
removal of concrete box culverts
|
1   |
EACH |
3,600.00 |
3,600.00 |
1,500.00 |
1,500.00 |
|
|
|
|
| 202-02-H |
removal of guard rail
|
186   |
LNFT |
16.00 |
2,976.00 |
7.00 |
1,302.00 |
|
|
|
|
| 203-07 |
borrow (vehicular measurement)
|
400   |
CUYD |
26.00 |
10,400.00 |
30.00 |
12,000.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
294   |
EACH |
10.00 |
2,940.00 |
9.50 |
2,793.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
1,424   |
LNFT |
1.75 |
2,492.00 |
1.65 |
2,349.60 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
20,254.0 |
TON |
84.50 |
1,711,463.00 |
90.00 |
1,822,860.00 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
2,118.1 |
TON |
120.00 |
254,172.00 |
1.00 |
2,118.10 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
170,787   |
SQYD |
1.00 |
170,787.00 |
2.80 |
478,203.60 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 6,207   |
CUYD |
0.10 |
- 620.70 |
10.00 |
- 62,070.00 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
2,547   |
SQYD |
90.00 |
229,230.00 |
70.00 |
178,290.00 |
|
|
|
|
| 510-03 |
pavement joint repair
|
358.3 |
TON |
225.00 |
80,617.50 |
50.00 |
17,915.00 |
|
|
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
2,534   |
LNFT |
2.30 |
5,828.20 |
3.00 |
7,602.00 |
|
|
|
|
| 602-03 |
cleaning and sealing random cracks
|
2,586   |
LNFT |
2.80 |
7,240.80 |
4.00 |
10,344.00 |
|
|
|
|
| 701-02-G |
cross drain pipe arch (42" equiv. cmpa)
|
66   |
LNFT |
190.00 |
12,540.00 |
400.00 |
26,400.00 |
|
|
|
|
| 701-06-G |
side drain pipe arch (42" equiv. cmpa)
|
22   |
LNFT |
180.00 |
3,960.00 |
400.00 |
8,800.00 |
|
|
|
|
| 701-08 |
relaying pipe
|
8   |
LNFT |
160.00 |
1,280.00 |
100.00 |
800.00 |
|
|
|
|
| 701-15 |
concrete collar
|
2   |
EACH |
775.00 |
1,550.00 |
2,500.00 |
5,000.00 |
|
|
|
|
| 704-01-B |
guard rail (single thrie beam)(6'-3" post spacing)
|
144.0 |
LNFT |
48.00 |
6,912.00 |
46.00 |
6,624.00 |
|
|
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
4   |
EACH |
2,600.00 |
10,400.00 |
2,500.00 |
10,000.00 |
|
|
|
|
| 706-01-C |
concrete walk (6" thick)
|
128.4 |
SQYD |
66.00 |
8,474.40 |
80.00 |
10,272.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
21,000.00 |
21,000.00 |
150,000.00 |
150,000.00 |
|
|
|
|
| 713-02-C |
temporary pavement markings (8" width)
|
1,160   |
LNFT |
0.30 |
348.00 |
0.30 |
348.00 |
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
456   |
LNFT |
0.90 |
410.40 |
0.90 |
410.40 |
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
35.260 |
MILE |
126.00 |
4,442.76 |
1.00 |
35.26 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
20.000 |
MILE |
250.00 |
5,000.00 |
250.00 |
5,000.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
59.890 |
MILE |
395.00 |
23,656.55 |
400.00 |
23,956.00 |
|
|
|
|
| 713-05-D |
temporary pavement legends and symbols (rr crossing)
|
2   |
EACH |
100.00 |
200.00 |
100.00 |
200.00 |
|
|
|
|
| 726-01 |
bedding material
|
27.6 |
CUYD |
80.00 |
2,208.00 |
100.00 |
2,760.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
75,000.00 |
75,000.00 |
300,000.00 |
300,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
43   |
EACH |
77.00 |
3,311.00 |
70.00 |
3,010.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
1,544   |
EACH |
5.00 |
7,720.00 |
5.10 |
7,874.40 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
520   |
LNFT |
0.85 |
442.00 |
0.80 |
416.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
204   |
LNFT |
3.00 |
612.00 |
3.00 |
612.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
28.380 |
MILE |
2,500.00 |
70,950.00 |
2,500.00 |
70,950.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
9.730 |
MILE |
700.00 |
6,811.00 |
700.00 |
6,811.00 |
|
|
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
1   |
EACH |
410.00 |
410.00 |
400.00 |
400.00 |
|
|
|
|
| 735-01 |
mailboxes
|
118   |
EACH |
1.00 |
118.00 |
1.00 |
118.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
112   |
EACH |
90.00 |
10,080.00 |
90.00 |
10,080.00 |
|
|
|
|
| 735-04 |
mailbox supports (multiple)
|
1   |
EACH |
205.00 |
205.00 |
1.00 |
1.00 |
|
|
|
|
| 736-09 |
loop detector
|
1,584   |
LNFT |
13.00 |
20,592.00 |
15.00 |
23,760.00 |
|
|
|
|
| 736-10 |
underground junction box
|
5   |
EACH |
300.00 |
1,500.00 |
300.00 |
1,500.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
1.21 |
ACRE |
1,150.00 |
1,391.50 |
2,000.00 |
2,420.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
20,000.00 |
20,000.00 |
104,500.00 |
104,500.00 |
|
|
|
|
| S-001 |
cleaning existing ditches
|
600   |
LNFT |
3.10 |
1,860.00 |
10.00 |
6,000.00 |
|
|
|
|
| S-002 |
u-channel post installation
|
113   |
EACH |
52.00 |
5,876.00 |
50.00 |
5,650.00 |
|
|
|
|
| S-003 |
sawcuts in asphaltic concrete lifts
|
2,534   |
LNFT |
1.30 |
3,294.20 |
1.00 |
2,534.00 |
|
|
|
|
| S-004 |
sawing and sealing transverse joints in asphaltic
concrete overlay |
2,534   |
LNFT |
1.80 |
4,561.20 |
3.00 |
7,602.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
2,818,241.81 |
|
3,280,051.36 |
|
|
|
|
|