| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - D & J CONSTRUCTION CO., INC. |
- 2 - AMETHYST CONSTRUCTION, INC. |
- 3 - INTERSTATE IMPROVEMENT, INC. |
- 4 - DIAMOND B CONSTRUCTION CO., L.L.C. |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
208   |
LNFT |
5.00 |
1,040.00 |
8.00 |
1,664.00 |
20.00 |
4,160.00 |
20.00 |
4,160.00 |
| 502-01 |
superpave asphaltic concrete
|
1,126.8 |
TON |
155.00 |
174,654.00 |
170.00 |
191,556.00 |
140.00 |
157,752.00 |
140.00 |
157,752.00 |
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
94.8 |
TON |
155.00 |
14,694.00 |
170.00 |
16,116.00 |
225.00 |
21,330.00 |
225.00 |
21,330.00 |
| 509-01 |
cold planing asphaltic pavement
|
6,829   |
SQYD |
3.00 |
20,487.00 |
3.00 |
20,487.00 |
4.00 |
27,316.00 |
4.00 |
27,316.00 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 569   |
CUYD |
0.01 |
- 5.69 |
0.01 |
- 5.69 |
0.01 |
- 5.69 |
0.10 |
- 56.90 |
| 510-03 |
pavement joint repair
|
50.0 |
TON |
250.00 |
12,500.00 |
250.00 |
12,500.00 |
255.00 |
12,750.00 |
255.00 |
12,750.00 |
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
9,138   |
LNFT |
1.65 |
15,077.70 |
1.30 |
11,879.40 |
3.00 |
27,414.00 |
1.45 |
13,250.10 |
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
3,672   |
LNFT |
2.00 |
7,344.00 |
1.55 |
5,691.60 |
3.00 |
11,016.00 |
1.65 |
6,058.80 |
| 602-05-I-01 |
full depth patching of jointed conc pvmt (9" thick)
(16.0 sq yds & under) |
416.0 |
SQYD |
175.00 |
72,800.00 |
210.00 |
87,360.00 |
319.00 |
132,704.00 |
175.00 |
72,800.00 |
| 602-05-I-02 |
full depth patching of jointed conc pvmt (9" thick)
(16.1 - 48.0 sq yds) |
316.0 |
SQYD |
170.00 |
53,720.00 |
180.00 |
56,880.00 |
319.00 |
100,804.00 |
165.00 |
52,140.00 |
| 602-05-I-03 |
full depth patching of jointed conc pvmt (9" thick)
(48.1 sq yds & over) |
172.0 |
SQYD |
140.00 |
24,080.00 |
180.00 |
30,960.00 |
319.00 |
54,868.00 |
135.00 |
23,220.00 |
| 702-04-A |
adjusting manholes
|
16   |
EACH |
1,700.00 |
27,200.00 |
2,000.00 |
32,000.00 |
2,000.00 |
32,000.00 |
1,650.00 |
26,400.00 |
| 704-03 |
blocked out guard rail
|
75.0 |
LNFT |
32.00 |
2,400.00 |
30.00 |
2,250.00 |
24.00 |
1,800.00 |
33.00 |
2,475.00 |
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
25.0 |
LNFT |
60.00 |
1,500.00 |
55.00 |
1,375.00 |
60.00 |
1,500.00 |
60.00 |
1,500.00 |
| 704-08-B |
guard rail transitions (double thrie beam)
|
50.0 |
LNFT |
70.00 |
3,500.00 |
65.00 |
3,250.00 |
60.00 |
3,000.00 |
70.00 |
3,500.00 |
| 704-11-A |
guard rail end treatment (flared)
|
2   |
EACH |
2,800.00 |
5,600.00 |
2,750.00 |
5,500.00 |
2,400.00 |
4,800.00 |
3,000.00 |
6,000.00 |
| 707-03 |
combination concrete curb & gutter
|
100.0 |
LNFT |
50.00 |
5,000.00 |
60.00 |
6,000.00 |
25.00 |
2,500.00 |
28.00 |
2,800.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
32,000.00 |
32,000.00 |
25,000.00 |
25,000.00 |
30,000.00 |
30,000.00 |
100,000.00 |
100,000.00 |
| 713-02-C |
temporary pavement markings (8" width)
|
1,113   |
LNFT |
1.55 |
1,725.15 |
1.50 |
1,669.50 |
0.50 |
556.50 |
0.65 |
723.45 |
| 713-02-E |
temporary pavement markings (24" width)
|
222   |
LNFT |
2.55 |
566.10 |
2.50 |
555.00 |
1.50 |
333.00 |
2.00 |
444.00 |
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
0.944 |
MILE |
250.00 |
236.00 |
2,000.00 |
1,888.00 |
1,500.00 |
1,416.00 |
200.00 |
188.80 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
3.237 |
MILE |
360.00 |
1,165.32 |
350.00 |
1,132.95 |
1,500.00 |
4,855.50 |
2,000.00 |
6,474.00 |
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
12   |
EACH |
100.00 |
1,200.00 |
100.00 |
1,200.00 |
100.00 |
1,200.00 |
130.00 |
1,560.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
28,000.00 |
28,000.00 |
30,000.00 |
30,000.00 |
90,000.00 |
90,000.00 |
100,000.00 |
100,000.00 |
| 729-16-C |
object marker assembly (type 3)
|
2   |
EACH |
100.00 |
200.00 |
80.00 |
160.00 |
110.00 |
220.00 |
100.00 |
200.00 |
| 731-02 |
reflectorized raised pavement markers
|
209   |
EACH |
9.00 |
1,881.00 |
8.50 |
1,776.50 |
6.00 |
1,254.00 |
8.00 |
1,672.00 |
| 732-01-C |
plastic pavement striping (8" width)
|
461   |
LNFT |
5.00 |
2,305.00 |
4.50 |
2,074.50 |
1.00 |
461.00 |
1.35 |
622.35 |
| 732-01-E |
plastic pavement striping (24" width)
|
74   |
LNFT |
15.00 |
1,110.00 |
13.00 |
962.00 |
3.00 |
222.00 |
4.00 |
296.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
5.772 |
MILE |
2,850.00 |
16,450.20 |
2,800.00 |
16,161.60 |
4,000.00 |
23,088.00 |
5,000.00 |
28,860.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.267 |
MILE |
1,400.00 |
1,773.80 |
1,400.00 |
1,773.80 |
1,500.00 |
1,900.50 |
2,000.00 |
2,534.00 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
6   |
EACH |
300.00 |
1,800.00 |
300.00 |
1,800.00 |
300.00 |
1,800.00 |
400.00 |
2,400.00 |
| 732-05 |
removal of existing markings
|
3.802 |
MILE |
6,500.00 |
24,713.00 |
6,500.00 |
24,713.00 |
10,000.00 |
38,020.00 |
12,000.00 |
45,624.00 |
| 736-09 |
loop detector
|
360   |
LNFT |
15.00 |
5,400.00 |
15.00 |
5,400.00 |
14.00 |
5,040.00 |
23.00 |
8,280.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
2,300.00 |
2,300.00 |
2,500.00 |
2,500.00 |
30,000.00 |
30,000.00 |
40,000.00 |
40,000.00 |
| 741-11 |
adjusting water valve and meter box
|
8   |
EACH |
950.00 |
7,600.00 |
1,000.00 |
8,000.00 |
500.00 |
4,000.00 |
898.22 |
7,185.76 |
| S-001 |
catch basin modification
|
49   |
EACH |
2,800.00 |
137,200.00 |
3,500.00 |
171,500.00 |
2,000.00 |
98,000.00 |
6,500.00 |
318,500.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
709,216.58 |
|
783,730.16 |
|
928,074.81 |
|
1,098,959.36 |
|